ASTM E2813-18
(Practice)Standard Practice for Building Enclosure Commissioning
Standard Practice for Building Enclosure Commissioning
SIGNIFICANCE AND USE
6.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that is based upon:
6.1.1 The Owner Project Requirements;
6.1.2 Clearly defined and enforceable levels of BECx; and
6.1.3 Minimum core competencies required of the BECxP and associated service-providers28 (see 4.2) to qualify as Fundamental or Enhanced BECx under this practice.
6.2 This practice is suitable for use as an independently applied standard for new buildings and structures, or as part of a more broadly based Total (or “Whole”) Building Commissioning Program.
SCOPE
1.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that establishes two levels of BECx: Fundamental and Enhanced (refer also to Section 4).
1.2 The BECx process as defined in this practice includes the following phases and sub-phases:
1.2.1 Pre-design,
1.2.2 Design,
1.2.2.1 Schematic Design,
1.2.2.2 Design Development,
1.2.2.3 Construction Documentation,
1.2.3 Bidding and Negotiation Phase,
1.2.4 Construction,
1.2.4.1 Pre-Construction,
1.2.4.2 Construction Administration, and
1.2.5 Occupancy and Operations.
1.3 This practice includes a mandatory OPR Development Guideline (Annex A1) and requires the development of an OPR for both Fundamental and Enhanced BECx that addresses, at a minimum, the performance attributes and metrics included in Annex A1 of this practice.
1.4 This practice includes mandatory BECx Performance Testing Requirements (Annex A2) approved for use with this practice to evaluate the performance and durability of enclosure materials, components, systems, and assemblies.
1.5 This practice mandates independent design review during the Design Phase of both Fundamental and Enhanced BECx.
1.6 This practice recognizes that the OPR for exterior enclosure performance and environmental separation may exceed the baseline requirements of applicable building codes and standards and provides guidance for the development of an OPR based on the following attributes as defined in Annex A1 of this practice:
1.6.1 Energy,
1.6.2 Environment,
1.6.3 Safety,
1.6.4 Security,
1.6.5 Durability,
1.6.6 Sustainability, and
1.6.7 Operation.
1.7 The terms “building enclosure” and “enclosure” as they appear in this practice refer collectively to all materials, components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or between two or more environmentally distinct interior spaces in a building or structure.
1.8 This practice establishes that the Building Enclosure Commissioning Provider (BECxP) refers specifically to the individual retained by the Owner to develop, manage, and be in responsible charge of the BECx process, including individual members and technical specialists that may comprise the BECx group (see 4.2).
1.9 The role and responsibilities of the BECxP as defined by this practice are not intended to supersede or otherwise replace the contractual obligations reserved specifically for the parties responsible for the design and construction of a building or structure, nor the duties that may otherwise be assigned to those parties by applicable regulatory or statutory law.
1.10 This practice is not intended to warrant or otherwise guarantee the as-built or in-service durability, or both, and performance of enclosure materials, components, systems, and assemblies.
1.11 The values stated in SI units are to be regarded as standard. The values given in parentheses are mathematical conversions to inch-pound units that are provided for information only and are not considered standard.
1.12 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to e...
General Information
- Status
- Published
- Publication Date
- 30-Sep-2018
- Technical Committee
- E06 - Performance of Buildings
- Drafting Committee
- E06.55 - Performance of Building Enclosures
Relations
- Effective Date
- 01-Oct-2018
- Refers
ASTM E2357-24 - Standard Test Method for Determining Air Leakage Rate of Air Barrier Assemblies - Effective Date
- 01-Jan-2024
- Effective Date
- 01-Dec-2023
- Effective Date
- 01-Nov-2023
- Effective Date
- 01-Oct-2023
- Effective Date
- 01-Sep-2023
- Effective Date
- 01-Aug-2020
- Effective Date
- 01-May-2020
- Effective Date
- 01-May-2020
- Effective Date
- 15-Feb-2020
- Effective Date
- 01-Dec-2019
- Effective Date
- 01-Oct-2019
- Effective Date
- 01-Oct-2019
- Effective Date
- 01-Oct-2019
- Effective Date
- 01-Aug-2019
Overview
ASTM E2813-18: Standard Practice for Building Enclosure Commissioning is an authoritative guideline developed by ASTM International to provide a framework for the systematic commissioning of building enclosures. Building Enclosure Commissioning (BECx) is a quality-focused process that begins with clear Owner Project Requirements (OPR) and carries through project design, construction, and operation. This standard distinguishes between Fundamental and Enhanced BECx, ensuring robust methods and minimum competencies for service providers. ASTM E2813-18 is suitable for new buildings and structures or can form part of a broader whole-building commissioning program.
Key Topics
- Owner Project Requirements (OPR): Establishes the necessity for a written OPR, addressing essential attributes such as energy performance, environmental separation, durability, safety, and sustainability.
- Two Levels of BECx:
- Fundamental BECx involves essential services, peer reviews, and performance testing.
- Enhanced BECx provides a more rigorous process, including additional peer reviews and early engagement.
- Core Competencies: Specifies the required knowledge areas for Building Enclosure Commissioning Providers (BECxP) and teams, such as building science, procurement, construction administration, and performance testing.
- Commissioning Phases: Outlines phases and sub-phases, including pre-design, design (schematic through construction documents), bidding/negotiation, construction (pre-construction and administration), and occupancy/operations.
- Performance Testing Requirements: Mandates laboratory and field testing of enclosure materials, components, systems, and assemblies to confirm compliance with OPR and contract documents.
- Independent Peer Review: Requires third-party review during design for both Fundamental and Enhanced BECx.
- Integration with Other Standards: Recommends the use of ASHRAE 202 and ASTM E2947 for optimal implementation.
Applications
ASTM E2813-18 serves as a foundation for:
- Commissioning New Buildings: Ensures the building envelope (walls, windows, doors, roofs, etc.) meets functional and performance goals from the outset.
- Quality Assurance in Construction: Identifies and verifies compliance with project requirements through systematic review and testing.
- Operational Readiness: Provides protocols for verifying that enclosure systems perform as intended post-construction, supporting sustainability, durability, and occupant comfort.
- Risk Mitigation: Early identification of potential issues through independent design review and performance testing reduces the risk of costly rework or failures.
- LEED and Green Building Projects: Supports documentation and practices needed for green building certifications that include building envelope commissioning credits.
- Integration into Whole-Building Commissioning: Can be applied independently or as part of comprehensive asset management and building performance programs.
Related Standards
For best results, ASTM E2813-18 should be used in conjunction with related standards and references, including:
- ASHRAE Standard 202 – Commissioning Process for Buildings and Systems
- ASTM E2947 – Guide for Building Enclosure Commissioning
- ASHRAE 90.1 – Energy Standard for Buildings Except Low-Rise Residential Buildings
- NFRC 100/200/300 Series – Fenestration Product Ratings
- AAMA 501 Series – Window, Door, Curtain Wall Testing Methods
- International Building Code (IBC)
- Numerous ASTM test methods for air leakage, water penetration, acoustic performance, material compatibility, and structural performance
Practical Value
Adhering to ASTM E2813-18 ensures a methodical, consistent process for building enclosure commissioning, which safeguards investments, enhances building performance, and contributes to occupant well-being. By mandating clear owner requirements, performance metrics, and robust third-party review, this standard minimizes risks and facilitates compliance with evolving energy codes and sustainability objectives. Facility owners, designers, constructors, and commissioning professionals will find ASTM E2813-18 an indispensable resource for delivering high-quality, durable building enclosures.
Buy Documents
ASTM E2813-18 - Standard Practice for Building Enclosure Commissioning
REDLINE ASTM E2813-18 - Standard Practice for Building Enclosure Commissioning
Get Certified
Connect with accredited certification bodies for this standard

ICC Evaluation Service
Building products evaluation and certification.

QAI Laboratories
Building and construction product testing and certification.

Aboma Certification B.V.
Specialized in construction, metal, and transport sectors.
Sponsored listings
Frequently Asked Questions
ASTM E2813-18 is a standard published by ASTM International. Its full title is "Standard Practice for Building Enclosure Commissioning". This standard covers: SIGNIFICANCE AND USE 6.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that is based upon: 6.1.1 The Owner Project Requirements; 6.1.2 Clearly defined and enforceable levels of BECx; and 6.1.3 Minimum core competencies required of the BECxP and associated service-providers28 (see 4.2) to qualify as Fundamental or Enhanced BECx under this practice. 6.2 This practice is suitable for use as an independently applied standard for new buildings and structures, or as part of a more broadly based Total (or “Whole”) Building Commissioning Program. SCOPE 1.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that establishes two levels of BECx: Fundamental and Enhanced (refer also to Section 4). 1.2 The BECx process as defined in this practice includes the following phases and sub-phases: 1.2.1 Pre-design, 1.2.2 Design, 1.2.2.1 Schematic Design, 1.2.2.2 Design Development, 1.2.2.3 Construction Documentation, 1.2.3 Bidding and Negotiation Phase, 1.2.4 Construction, 1.2.4.1 Pre-Construction, 1.2.4.2 Construction Administration, and 1.2.5 Occupancy and Operations. 1.3 This practice includes a mandatory OPR Development Guideline (Annex A1) and requires the development of an OPR for both Fundamental and Enhanced BECx that addresses, at a minimum, the performance attributes and metrics included in Annex A1 of this practice. 1.4 This practice includes mandatory BECx Performance Testing Requirements (Annex A2) approved for use with this practice to evaluate the performance and durability of enclosure materials, components, systems, and assemblies. 1.5 This practice mandates independent design review during the Design Phase of both Fundamental and Enhanced BECx. 1.6 This practice recognizes that the OPR for exterior enclosure performance and environmental separation may exceed the baseline requirements of applicable building codes and standards and provides guidance for the development of an OPR based on the following attributes as defined in Annex A1 of this practice: 1.6.1 Energy, 1.6.2 Environment, 1.6.3 Safety, 1.6.4 Security, 1.6.5 Durability, 1.6.6 Sustainability, and 1.6.7 Operation. 1.7 The terms “building enclosure” and “enclosure” as they appear in this practice refer collectively to all materials, components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or between two or more environmentally distinct interior spaces in a building or structure. 1.8 This practice establishes that the Building Enclosure Commissioning Provider (BECxP) refers specifically to the individual retained by the Owner to develop, manage, and be in responsible charge of the BECx process, including individual members and technical specialists that may comprise the BECx group (see 4.2). 1.9 The role and responsibilities of the BECxP as defined by this practice are not intended to supersede or otherwise replace the contractual obligations reserved specifically for the parties responsible for the design and construction of a building or structure, nor the duties that may otherwise be assigned to those parties by applicable regulatory or statutory law. 1.10 This practice is not intended to warrant or otherwise guarantee the as-built or in-service durability, or both, and performance of enclosure materials, components, systems, and assemblies. 1.11 The values stated in SI units are to be regarded as standard. The values given in parentheses are mathematical conversions to inch-pound units that are provided for information only and are not considered standard. 1.12 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to e...
SIGNIFICANCE AND USE 6.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that is based upon: 6.1.1 The Owner Project Requirements; 6.1.2 Clearly defined and enforceable levels of BECx; and 6.1.3 Minimum core competencies required of the BECxP and associated service-providers28 (see 4.2) to qualify as Fundamental or Enhanced BECx under this practice. 6.2 This practice is suitable for use as an independently applied standard for new buildings and structures, or as part of a more broadly based Total (or “Whole”) Building Commissioning Program. SCOPE 1.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure Commissioning (BECx) that establishes two levels of BECx: Fundamental and Enhanced (refer also to Section 4). 1.2 The BECx process as defined in this practice includes the following phases and sub-phases: 1.2.1 Pre-design, 1.2.2 Design, 1.2.2.1 Schematic Design, 1.2.2.2 Design Development, 1.2.2.3 Construction Documentation, 1.2.3 Bidding and Negotiation Phase, 1.2.4 Construction, 1.2.4.1 Pre-Construction, 1.2.4.2 Construction Administration, and 1.2.5 Occupancy and Operations. 1.3 This practice includes a mandatory OPR Development Guideline (Annex A1) and requires the development of an OPR for both Fundamental and Enhanced BECx that addresses, at a minimum, the performance attributes and metrics included in Annex A1 of this practice. 1.4 This practice includes mandatory BECx Performance Testing Requirements (Annex A2) approved for use with this practice to evaluate the performance and durability of enclosure materials, components, systems, and assemblies. 1.5 This practice mandates independent design review during the Design Phase of both Fundamental and Enhanced BECx. 1.6 This practice recognizes that the OPR for exterior enclosure performance and environmental separation may exceed the baseline requirements of applicable building codes and standards and provides guidance for the development of an OPR based on the following attributes as defined in Annex A1 of this practice: 1.6.1 Energy, 1.6.2 Environment, 1.6.3 Safety, 1.6.4 Security, 1.6.5 Durability, 1.6.6 Sustainability, and 1.6.7 Operation. 1.7 The terms “building enclosure” and “enclosure” as they appear in this practice refer collectively to all materials, components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or between two or more environmentally distinct interior spaces in a building or structure. 1.8 This practice establishes that the Building Enclosure Commissioning Provider (BECxP) refers specifically to the individual retained by the Owner to develop, manage, and be in responsible charge of the BECx process, including individual members and technical specialists that may comprise the BECx group (see 4.2). 1.9 The role and responsibilities of the BECxP as defined by this practice are not intended to supersede or otherwise replace the contractual obligations reserved specifically for the parties responsible for the design and construction of a building or structure, nor the duties that may otherwise be assigned to those parties by applicable regulatory or statutory law. 1.10 This practice is not intended to warrant or otherwise guarantee the as-built or in-service durability, or both, and performance of enclosure materials, components, systems, and assemblies. 1.11 The values stated in SI units are to be regarded as standard. The values given in parentheses are mathematical conversions to inch-pound units that are provided for information only and are not considered standard. 1.12 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to e...
ASTM E2813-18 is classified under the following ICS (International Classification for Standards) categories: 91.010.99 - Other aspects; 91.040.01 - Buildings in general; 91.060.01 - Elements of buildings in general. The ICS classification helps identify the subject area and facilitates finding related standards.
ASTM E2813-18 has the following relationships with other standards: It is inter standard links to ASTM E2813-12e1, ASTM E2357-24, ASTM E90-23, ASTM C1279-23, ASTM E2359/E2359M-13(2023), ASTM C1153-23, ASTM C724-91(2020), ASTM C1294-20, ASTM E576-14(2020), ASTM E2649-20, ASTM F2170-19a, ASTM E336-19a, ASTM E1050-19, ASTM E1886-19, ASTM C1279-13(2019). Understanding these relationships helps ensure you are using the most current and applicable version of the standard.
ASTM E2813-18 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.
Standards Content (Sample)
This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the
Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
Designation: E2813 − 18
Standard Practice for
Building Enclosure Commissioning
This standard is issued under the fixed designation E2813; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
INTRODUCTION
Building Enclosure Commissioning (BECx) is a process that begins with the establishment of the
Owner’s Project Requirements (OPR) and endeavors to confirm that the exterior enclosure and those
elements intended to provide environmental separation within a building or structure meet or exceed
the expectations of the Owner as described in the OPR, and as defined by the contract documents.A
fundamental understanding of the most current published edition of ANSI/ASHRAE/IES Standard
202, Commissioning Process for Buildings and Systems and ASTM E2947, Standard Guide for
Building Enclosure Commissioning is recommended for optimal use and application of this practice.
1. Scope 1.5 This practice mandates independent design review dur-
ing the Design Phase of both Fundamental and Enhanced
1.1 This practice is intended to serve as a concise,
BECx.
authoritative, and technically sound practice for Building
Enclosure Commissioning (BECx) that establishes two levels
1.6 This practice recognizes that the OPR for exterior
ofBECx: Fundamentaland Enhanced(referalsotoSection4).
enclosure performance and environmental separation may
exceed the baseline requirements of applicable building codes
1.2 The BECx process as defined in this practice includes
andstandardsandprovidesguidanceforthedevelopmentofan
the following phases and sub-phases:
OPR based on the following attributes as defined in AnnexA1
1.2.1 Pre-design,
of this practice:
1.2.2 Design,
1.6.1 Energy,
1.2.2.1 Schematic Design,
1.6.2 Environment,
1.2.2.2 Design Development,
1.2.2.3 Construction Documentation, 1.6.3 Safety,
1.2.3 Bidding and Negotiation Phase,
1.6.4 Security,
1.2.4 Construction,
1.6.5 Durability,
1.2.4.1 Pre-Construction,
1.6.6 Sustainability, and
1.2.4.2 Construction Administration, and
1.6.7 Operation.
1.2.5 Occupancy and Operations.
1.7 The terms “building enclosure” and “enclosure” as they
1.3 This practice includes a mandatory OPR Development
appear in this practice refer collectively to all materials,
Guideline(AnnexA1)andrequiresthedevelopmentofanOPR
components, systems, and assemblies intended to provide
for both Fundamental and Enhanced BECx that addresses, at a
shelter and environmental separation between interior and
minimum, the performance attributes and metrics included in
exterior, or between two or more environmentally distinct
Annex A1 of this practice.
interior spaces in a building or structure.
1.4 This practice includes mandatory BECx Performance
1.8 This practice establishes that the Building Enclosure
Testing Requirements (Annex A2) approved for use with this
Commissioning Provider (BECxP) refers specifically to the
practice to evaluate the performance and durability of enclo-
individualretainedbytheOwnertodevelop,manage,andbein
sure materials, components, systems, and assemblies.
responsible charge of the BECx process, including individual
membersandtechnicalspecialiststhatmaycomprisetheBECx
group (see 4.2).
This practice is under the jurisdiction of ASTM Committee E06 on Perfor-
mance of Buildings and is the direct responsibility of Subcommittee E06.55 on
1.9 TheroleandresponsibilitiesoftheBECxPasdefinedby
Performance of Building Enclosures.
this practice are not intended to supersede or otherwise replace
Current edition approved Oct. 1, 2018. Published December 2018. Originally
ɛ1
the contractual obligations reserved specifically for the parties
approved in 2012. Last previous edition approved in 2012 as E2813–12 . DOI:
10.1520/E2813–18. responsible for the design and construction of a building or
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
E2813 − 18
structure, nor the duties that may otherwise be assigned to C1294 Test Method for Compatibility of Insulating Glass
those parties by applicable regulatory or statutory law. Edge Sealants with Liquid-Applied Glazing Materials
C1371 Test Method for Determination of Emittance of
1.10 This practice is not intended to warrant or otherwise
Materials Near Room Temperature Using Portable Emis-
guarantee the as-built or in-service durability, or both, and
someters
performance of enclosure materials, components, systems, and
C1522 Test Method for Extensibility After Heat Aging of
assemblies.
Cold Liquid-Applied Elastomeric Waterproofing Mem-
1.11 The values stated in SI units are to be regarded as
branes
standard. The values given in parentheses are mathematical
C1549 Test Method for Determination of Solar Reflectance
conversions to inch-pound units that are provided for informa-
NearAmbientTemperature Using a Portable Solar Reflec-
tion only and are not considered standard.
tometer
1.12 This standard does not purport to address all of the
C1601 Test Method for Field Determination of Water Pen-
safety concerns, if any, associated with its use. It is the
etration of Masonry Wall Surfaces
responsibility of the user of this standard to establish appro-
C1651 Test Method for Measurement of Roll Wave Optical
priate safety, health, and environmental practices and deter-
Distortion in Heat-Treated Flat Glass
mine the applicability of regulatory limitations prior to use.
C1652/C1652M Test Method for Measuring Optical Distor-
1.13 This international standard was developed in accor-
tion in Flat Glass Products Using Digital Photography of
dance with internationally recognized principles on standard-
Grids
ization established in the Decision on Principles for the
D2203 Test Method for Staining from Sealants
Development of International Standards, Guides and Recom-
D4541 Test Method for Pull-Off Strength of Coatings Using
mendations issued by the World Trade Organization Technical
Portable Adhesion Testers
Barriers to Trade (TBT) Committee.
D5957 Guide for Flood Testing Horizontal Waterproofing
Installations
2. Referenced Documents
E90 Test Method for Laboratory Measurement of Airborne
2.1 ASTM Standards:
Sound Transmission Loss of Building Partitions and
C423 TestMethodforSoundAbsorptionandSoundAbsorp-
Elements
tion Coefficients by the Reverberation Room Method
E283 Test Method for Determining Rate of Air Leakage
C510 Test Method for Staining and Color Change of Single-
Through Exterior Windows, Curtain Walls, and Doors
or Multicomponent Joint Sealants
Under Specified Pressure Differences Across the Speci-
C522 Test Method for Airflow Resistance of Acoustical
men
Materials
E330/E330M Test Method for Structural Performance of
C724 Test Method for Acid Resistance of Ceramic Decora-
Exterior Windows, Doors, Skylights and Curtain Walls by
tions on Architectural-Type Glass
Uniform Static Air Pressure Difference
C732 Test Method forAging Effects ofArtificialWeathering
E331 Test Method for Water Penetration of Exterior
on Latex Sealants
Windows, Skylights, Doors, and Curtain Walls by Uni-
C794 TestMethodforAdhesion-in-PeelofElastomericJoint
form Static Air Pressure Difference
Sealants
E336 Test Method for Measurement of Airborne Sound
C1060 Practice for Thermographic Inspection of Insulation
Attenuation between Rooms in Buildings
Installations in Envelope Cavities of Frame Buildings
E488/E488M Test Methods for Strength of Anchors in
C1087 Test Method for Determining Compatibility of
Concrete Elements
Liquid-Applied Sealants with Accessories Used in Struc-
E492 Test Method for Laboratory Measurement of Impact
tural Glazing Systems
Sound Transmission Through Floor-Ceiling Assemblies
C1153 Practice for Location of Wet Insulation in Roofing
Using the Tapping Machine
Systems Using Infrared Imaging
E514/E514M Test Method for Water Penetration and Leak-
C1193-11a Guide for Use of Joint Sealants
age Through Masonry
C1246 Test Method for Effects of Heat Aging on Weight
E576 Test Method for Frost/Dew Point of Sealed Insulating
Loss, Cracking, and Chalking of Elastomeric Sealants
Glass Units in the Vertical Position
After Cure
E596 Test Method for Laboratory Measurement of Noise
C1258 Test Method for Elevated Temperature and Humidity
Reduction of Sound-Isolating Enclosures
Resistance of Vapor Retarders for Insulation
E631 Terminology of Building Constructions
C1279 Test Method for Non-Destructive Photoelastic Mea-
E779 TestMethodforDeterminingAirLeakageRatebyFan
surement of Edge and Surface Stresses in Annealed,
Pressurization
Heat-Strengthened, and Fully Tempered Flat Glass
E783 Test Method for Field Measurement of Air Leakage
Through Installed Exterior Windows and Doors
E795 Practices for Mounting Test Specimens During Sound
For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Absorption Tests
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
E903 Test Method for Solar Absorptance, Reflectance, and
Standards volume information, refer to the standard’s Document Summary page on
the ASTM website. Transmittance of Materials Using Integrating Spheres
E2813 − 18
E966 Guide for Field Measurements of Airborne Sound E2359/E2359M Test Method for Field Pull Testing of an
Attenuation of Building Facades and Facade Elements In-Place Exterior Insulation and Finish System Clad Wall
Assembly
E997 Test Method for Evaluating Glass Breakage Probabil-
ity Under the Influence of Uniform Static Loads by Proof E2570/E2570M Test Methods for Evaluating Water-
Resistive Barrier (WRB) Coatings Used under Exterior
Load Testing
Insulation and Finish Systems (EIFS) or EIFS with
E1007 Test Method for Field Measurement of Tapping
Drainage
Machine Impact Sound Transmission Through Floor-
E2649 Test Method for DeterminingArgon Concentration in
Ceiling Assemblies and Associated Support Structures
Sealed Insulating Glass Units Using Spark Emission
E1014 Guide for Measurement of Outdoor A-Weighted
Spectroscopy
Sound Levels
E2947 Guide for Building Enclosure Commissioning
E1050 Test Method for Impedance and Absorption of
F1233 Test Method for Security Glazing Materials And
AcousticalMaterialsUsingaTube,TwoMicrophonesand
Systems
a Digital Frequency Analysis System
F1642/F1642M Test Method for Glazing and Glazing Sys-
E1105 Test Method for Field Determination of Water Pen-
tems Subject to Airblast Loadings
etration of Installed Exterior Windows, Skylights, Doors,
F1869 Test Method for Measuring MoistureVapor Emission
and Curtain Walls, by Uniform or Cyclic Static Air
Rate of Concrete Subfloor Using Anhydrous Calcium
Pressure Difference
Chloride
E1186 Practices for Air Leakage Site Detection in Building
F2170 Test Method for Determining Relative Humidity in
Envelopes and Air Barrier Systems
Concrete Floor Slabs Using in situ Probes
E1425 Practice for Determining theAcoustical Performance
F2420 Test Method for Determining Relative Humidity on
of Windows, Doors, Skylight, and Glazed Wall Systems
the Surface of Concrete Floor Slabs Using Relative
E1503 Test Method for Conducting Outdoor Sound Mea-
Humidity Probe Measurement and Insulated Hood (With-
surements Using a Digital Statistical Sound Analysis
drawn 2014)
System
2.2 AAMA Standards:
E1827 Test Methods for Determining Airtightness of Build-
AAMA501.1 StandardTestMethodforWaterPenetrationof
ings Using an Orifice Blower Door
Windows, Curtain Walls and Doors Using Dynamic Pres-
E1886 Test Method for Performance of Exterior Windows,
sure
Curtain Walls, Doors, and Impact Protective Systems
AAMA 501.2 Quality Assurance and Diagnostic Water
Impacted by Missile(s) and Exposed to Cyclic Pressure
Leakage Field Check of Installed Storefronts, Curtain
Differentials
Walls, and Sloped Glazing Systems
E1980 Practice for Calculating Solar Reflectance Index of
AAMA 501.4 Recommended Static Test Method for Evalu-
Horizontal and Low-Sloped Opaque Surfaces
ating Window Wall, Curtain Wall and Storefront Systems
E1996 Specification for Performance of Exterior Windows,
Subjected to Seismic and Wind-Induced Inter-Story Drift
Curtain Walls, Doors, and Impact Protective Systems
AAMA 501.5 Test Method for Thermal Cycling of Exterior
Impacted by Windborne Debris in Hurricanes
Walls
E2099 Practice for the Specification and Evaluation of
AAMA508-07 Voluntary Test Method and Specification for
Pre-Construction Laboratory Mockups of Exterior Wall
Pressure Equalized Rain Screen Wall Cladding Systems
Systems
AAMA 1503 Voluntary Test Method for Thermal Transmit-
E2178 TestMethodforAirPermeanceofBuildingMaterials
tance and Condensation Resistance of Windows, Doors,
E2179 Test Method for Laboratory Measurement of the
and Glazed Wall Sections
Effectiveness of Floor Coverings in Reducing Impact
AAMA 1801 Voluntary Specification for the Acoustical
Sound Transmission Through Concrete Floors
Rating of ExteriorWindows, Doors, Skylights and Glazed
E2249 Test Method for Laboratory Measurement of Air-
Wall Sections
borne Transmission Loss of Building Partitions and Ele-
2.3 ANSI Standards:
ments Using Sound Intensity
ANSI/ASA S12.8 Methods for Determination of Insertion
E2264 Practice for Determining the Effects of Temperature
Loss of Outdoor Noise Barriers
Cycling on Fenestration Products
ANSI/ASAS12.60 Acoustical Performance Criteria, Design
E2268 Test Method for Water Penetration of Exterior
Requirements, and Guidelines for Schools
Windows, Skylights, and Doors by Rapid Pulsed Air
ANSI/ASHRAE/IES 90.1 Energy Standard for Buildings
Pressure Difference
Except Low-Rise Residential Buildings (Map of Climate
E2319 Test Method for Determining Air Flow Through the
Zones)
Face and Sides of Exterior Windows, Curtain Walls, and
Doors Under Specified Pressure Differences Across the
The last approved version of this historical standard is referenced on
Specimen
www.astm.org.
Available from American Architectural Manufacturers Association (AAMA),
E2353 Test Methods for Performance of Glazing in Perma-
1827 Walden Office Square, Suite 550, Schaumburg, Illinois 60173-4268, http://
nent Railing Systems, Guards, and Balustrades
www.aamanet.org.
E2357 TestMethodforDeterminingAirLeakageRateofAir
Available fromAmerican National Standards Institute (ANSI), 25 W. 43rd St.,
Barrier Assemblies 4th Floor, New York, NY 10036, http://www.ansi.org.
E2813 − 18
ANSI/ASHRAE/IES Standard 101 Application of Infrared 2.13 NIJ Standard:
Sensing Devices to theAssessment of Building Heat Loss NIJ Std. 0108.01 Ballistic Resistant Protective Materials
Characteristics
2.14 State Department (SD) Ballistic Standard:
ANSI/ASHRAE/IES Standard 202 Commissioning Process
SD-STD-01.01 Forced Entry and Ballistic Resistance of
for Buildings and Systems
Structural Systems
2.4 CAN/CGSB Standard:
2.15 UL Standard:
CAN/CGSB 149-GP-2MP Manual for Thermographic
UL 752 Standard of Safety for Bullet-Resisting Equipment
Analysis of Building Enclosures
3. Terminology
2.5 CEN Standard:
CEN 1063 Glass in building - Security glazing - Testing and
3.1 Definitions—Refer to the most current edition of the
classification of resistance against bullet attack
following:
3.1.1 ANSI/ASHRAE/IES Standard 202, Section 3, Defini-
2.6 CSA Standard:
tions
CSA-A123.21 Standard Test Method for the Dynamic Wind
3.1.2 Guide E2947
Uplift Resistance of Membrane-Roofing Systems
9 3.1.3 Terminology E631
2.7 CSI Standard:
3.1.4 AIAArchitect’s Handbook of Professional Practice
Project Resource Manual and Manual of Practice
3.1.5 CSI Project Resource Manual and Manual of Practice
2.8 GANA Test Methods:
3.2 Acronyms:
GANA LD 100-06 Standard Test Method for Ball Drop
3.2.1 AAMA—American Architectural Manufacturers Asso-
Impact of Laminated Architectural Flat Glass
ciation
GANA TD 101-04 Standard Test Method for Center-Punch
Fragmentation of Fully-Tempered Flat Glass
3.2.2 A/E—Architect/Engineer
GANA LD 101-08 Standard Specification for Ball Drop
3.2.3 AIA—American Institute of Architects
Impact Resistance of Laminated Architectural Flat Glaz-
3.2.4 ANSI—American National Standards Institute
ing
3.2.5 AOR—Architect-of-Record
2.9 GSA Standard:
3.2.6 ASCE—American Society of Civil Engineers
GSA-TS01 Standard Test Method for Glazing and Window
Systems Subject to Dynamic Overpressure Loadings
3.2.7 ASHRAE—American Society of Heating, Refrigerat-
ing and Air Conditioning Engineers
2.10 ICC Publication:
International Building Code
3.2.8 BCA—Building Commissioning Association
2.11 ISO Publication:
3.2.9 BECx—Building Enclosure Commissioning
ISO 9000
3.2.10 BECxG—Building Enclosure Commissioning Group
2.12 NFRC Standards:
3.2.11 BECxP—Building Enclosure Commissioning Pro-
NFRC 100 Procedure for Determining Fenestration Product
vider (aka “Agent” or “Authority”)
U-Factors
3.2.12 BOD—Building Enclosure Basis-of-Design
NFRC 200 Procedure for Determining Fenestration Product
Solar Heat Gain Coefficient and Visible Transmittance at
3.2.13 CAN/CGSB—Canadian General Standards Board
Normal Incidence
3.2.14 CSA—Canadian Standards Association
NFRC 300 Test Method for Determining the Solar Optical
3.2.15 CSI—Construction Specifications Institute
Properties of Glazing Materials and Systems
3.2.16 Cx—Commissioning
3.2.17 CxP—Commissioning Provider
Available from Canadian General Standards Board (CGSB), 11 Laurier St.,
3.2.18 EIS—Energy Information System
Phase III, Place du Portage, Gatineau, Quebec K1A0S5, Canada, http://www.tpsgc-
pwgsc.gc.ca/ongc-cgsb/index-eng.html.
3.2.19 EMCS—Energy Management and Control System
Available from European Committee for Standardization (CEN), Avenue
3.2.20 EOR—Engineer-of-Record
Marnix 17, B-1000, Brussels, Belgium, http://www.cen.eu.
Available from Canadian Standards Association (CSA), 178 Rexdale Blvd.,
3.2.21 GANA—Glass Association of North America
Toronto, ON M9W 1R3, Canada, http://www.csagroup.org.
AvailablefromConstructionSpecificationsInstitute(CSI),110S.UnionStreet,
Suite 100, Alexandria VA 22314, http://www.csiresources.org.
10 15
AvailablefromGlassAssociationofNorthAmerica(GANA),800SWJackson Available from National Institute of Justice (NIJ), 810 7th St., NW,
St., Suite 1500, Topeka, KS 66612-1200, http://www.glasswebsite.com. Washington, DC 20531, http://nij.gov.
11 16
Available from U.S. General Services Administration (GSA), 1800 F Street, Available from U.S. Government Publishing Office (GPO), 732 N. Capitol St.,
NW, Washington, DC 20405, http://www.gsa.gov. NW, Washington, DC 20401-0001, http://www.gpo.gov.
12 17
Available from International Code Council (ICC), 500 New JerseyAve., NW, Available from Underwriters Laboratories (UL), 2600 N.W. Lake Rd., Camas,
6th Floor, Washington, DC 20001, http://www.iccsafe.org. WA 98607-8542, http://www.ul.com.
13 18
Available from International Organization for Standardization (ISO), ISO Selection, interpretation, application, and use of the terminology contained in
Central Secretariat, BIBC II, Chemin de Blandonnet 8, CP 401, 1214 Vernier, these documents shall be at the sole discretion of the BECxP. Reconciliation of
Geneva, Switzerland, http://www.iso.org. conflicts in terminology or the definition of terms that may exist among or between
Available from National Fenestration Rating Council (NFRC), 6305 Ivy Ln., thesedocumentsshallbethesoleresponsibilityoftheBECxP,subjecttoreviewand
Suite 140, Greenbelt, MD 20770, http://www.nfrc.org. final approval by the AOR and Owner.
E2813 − 18
3.2.22 GSA—United States General Services Administra- mum of one independent design review of enclosure-related
tion constructiondocumentdrawingsandspecificationsinamanner
thatwillallowfortimelyreviewandconsiderationbytheAOR
3.2.23 HVAC—Heating, Ventilation, and Air Conditioning
prior to solicitation and contract award. The project-specific
3.2.24 IAQ—Indoor Air Quality
BECx specification section establishes the roles and responsi-
3.2.25 IEQ—Indoor Environmental Quality
bilities of the contractor and individual members of the
construction team in the context of the BECx process, includ-
3.2.26 LEED—Leadership in Energy and Environmental
Design (trademark ) ing a summary of required pre-construction laboratory and
field performance test standards and methodology for
3.2.27 NASFA—NationalAssociation of State FacilitiesAd-
enclosure-related materials, components, systems, and assem-
ministrators
blies required by AnnexA2 of this practice and further defined
3.2.28 NEBB—National Environmental Balancing Bureau
by the AOR in the construction documents;
3.2.29 NIBS—National Institute of Building Sciences
4.1.1.5 DocumentafinalBECxPlanthatincludesanoutline
of the BECx process, BECx roles and responsibilities of the
3.2.30 NFRC—National Fenestration Rating Council
BECxP, individual members of the BECx group, the Design
3.2.31 O&M—Operations and Maintenance
Team, the Construction Team, and the methodology estab-
3.2.32 OPR—Building Enclosure Owner’s Project Require-
lished to verify and document compliance of the as-built
ments
construction with the requirements of the approved contract
3.2.33 RCx—Retro-Commissioning
documents. The BECx Plan shall be developed to align with
the requirements of the BECx section of the project specifica-
3.2.34 ReCx—Re-Commissioning
tions;
3.2.35 RFI—Request For Information
4.1.1.6 Direct and substantive participation by the BECxP
3.2.36 USDHS (or DHS)—U.S. Department of Homeland
during the Bidding and Negotiation, Pre-Construction, Con-
Security
structionAdministration, and Occupancy & Operations phases
3.2.37 USDOD (or DOD)—U.S. Department of Defense
oftheBECxprocess,includingpre-constructionlaboratoryand
field performance testing as required in Annex A2 for Funda-
3.2.38 USDOE (or DOE)—U.S. Department of Energy
mental BECx.
3.2.39 USDOS (or DOS)—U.S. Department of State
4.1.2 Enhanced BECx—Architecture or engineering-related
3.2.40 USGBC—U.S. Green Building Council
technical services, or both, performed on behalf of the Owner
3.2.41 VA—U.S. Department of Veterans Affairs
by the BECxP and associated BECx group members in
accordance with the requirements of Fundamental BECx, but
4. Summary of Practice
with the following additional requirements:
4.1 This practice establishes two levels of BECx: Funda-
4.1.2.1 BECxPengagement during the Pre-Design Phase of
mental and Enhanced.
the BECx process, but no later than commencement of the
4.1.1 Fundamental BECx—Architecture or engineering-
Schematic Design sub-phase;
related technical services, or both, performed on behalf of the
4.1.2.2 Technical assistance and documentation during the
Owner by the BECxP and associated group members and
development of the preliminary OPR;
summarized as follows:
4.1.2.3 Technical assistance and documentation during the
4.1.1.1 BECxP engagement during the Design Phase of the
development of the BOD, contract documents, including the
BECx process, but no later than commencement of the Design
project-specific BECx specification section, and final OPR
Development sub-phase;
during the Design Phase of the BECx process, including
4.1.1.2 Review and documentation of the preliminary OPR
completion of a minimum of three independent design re-
developedduringthePre-DesignPhaseoftheBECxprocess;
views of enclosure-related construction document drawings
4.1.1.3 Identification of the scope and recommended budget
andspecificationsinamannerthatwillallowfortimelyreview
for the BECx process and development of a preliminary BECx
and consideration by theAOR prior to solicitation and contract
Plan;
award, and;
4.1.1.4 Technical assistance and documentation during the 25
4.1.2.4 Direct and substantive participation (see 4.2)by
development of the BOD, contract documents, project-specific
the BECxP and BECxG during the Bidding and Negotiation,
BECx specification section, and final OPR during the Design
Phase of the BECx process, including completion of a mini-
Though it is recognized that all parties participating in the design and
LEED is a trademark held by the U.S. Green Building Council. construction of the building are part of the BECx process, for the purposes of this
Typically characterized by theAOR as “50 %” completion of the Construction practice, the BECx group (BECxG) is defined as the group of individuals, working
Documents, subject to review and concurrence by the Owner and BECxP. under direct supervision of the BECxP. This group may be comprised of a single
Including retroactive development of a written OPR in circumstances where a person or may include multiple subject matter specialists and administrative staff. It
formal OPR may not exist or otherwise was not fully developed during the is the responsibility of the BECxP to perform each required task or to delegate the
Pre-Design Phase of the BECx process as defined byANSI/ASHRAE/IES Standard appropriate task to the appropriate Group member.
202 and Guide E2947. As outlined in ANSI/ASHRAE/IES Standard 202 and Guide E2947, unless
The BECx Plan shall be as defined byANSI/ASHRAE/IES Standard 202 and otherwise defined in this practice.
Guide E2947. As defined in ANSI/ASHRAE/IES Standard 202 and Guide E2947.
E2813 − 18
Pre-Construction, Construction Administration, and Occu- 4.2.1.3 Contract Documents and Construction
pancy and Operations phases of the BECx process, including Administration,including,ataminimum,demonstratedknowl-
pre-construction laboratory and field performance testing as edge of the:
required in Annex A2 for Enhanced BECx. (1) Interrelationship and commonly understood hierarchy
that exists between Procurement Documents, Contract
4.2 This practice establishes that the BECxP shall assemble
Documents,ContractDrawingsandSpecifications developed
a group (BECxG) that, at a minimum, demonstrates a level of
during the Design Phase of the BECx process, as well as
proficiency in the core competencies listed below that meets or
submittals and legally binding Instruments of Change issued
exceeds the requirements of building codes, standards,
during the Pre-Construction (Procurement) and Construction
guidelines, and regulations applicable to or otherwise volun-
Phases of the BECx process, including but not limited to:
tarily adopted by the Owner to govern enclosure-related
Addenda; Submittals; Architect’s Supplemental Instructions
design, construction, and performance. Determination of the
and Field Directives; Construction Change Directives, and;
qualification of the BECxP and BECxG will be at the discre-
Change Orders;
tion of the Owner:
(2) Influence of enclosure-related design, detailing, and
4.2.1 BECxG Core Competencies:
integration on total building performance, including at a
4.2.1.1 Building and Materials Science, including, at a
minimum consideration of the performance attributes listed in
minimum, demonstrated knowledge of the:
1.5 and Annex A1 of this practice;
(1) Principles associated with heat transfer via conduction,
(3) Influence of product selection, allowable construction
convection, radiation, and air infiltration/exfiltration;
tolerances, and dimensional requirements to accommodate
(2) Principles associated with moisture storage and trans-
environmental and service loads on detailing at interface
port via gravity, diffusion, convection, capillary action, ab-
conditions between enclosure-related materials, components,
sorbed flow, and osmosis; and
systems, and assemblies, and; the corresponding influence on
(3) Characteristics and behavior of enclosure-related
sequencing, phasing, and coordination of trades during the
materials, components, systems, and assemblies when speci-
Construction Phase of the BECx process;
fied for a given application, geographic region, location,
(4) Importance of material compatibility and continuity of
exposure, or climate, and corresponding influence on
primary heat, air, and moisture control layers throughout the
workability, durability, serviceability, performance, and antici-
building enclosure on total building performance and the
pated service-life.
appropriate mitigation of risks associated with improperly
(4) Principles of structural loading and structural capacity
managed heat, air, and moisture transport across the building
of enclosure-related materials, components, systems, and as-
enclosure;
semblies for specified loads including: wind, earthquake,
(5) Importanceofthetimelypreparationanddistributionof
projectile, differential volume change, and kinetic energy and
subject-direct, technically sound, and actionable documenta-
differential pressure conditions.
tionandfeedbacktotheOwner,design,andconstructionteams
4.2.1.2 Procurement and Project Delivery, including, at a
throughout the Construction Phase of the BECx process.
minimum, demonstrated knowledge of the:
26 4.2.1.4 Performance Test Standards and Methodology,
(1) Influence of the project delivery method selected by
including, at a minimum, demonstrated knowledge of the:
the Owner on the scope, adaptation, implementation, and cost
(1) Pre-construction laboratory and field-applied test stan-
of the BECx process as defined in this practice;
27 dards and methodology referenced in this practice (see Annex
(2) Influence of the number and type of contracts estab-
A2) and their intended use and application in evaluating the
lished between the Owner and the design and construction
durability, performance, constructability, and anticipated
teams on the role and responsibilities of the BECxP and
service-life of enclosure-related materials, components,
individual members of the BECx group;
systems, and assemblies;
(3) Influence of design and construction scheduling,
(2) Importance of establishing appropriate and quantifiable
phasing, and sequencing of the work on the scope, adaptation,
thresholds of performance and clear and unambiguous defini-
implementation, and cost of the BECx process as defined in
tions of failure for enclosure-related materials, components,
this practice;
systems, and to allow for proper enforcement of the contract
(4) Influence of the experience, qualifications, technical
documents;
depth,andcommitmentofthedesignandconstructionteamsto
(3) Influence of modifications to the intended use and
the BECx process on the role and responsibilities of the
application of pre-construction laboratory and field test stan-
BECxP, the range and technical depth required of the BECx
dardsandmethodologyontheappropriateinterpretationoftest
group, and the anticipated scope and cost of the BECx process.
results and their relevance to the requirements of the contract
documents;
Including, but not limited to: Design-Build; Design-Bid-Build; Design-
Negotiate-Build; Construction Management, and; Owner-Build as defined by CSI As defined by the Construction Specifications Institute (CSI).
Project Resource Manual and Manual of Practice. Including, but not limited to integration with base building structural and
Including, but not limited to Single-Prime Contract and Multiple-Prime environmental control systems.
Contracts, with basis-of-payment provisions that may include: Stipulated/Lump Including the limitations associated with each test standard.
Sum; Cost-Plus Fee; Fixed Fee, and; Guaranteed Maximum Price, with penalties, Including remedial action required in the event of failure and the nature and
bonuses,andincentivesforearlycompletionoftheworkandliquidateddamagesfor extent of re-testing necessary to evaluate compliance of the repair(s) with the
any delays in substantial or final completion of the project. requirements of the contract documents.
E2813 − 18
(4) Importance of confirming the timely, clear, and unam- 5.1.1.4 Provide technical assistance to the Owner during the
biguous translation of all modifications to the design, development of a written OPR for enclosure materials,
construction, and integration of enclosure-related materials, components, systems, and assemblies in accordance with
components, systems, and assemblies arising from pre- Annex A1 of this practice, including at a minimum an
constructionlaboratorytestingtothefieldduringtheConstruc- evaluation of the interrelationship between the following
tion Phase of the BECx process; performance attributes and the relative influence of each on
(5) Importance of recognizing the distinction between er- enclosure, performance, and total cost of ownership:
rors and omissions in architectural or product design, or both, (1) Energy
versus defective installation or workmanship, or both, when (2) Environment
interpreting field test results, and; the techniques available (3) Safety
during the development and implementation of field testing (4) Security
protocols that will minimize the risk for confusion and misin- (5) Durability
terpretation relative to the requirements of the contract docu- (6) Sustainability
ments; (7) Operation
(6) Distinction between test standards and methodologies 5.1.1.5 Provide a summary of the preliminary BECx Plan
“recognized in the industry” or otherwise developed by indus- scope and budget to the Owner.
try or trade associations versus test standards developed by 5.1.2 Design Phase:
independent standards-writing organizations and the impact, if 5.1.2.1 Review and document the OPR and preliminary
any, on the enforcement of the contract documents when both BECx Plan developed during the Pre-Design phase of the
are included in the project specifications. BECx process;
5.1.2.2 Review and provide technical assistance during the
5. Procedure
development of the preliminary enclosure BOD;
5.1.2.3 Provide or otherwise coordinate the completion of
5.1 This practice establishes that the BECx process shall be
anindependentdesignreviewofenclosure-relatedconstruction
as outlined in ANSI/ASHRAE/IES Standard 202 and Guide
document drawings and specifications based on the following
E2947 and include, at a minimum, the following:
sub-phases of the design process:
5.1.1 Pre-Design Phase:
5.1.1.1 Attend a project planning conference (“Kick-Off (1) Schematic Design
(2) Design Development
Meeting”);
5.1.1.2 Review the functional and programmatic require- (3) Construction Documents
5.1.2.4 Update, refine, and document the OPR, enclosure
ments for the project established by the Owner and AOR;
5.1.1.3 Review and discuss factors influencing enclosure BOD, and BECx Plan at the conclusion of each sub-phase of
the design process;
design, construction, long-term durability, serviceability, and
performance with the Owner and AOR (if retained), including 5.1.2.5 Establish appropriate and quantifiable enclosure-
related performance metrics, test standards, and test method-
at a minimum (see also Annex A1):
ology in accordance with Annex A2 for incorporation into the
(1) Anticipated construction type, importance factor, and
contract documents, including:
occupancy/use classification;
(1) Preconstruction laboratory mockups;
(2) Geographic location and climate;
(2) Field-constructed “off-structure” mockups;
(3) Site orientation, massing, and options for enclosure
(3) Field-constructed “on-structure,” first-installation
material selection, integration, and relative distribution at each
mockups;
building exposure that will consider:
(4) Field testing at milestone intervals during construction;
(a) Identification and apportionment of initial enclosure
(5) Post-occupancy evaluation and performance testing.
costs;
5.1.2.6 Provide a formal, written response to the position(s)
(b) Occupant comfort, productivity, and rate of return on
taken by theAOR and other contracted parties to the project in
initial investment;
response to BECxP/BECxG comments and recommendations,
(c) Enclosure long-term durability and performance;
(d) Costs associated with routine maintenance and energy including BECxP/BECxG recommendations not accepted by
theAOR and a summary discussion of the relative advantages,
use;
(e) Sustainable design objectives with long-term durabil-
ity and performance;
(f) Optimize acoustical requirements; and 33
Refer also to Guide E2947 for additional information regarding development
of the OPR document.
(g) Safety and security requirements.
The Design Phase is the BECxP minimum point-of-engagement required to
(4) Consideration of exemplars that may exist in the same
qualify as Fundamental BECx under this practice. Refer to ANSI/ASHRAE/IES
region or climate for which actual as-built enclosure perfor-
Standard 202 and Guide E2947 for additional steps associated with this phase of the
mance can be quantifiably evaluated.
BECx process.
Includingretro-activedevelopmentofawrittenOPRdocumentbasedoninput
provided by the Owner in circumstances where a formal written OPR may not exist
The Pre-Design Phase is the BECxP minimum point-of-engagement required but is required to qualify as Fundamental BECx under this practice.
to qualify as Enhanced BECx under this practice. Refer to ANSI/ASHRAE/IES Required to qualify for Enhanced BECx under this practice (optional for
Standard 202 and Guide E2947 for additional steps associated with this phase of the Fundamental BECx).
BECx process. Required to qualify for both Fundamental and Enhanced BECx.
E2813 − 18
disadvantages,andpotentialrisksassociatedwitheachofthose (6) Test standards and methodologies, performance
decisions on building enclosure durability, performance, and thresholds, appropriate interpretation of test results, and defi-
38 43
total cost of ownership. nitions of failure required in the contract documents;
5.1.2.7 Confirm documentation of the Design Phase OPR, (7) On-site construction observation and documentation
enclosureBOD,andBECxPlanforreviewandapprovalbythe
protocol established for the timely identification and remedia-
Owner. tion of hidden/concealed or otherwise unanticipated conditions
5.1.3 Bidding and Negotiation Phase:
in the field, enclosure-related product or installation defects,
5.1.3.1 Attend a Pre-Bid Conference to review the BECx and non-conforming work;
specification with prospective bidders;
(8) Modification or refinement of enclosure-related
5.1.3.2 Review and assist by providing Owner requested detailing, fabrication, installation requirements, or sequencing
evaluation of enclosure-related bidder requests for information
and coordination of trades, or a combination thereof, arising
or clarification and assist the AOR and Owner with the from pre-construction mock-up assembly and testing.
development of Addenda as appropriate;
5.1.4.3 Substantive participation during in-plant QA and
5.1.3.3 Review and assist with the evaluation of enclosure-
QC reviews including, at a minimum, review and documenta-
related contractor/subcontractor bids, including at a minimum:
tion of the methodology of:
(1) Scheduling, phasing, and coordination of trades;
(1) Industry standard quality control criteria that may be
(2) Quality Assurance (QA) and Quality Control (QC)
applicable to the procurement or manufacture, or both, of the
programs;
materials, components, systems, and assemblies specified for
(3) Qualifications and Exclusions; and
the project;
(4) Substitutions and “Value Engineering” options.
(2) Methodology established to identify, track, and
5.1.3.4 Confirm documentation of the Pre-Construction
remediate, at milestone intervals during production, defective
Phase OPR, enclosure BOD, and BECx Plan for review and
and nonconforming work;
approval by the Owner.
(3) Product or project-specific in-house technical training
5.1.4 Construction Phase:
programs;
5.1.4.1 Technical assistance during the review of enclosure-
(4) In-house performance testing capabilities available for
related shop drawings and technical submittals for compliance
application to completed components and assemblies at mile-
with the contract documents;
stone intervals during production.
5.1.4.2 Substantive participation in a Pre-Construction
5.1.4.4 On-site construction observation and
Meeting and Pre-Installation Meetings with the GC, CM, and
documentation, including:
enclosure-related subcontractors and trades to review and
(1) Periodic observation, evaluation, and documentation of
document, at a minimum:
enclosure-related work in progress at representative locations
(1) Final approved OPR, enclosure BOD, and BECx Plan; 45
on the project for compliance with the contract documents;
(2) Status of all outstanding shop drawings and technical
(2) Development and distribution of field observation
submittals;
reports, field test reports, and related documentation as re-
(3) Schedule, phasing, and coordination of enclosure-
quired for timely and effective review and remedial action by
related subcontractors and trades; 46
the GC, CM, and appropriate subcontractors and trades;
(4) GC,CM,subcontractor,andenclosure-relatedtradeQA
(3) Coordination of and attendance at regularly scheduled
and QC programs;
BECx meetings with the GC, CM, and appropriate subcontrac-
(5) Subcontractorqualifications,exclusions,andconditions
tors and trades;
associated with the construction of a fully integrated building
enclosure that may influence product, material, or installation
warranties;
Including anticipated schedule for field testing and required coordination of
trades to fully complete the work at each test specimen prior to testing.
38 44
Documentation shall be provided as part of the updated OPR. Examples include inspection or quality control criteria, or both, established by
ReferenceANSI/ASHRAE/IES Standard 202 and Guide E2947 for additional AAMA, the Portland Cement Association, and similar organizations that are in
information. compliance with ISO 9000 and may be already required contractually or otherwise
Including, but not limited to, meetings in preparation for pre-construction have been adopted for use by the supplier/manufacturer to which this practice is
laboratoryorfield-constructed,orboth,mock-ups,“firstinstallation”mock-ups,and applied.
actual construction in the field. The number and frequency of site visits required will vary based upon the
Including, but not limited to, review and coordination of approved shop complexity of the project and nature/extent of the work-in-progress and shall be
drawings for accuracy, completeness, and coordination with adjacent trades at determined at the sole discretion of the BECxP, subject to review and approval by
enclosure interface conditions. the Owner.
42 46
Including, but not limited to, in-plant performance testing capabilities during TheBECxPshalldevelop,periodicallyupdate,andmaintainasummaryissues
production and milestone evaluation forms, checklists, and similar documentation and resolutions log including items identified during the Construction Phase of the
intended to support both off-site fabrication and on-site field quality control BECx process, and the actions taken by the construction team to address or
programs. otherwise remediate missing or non-conforming work.
E2813 − 18
(4) Review and documentation of enclosure-related field (2) Location and status of “open” or otherwise unresolved/
performancetestingatmilestoneintervalsthroughoutconstruc- undocumented remediation activities to address nonconform-
tion for compliance with the requirements of the contract ing work identified during construction and documented at
documents, including at a minimum: substantial completion of the project;
(a) Review and documentation of the design and con- (3) Estimated schedule for routine evaluation and mainte-
struction of all field-constructed test chambers and verification nance.
of current calibration of all test equipment as required by the 5.1.5.2 Perform a limited (nondestructive) visual condition
governing industry standard for the test method specified; survey, performance testing, and qualitative assessment of
(b) Review and clarification of test procedures and enclosure-related materials, components, systems, and assem-
methodology, performance thresholds, and definition(s) of blies at milestone intervals during applicable warranty periods
“non-compliance” or “failure” as required in the contract as outlined in the BECx schedule for routine evaluation and
documents. maintenance, or as requested by the Owner based on in-service
(5) Review and documentation of modifications to or performance;
further refinement of the contrac
...
This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Because
it may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current version
of the standard as published by ASTM is to be considered the official document.
´1
Designation: E2813 − 12 E2813 − 18
Standard Practice for
Building Enclosure Commissioning
This standard is issued under the fixed designation E2813; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
ε NOTE—Editorial changes were made throughout in April 2015.
INTRODUCTION
Building Enclosure Commissioning (BECx) is a process that begins with the establishment of the
Owner’s Project Requirements (OPR) and endeavors to ensureconfirm that the exterior enclosure and
those elements intended to provide environmental separation within a building or structure meet or
exceed the expectations of the Owner as defined in the OPR. described in the OPR, and as defined by
the contract documents. A fundamental understanding of the most current published edition of
ASHRAEANSI/ASHRAE/IES Standard 202, Commissioning Process for Buildings and Systems and
ASTM E2947, Standard Guide for Building Enclosure Commissioning is recommended for optimal
use and application of this practice.
1. Scope
1.1 This practice is intended to serve as a concise, authoritative, and technically sound practice for Building Enclosure
Commissioning (BECx) that establishes two levels of BECx: Fundamental and Enhanced (refer also to Section 4).
1.2 The BECx process as defined in this practice includes the following phases and sub-phases:
1.2.1 Pre-design,
1.2.2 Design,
1.2.2.1 Schematic Design,
1.2.2.2 Design Development,
1.2.2.3 Construction Documentation,
1.2.3 Pre-Construction,Bidding and Negotiation Phase,
1.2.4 Construction, and
1.2.4.1 Pre-Construction,
1.2.4.2 Construction Administration, and
1.2.5 Occupancy and Operations.
1.3 This practice includes a mandatory OPR Development Guideline (Annex A1) and requires the development of an OPR for
both Fundamental and Enhanced BECx that addresses, at a minimum, the performance attributes and metrics included in Annex
A1 of this practice.
1.4 This practice includes mandatory BECx Performance Testing Requirements (Annex A2) approved for use with this practice
to evaluate the performance and durability of enclosure materials, components, systems, and assemblies.
1.5 This practice mandates independent, third-party independent design peer review during the Design Phase of both
Fundamental and Enhanced BECx.
1.6 This practice recognizes that the OPR for exterior enclosure performance and environmental separation may exceed the
baseline requirements of applicable building codes and standards and provides guidance for the development of an OPR based on
the following attributes as defined in Annex A1 of this practice:
1.6.1 Energy,
1.6.2 Environment,
This practice is under the jurisdiction of ASTM Committee E06 on Performance of Buildings and is the direct responsibility of Subcommittee E06.55 on Performance
of Building Enclosures.
Current edition approved Feb. 1, 2012Oct. 1, 2018. Published April 2015December 2018. Originally approved in 2012. Last previous edition approved in 2012 as
ɛ1
E2813–12.–12 . DOI: 10.1520/E2813-12E01.10.1520/E2813–18.
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
E2813 − 18
1.6.3 Safety,
1.6.4 Security,
1.6.5 Durability,
1.6.6 Sustainability, and
1.6.7 Operation.
1.7 The terms “building enclosure” and “enclosure” as they appear in this practice refer collectively to all materials,
components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or
between two or more environmentally distinct interior spaces in a building or structure.
1.8 This practice establishes that the Building Enclosure Commissioning Provider (BECxP) refers specifically to the individual
retained by the Owner to develop, manage, and be in responsible charge of the BECx process, including individual members and
technical specialists that may comprise the BECx teamgroup (see 4.2).
1.9 The role and responsibilities of the BECxP as defined by this practice are not intended to supersede or otherwise replace
the contractual obligations reserved specifically for the parties responsible for the design and construction of a building or structure,
nor the duties that may otherwise be assigned to those parties by applicable regulatory or statutory law.
1.10 This practice is not intended to warrant or otherwise guarantee the as-built or in-service durability, or both, and
performance of enclosure materials, components, systems, and assemblies.
1.11 The values stated in SI units are to be regarded as standard. The values given in parentheses are mathematical conversions
to inch-pound units that are provided for information only and are not considered standard.
1.12 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility
of the user of this standard to establish appropriate safety safety, health, and healthenvironmental practices and determine the
applicability of regulatory limitations prior to use.
1.13 This international standard was developed in accordance with internationally recognized principles on standardization
established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued
by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
2. Referenced Documents
2.1 ASTM Standards:
C423 Test Method for Sound Absorption and Sound Absorption Coefficients by the Reverberation Room Method
C510 Test Method for Staining and Color Change of Single- or Multicomponent Joint Sealants
C522 Test Method for Airflow Resistance of Acoustical Materials
C724 Test Method for Acid Resistance of Ceramic Decorations on Architectural-Type Glass
C732 Test Method for Aging Effects of Artificial Weathering on Latex Sealants
C794 Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants
C1060 Practice for Thermographic Inspection of Insulation Installations in Envelope Cavities of Frame Buildings
C1087 Test Method for Determining Compatibility of Liquid-Applied Sealants with Accessories Used in Structural Glazing
Systems
C1153 Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging
C1193C1193-11a Guide for Use of Joint Sealants
C1246 Test Method for Effects of Heat Aging on Weight Loss, Cracking, and Chalking of Elastomeric Sealants After Cure
C1258 Test Method for Elevated Temperature and Humidity Resistance of Vapor Retarders for Insulation
C1279 Test Method for Non-Destructive Photoelastic Measurement of Edge and Surface Stresses in Annealed, Heat-
Strengthened, and Fully Tempered Flat Glass
C1294 Test Method for Compatibility of Insulating Glass Edge Sealants with Liquid-Applied Glazing Materials
C1371 Test Method for Determination of Emittance of Materials Near Room Temperature Using Portable Emissometers
C1522 Test Method for Extensibility After Heat Aging of Cold Liquid-Applied Elastomeric Waterproofing Membranes
C1549 Test Method for Determination of Solar Reflectance Near Ambient Temperature Using a Portable Solar Reflectometer
C1601 Test Method for Field Determination of Water Penetration of Masonry Wall Surfaces
C1651 Test Method for Measurement of Roll Wave Optical Distortion in Heat-Treated Flat Glass
C1652C1652/C1652M Test Method for Measuring Optical Distortion in Flat Glass Products Using Digital Photography of Grids
D2203 Test Method for Staining from Sealants
D4541 Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers
D5957 Guide for Flood Testing Horizontal Waterproofing Installations
E90 Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements
For referenced ASTM standards, visit the ASTM website, www.astm.org, or contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Standards
volume information, refer to the standard’sstandard’s Document Summary page on the ASTM website.
E2813 − 18
E283 Test Method for Determining Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified
Pressure Differences Across the Specimen
E330E330/E330M Test Method for Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by
Uniform Static Air Pressure Difference
E331 Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air
Pressure Difference
E336 Test Method for Measurement of Airborne Sound Attenuation between Rooms in Buildings
E488E488/E488M Test Methods for Strength of Anchors in Concrete Elements
E492 Test Method for Laboratory Measurement of Impact Sound Transmission Through Floor-Ceiling Assemblies Using the
Tapping Machine
E514E514/E514M Test Method for Water Penetration and Leakage Through Masonry
E576 Test Method for Frost/Dew Point of Sealed Insulating Glass Units in the Vertical Position
E596 Test Method for Laboratory Measurement of Noise Reduction of Sound-Isolating Enclosures
E631 Terminology of Building Constructions
E779 Test Method for Determining Air Leakage Rate by Fan Pressurization
E783 Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors
E795 Practices for Mounting Test Specimens During Sound Absorption Tests
E903 Test Method for Solar Absorptance, Reflectance, and Transmittance of Materials Using Integrating Spheres
E966 Guide for Field Measurements of Airborne Sound Attenuation of Building Facades and Facade Elements
E997 Test Method for Evaluating Glass Breakage Probability Under the Influence of Uniform Static Loads by Proof Load
Testing
E1007 Test Method for Field Measurement of Tapping Machine Impact Sound Transmission Through Floor-Ceiling Assemblies
and Associated Support Structures
E1014 Guide for Measurement of Outdoor A-Weighted Sound Levels
E1050 Test Method for Impedance and Absorption of Acoustical Materials Using a Tube, Two Microphones and a Digital
Frequency Analysis System
E1105 Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain
Walls, by Uniform or Cyclic Static Air Pressure Difference
E1186 Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems
E1425 Practice for Determining the Acoustical Performance of Windows, Doors, Skylight, and Glazed Wall Systems
E1503 Test Method for Conducting Outdoor Sound Measurements Using a Digital Statistical Sound Analysis System
E1827 Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door
E1886 Test Method for Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems Impacted by
Missile(s) and Exposed to Cyclic Pressure Differentials
E1980 Practice for Calculating Solar Reflectance Index of Horizontal and Low-Sloped Opaque Surfaces
E1996 Specification for Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems Impacted by
Windborne Debris in Hurricanes
E2099 Practice for the Specification and Evaluation of Pre-Construction Laboratory Mockups of Exterior Wall Systems
E2178 Test Method for Air Permeance of Building Materials
E2179 Test Method for Laboratory Measurement of the Effectiveness of Floor Coverings in Reducing Impact Sound
Transmission Through Concrete Floors
E2249 Test Method for Laboratory Measurement of Airborne Transmission Loss of Building Partitions and Elements Using
Sound Intensity
E2264 Practice for Determining the Effects of Temperature Cycling on Fenestration Products
E2268 Test Method for Water Penetration of Exterior Windows, Skylights, and Doors by Rapid Pulsed Air Pressure Difference
E2319 Test Method for Determining Air Flow Through the Face and Sides of Exterior Windows, Curtain Walls, and Doors
Under Specified Pressure Differences Across the Specimen
E2353 Test Methods for Performance of Glazing in Permanent Railing Systems, Guards, and Balustrades
E2357 Test Method for Determining Air Leakage Rate of Air Barrier Assemblies
E2359E2359/E2359M Test Method for Field Pull Testing of an In-Place Exterior Insulation and Finish System Clad Wall
Assembly
E2570E2570/E2570M Test Methods for Evaluating Water-Resistive Barrier (WRB) Coatings Used under Exterior Insulation and
Finish Systems (EIFS) or EIFS with Drainage
E2649 Test Method for Determining Argon Concentration in Sealed Insulating Glass Units Using Spark Emission Spectroscopy
E2947 Guide for Building Enclosure Commissioning
F1233 Test Method for Security Glazing Materials And Systems
F1642F1642/F1642M Test Method for Glazing and Glazing Systems Subject to Airblast Loadings
F1869 Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride
E2813 − 18
F2170 Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes
F2420 Test Method for Determining Relative Humidity on the Surface of Concrete Floor Slabs Using Relative Humidity Probe
Measurement and Insulated Hood (Withdrawn 2014)
2.2 ASHRAE Guidelines:
ASHRAE 90.1 Map of Climate Zones
ASHRAE Standard 202 Commissioning Process for Buildings and Systems
2.2 AAMA Standards:
AAMA 501.1 Standard Test Method for Water Penetration of Windows, Curtain Walls,Walls and Doors Using Dynamic Pressure
AAMA 501.2 Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls, and Sloped
Glazing Systems
AAMA 501.4 Recommended Static Test Method for Evaluating Window Wall, Curtain Wall and Storefront Systems Subjected
to Seismic and Wind-Induced Interstory DriftsInter-Story Drift
AAMA 501.5 Test Method for Thermal Cycling of Exterior Walls
AAMA 508-07 Voluntary Test Method and SpecificationsSpecification for Pressure Equalized Rain Screen Wall Cladding
Systems
AAMA 1503 Voluntary Test Method for Thermal Transmittance and Condensation Resistance of Windows, Doors, and Glazed
Wall Sections
AAMA 1801 Voluntary Specification for the Acoustical Rating of Exterior Windows, Doors, Skylights and Glazed Wall Sections
2.3 ANSI Standards:
ANSIANSI/ASA S12.8 Methods for Determination of Insertion Loss of Outdoor Noise Barriers
ANSIANSI/ASA S12.60 Acoustical Performance Criteria, Design Requirements, and Guidelines for Schools
ANSI/ASHRAE/IES 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings (Map of Climate Zones)
ANSI-ASHRAE ANSI/ASHRAE/IES Standard 101 Application of Infrared Sensing Devices to the Assessment of Building Heat
Loss Characteristics
ANSI/ASHRAE/IES Standard 202 Commissioning Process for Buildings and Systems
2.4 CAN/CGSB Standards:Standard:
CAN/CGSB 149-GP-2MP Manual for Thermographic Analysis of Building EnvelopesEnclosures
2.5 CEN Standards:Standard:
CEN 1063 Testing and Classification of Resistance Against Bullet AttackGlass in building - Security glazing - Testing and
classification of resistance against bullet attack
2.6 CSA Standards:Standard:
CSA-A123.21 Standard Test Method for the Dynamic Wind Uplift Resistance of Membrane Roofing Membrane-Roofing
Systems
2.7 CSI Standards:Standard:
Project Resource Manual and Manual of Practice
2.8 GANA Test Methods:
GANA LD 100-06 Standard Test Method for Ball Drop Impact of Laminated Architectural Flat Glass
GANA TD 101-04 Standard Test Method for Center-Punch Fragmentation of Fully-Tempered Flat Glass
GANA LD 101-08 Standard Specification for Ball Drop Impact Resistance of Laminated Architectural Flat Glazing
2.9 GSA Standards:Standard:
GSA TS-01GSA-TS01 Standard Test Method for Glazing and Window Systems Subject to Dynamic Overpressure Loadings
2.10 ICC Publications:Publication:
International Building Code
The last approved version of this historical standard is referenced on www.astm.org.
Available from American Architectural Manufacturers Association (AAMA), 1827 Walden Office Square, Suite 550, Schaumburg, Illinois 60173-4268, http://
www.aamanet.org.
Available from American National Standards Institute (ANSI), 25 W. 43rd St., 4th Floor, New York, NY 10036, http://www.ansi.org.
Available from Canadian General Standards Board (CAN/CGSB), (CGSB), 11 Laurier St., Phase III, Place du Portage, Gatineau, Quebec K1A 0S5, Canada,
http://www.tpsgc-pwgsc.gc.ca/ongc-cgsb/index-eng.html.
Available from European Committee for Standardization (CEN), Avenue Marnix 17, B-1000, Brussels, Belgium, http://www.cen.eu.
Available from Canadian Standards Association (CSA), 5060 Spectrum Way, Mississauga, ON L4W 5N6, Canada, http://www.csa.ca.178 Rexdale Blvd., Toronto, ON
M9W 1R3, Canada, http://www.csagroup.org.
Available from Construction Specifications Institute (CSI), 110 SouthS. Union Street, Suite 100, Alexandria VA 22314, http://www.csinet.org. http://
www.csiresources.org.
Available from Glass Association of North America (GANA), 800 SW Jackson St.St., Suite 1500, Topeka, KS 66612-1200, http://www.glasswebsite.org.
http://www.glasswebsite.com.
Available from U.S. General Services Administration (GSA), One Constitution Square, 1275 First Street, NE, Washington, DC 20417,1800 F Street, NW, Washington,
DC 20405, http://www.gsa.gov.
Available from International Code Council (ICC), 500 New Jersey Ave., NW, 6th Floor, Washington, DC 20001, http://www.iccsafe.org.
E2813 − 18
2.11 ISO Publications:Publication:
ISO 9000
2.13 NIJ Standards:
NIJ Std. 0108.01 Ballistic Resistant Protective Materials
2.12 NFRC Standards:
NFRC 100 Procedure for Determining Fenestration Product U-Factors
NFRC 200 Procedure for Determining Fenestration Product Solar Heat Gain Coefficient and Visible Transmittance at Normal
Incidence
NFRC 300 Test Method for Determining the Solar Optical Properties of Glazing Materials and Systems
2.13 NIJ Standard:
NIJ Std. 0108.01 Ballistic Resistant Protective Materials
2.14 State Department (SD) Ballistic Standards:Standard:
SD-STD-01.01 Forced Entry and Ballistic Resistance of Structural Systems
2.15 UL Standards:Standard:
UL 752 Standard of Safety for Bullet-Resisting Equipment
3. Terminology
3.1 Definitions—Refer to the most current edition of the following:
3.1.1 ASHRAEANSI/ASHRAE/IES Standard 202, Section 3, Definitions
3.1.2 Guide E2947
3.1.3 Terminology E631
3.1.4 AIA Architect’s Handbook of Professional Practice
3.1.5 CSI Project Resource Manual and Manual of Practice
3.2 Acronyms:
3.2.1 AAMA—American Architectural Manufacturers Association
3.2.2 A/E—Architect/Engineer
3.2.3 AIA—American Institute of Architects
3.2.4 ANSI—American National Standards Institute
3.2.5 AOR—Architect-of-Record
3.2.6 ASCE—American Society of Civil Engineers
3.2.7 ASHRAE—American Society of Heating, Refrigerating and Air Conditioning Engineers
3.2.8 BCA—Building Commissioning Association
3.2.9 BECx—Building Enclosure Commissioning
3.2.10 BECxG—Building Enclosure Commissioning Group
3.2.11 BECxP—Building Enclosure Commissioning Provider (aka “Agent” or “Authority”)
3.2.12 BECxT—BOD—Building Enclosure Commissioning TeamBasis-of-Design
3.2.11 BOD—Basis-of-Design
3.2.13 CAN/CGSB—Canadian General Standards Board
3.2.14 CSA—Canadian Standards Association
3.2.15 CSI—Construction Specifications Institute
3.2.16 Cx—Commissioning
3.2.16 CxA—Commissioning Agent (or “Authority”)
3.2.17 CxP—Commissioning Provider
3.2.18 EIS—Energy Information System
Available from National Institute of Justice (NIJ), 810 7th St., NW, Washington, DC 20531, http://nij.gov.International Organization for Standardization (ISO), ISO
Central Secretariat, BIBC II, Chemin de Blandonnet 8, CP 401, 1214 Vernier, Geneva, Switzerland, http://www.iso.org.
Available from National Institute of Justice (NIJ), 810 7th St., NW, Washington, DC 20531, http://nij.gov.
Available from National Fenestration Rating Council (NFRC), 6305 Ivy Lane,Ln., Suite 140, Greenbelt, MD 20770, http://www.nfrc.org.
Available from U.S. Government Printing Office Superintendent of Documents, Publishing Office (GPO), 732 N. Capitol St., NW, Mail Stop: SDE, Washington, DC
20401, http://www.access.gpo.gov.20401-0001, http://www.gpo.gov.
Available from Underwriters Laboratories (UL), 2600 N.W. Lake Rd., Camas, WA 98607-8542, http://www.ul.com.
Selection, interpretation, application, and use of the terminology contained in these documents shall be at the sole discretion of the BECxP. Reconciliation of conflicts
in terminology or the definition of terms that may exist among or between these documents shall be the sole responsibility of the BECxP, subject to review and final approval
by the AOR and Owner.
E2813 − 18
3.2.19 EMCS—Energy Management and Control System
3.2.20 EOR—Engineer-of-Record
3.2.21 GANA—Glass Association of North America
3.2.22 GSA—United States General Services Administration
3.2.23 HVAC—Heating, Ventilation, and Air Conditioning
3.2.24 IAQ—Indoor Air Quality
3.2.25 IEQ—Indoor Environmental Quality
3.2.26 LEED—Leadership in Energy and Environmental Design (trademark )
3.2.27 NASFA—National Association of State Facilities Administrators
3.2.28 NEBB—National Environmental Balancing Bureau
3.2.29 NIBS—National Institute of Building Sciences
3.2.30 NFRC—National Fenestration Rating Council
3.2.31 O&M—Operations and Maintenance
3.2.32 OPR—Building Enclosure Owner’s Project Requirements
3.2.33 RCx—Retro-Commissioning
3.2.34 ReCx—Re-Commissioning
3.2.35 RFI—Request For Information
3.2.36 RFP—Request For Proposals
3.2.37 RFQ—Request For Qualifications
3.2.38 TAB—Testing, Adjusting, and Balancing
3.2.36 USDHS (or DHS)—U.S. Department of Homeland Security
3.2.37 USDOD (or DOD)—U.S. Department of Defense
3.2.38 USDOE (or DOE)—U.S. Department of Energy
3.2.39 USDOS (or DOS)—U.S. Department of State
3.2.40 USGBC—U.S. Green Building Council
3.2.41 VA—U.S. Department of Veterans Affairs
4. Summary of Practice
4.1 This practice establishes two levels of BECx: Fundamental and Enhanced.
4.1.1 Fundamental BECx—Architecture or engineering-related technical services, or both, performed on behalf of the Owner
by the BECxP and associated group members and summarized as follows:
4.1.1.1 BECxP engagement during the Design Phase of the BECx process, but no later than commencement of the Design
Development sub-phase;
4.1.1.2 Review and documentation of the preliminary OPR developed during the Pre-Design Phase of the BECx process;
4.1.1.3 Identification of the scope and recommended budget for the BECx process and development of a preliminary BECx
Plan;
4.1.1.4 Technical assistance and documentation during the development of the BOD, contract documents, project-specific BECx
specification section, and final OPR during the Design Phase of the BECx process, including completion of a minimum of one
independent, third-party independent design peer review of enclosure-related construction document drawings and specifications
in a manner that will allow for timely review and consideration by the AOR prior to solicitation and contract award. The
project-specific BECx specification section establishes the roles and responsibilities of the contractor and individual members of
the construction team in the context of the BECx process, including a summary of required pre-construction laboratory and field
performance test standards and methodology for enclosure-related materials, components, systems, and assemblies adopted
fromrequired by Annex A2 of this practice and further defined by the AOR in the approved contract document drawings and
specifications;construction documents;
LEED is a trademark held by the U.S. Green Building Council.
Typically characterized by the AOR as “50 %” completion of the Construction Documents, subject to review and concurrence by the Owner and BECxP.
Including retroactive development of a written OPR in circumstances where a formal OPR may not exist or otherwise was not fully developed during the Pre-Design
Phase of the BECx process as defined by ASHRAEANSI/ASHRAE/IES Standard 202 and Guide E2947.
The BECx Plan shall be as defined by ASHRAEANSI/ASHRAE/IES Standard 202 and Guide E2947.
E2813 − 18
4.1.1.5 Development of Document a final BECx Plan that includes an outline of the BECx process, BECx roles and
responsibilities of the BECxP and BECxP, individual members of the BECx team,group, the Design Team, the Construction
Team, and the methodology established to verify and document compliance of the as-built construction with the requirements of
the approved contract documents. The BECx Plan shall be developed to align with the requirements of the BECx section of the
project specifications, and;specifications;
4.1.1.6 Direct and substantive participation by the BECxP during the Pre-Construction, Construction, Bidding and
Negotiation, Pre-Construction, Construction Administration, and Occupancy & Operations phases of the BECx process, including
pre-construction laboratory and field performance testing as required in Annex A2 for Fundamental BECx.
4.1.2 Enhanced BECx—Architecture or engineering-related technical services, or both, performed on behalf of the Owner by
the BECxP and associated BECx group members in accordance with the requirements of Fundamental BECx, but with the
following additional requirements:
4.1.2.1 BECxP engagement during the Pre-Design Phase of the BECx process, but no later than commencement of the
Schematic Design sub-phase;
4.1.2.2 Technical assistance and documentation during the development of the preliminary OPR;
4.1.2.3 Technical assistance and documentation during the development of the BOD, contract documents, including the
project-specific BECx specification section, and final OPR during the Design Phase of the BECx process, including completion
of a minimum of three independent, third-party independent design peer reviews of enclosure-related construction document
drawings and specifications in a manner that will allow for timely review and consideration by the AOR prior to solicitation and
contract award, and;
4.1.2.4 Direct and substantive participation (see 4.2) by the BECxP and BECxG during the Pre-Construction, Construction,
Bidding and Negotiation, Pre-Construction, Construction Administration, and Occupancy and Operations phases of the BECx
process, including pre-construction laboratory and field performance testing as required in Annex A2 for Enhanced BECx.
4.2 This practice establishes that the BECxP shall assemble a team (BECxT)group (BECxG) that, at a minimum, demonstrates
a level of proficiency in the core competencies listed below that meetmeets or exceedexceeds the requirements of building codes,
standards, guidelines, and regulations applicable to or otherwise voluntarily adopted by the Owner to govern enclosure-related
design, construction, integration, and performance:and performance. Determination of the qualification of the BECxP and BECxG
will be at the discretion of the Owner:
4.2.1 BECxTBECxG Core Competencies:
4.2.1.1 Building and Materials Science, including, at a minimum, demonstrated knowledge of the:
(1) Principles associated with heat transfer via conduction, convection, radiation, and air infiltration/exfiltration;
(2) Principles associated with moisture storage and transport via gravity, diffusion, convection, capillary action, absorbed flow,
and osmosis; and
(3) Characteristics and behavior of enclosure-related materials, components, systems, and assemblies when specified for a
given application, geographic region, location, exposure, or climate, and corresponding influence on workability, durability,
serviceability, performance, and anticipated service-life.
(4) Principles of structural loading and structural capacity of enclosure-related materials, components, systems, and assemblies
for specified loads including: wind, earthquake, projectile, differential volume change, and kinetic energy and differential pressure
conditions.
4.2.1.2 Procurement and Project Delivery, including, at a minimum, demonstrated knowledge of the:
(1) Influence of the project delivery method selected by the Owner on the scope, adaptation, implementation, and cost of the
BECx process as defined in this practice;
(2) Influence of the number and type of contracts established between the Owner and the design and construction teams on
the role and responsibilities of the BECxP and individual members of the BECx team;group;
(3) Influence of design and construction scheduling, phasing, and sequencing of the work on the scope, adaptation,
implementation, and cost of the BECx process as defined in this practice;
(4) Influence of the experience, qualifications, technical depth, and commitment of the design and construction teams to the
BECx process on the role and responsibilities of the BECxP, the range and technical depth required of the BECx team,group, and
the anticipated scope and cost of the BECx process.
Though it is recognized that all parties participating in the design and construction of the building are part of the BECx process, for the purposes of this practice, the
BECx group (BECxG) is defined as the group of individuals, working under direct supervision of the BECxP. This group may be comprised of a single person or may include
multiple subject matter specialists and administrative staff. It is the responsibility of the BECxP to perform each required task or to delegate the appropriate task to the
appropriate Group member.
As outlined in ASHRAEANSI/ASHRAE/IES Standard 202 and Guide E2947, unless otherwise defined in this practice.
As defined in ASHRAEANSI/ASHRAE/IES Standard 202 and Guide E2947.
Including, but not limited to: Design-Build; Design-Bid-Build; Design-Negotiate-Build; Construction Management, and; Owner-Build as defined by CSI Project
Resource Manual and Manual of Practice.
Including, but not limited to Single-Prime Contract and Multiple-Prime Contracts, with basis-of-payment provisions that may include: Stipulated/Lump Sum; Cost-Plus
Fee; Fixed Fee, and; Guaranteed Maximum Price, with penalties, bonuses, and incentives for early completion of the work and liquidated damages for any delays in substantial
or final completion of the project.
E2813 − 18
4.2.1.3 Contract Documents and Construction Administration, including, at a minimum, demonstrated knowledge of the:
(1) Interrelationship and commonly understood hierarchy that exists between Procurement Documents, Contract Documents,
Contract Drawings and Specifications developed during the Design Phase of the BECx process, as well as submittals and legally
binding Instruments of Change issued during the Pre-Construction (Procurement) and Construction Phases of the BECx process,
including but not limited to: Addenda; Submittals; Architect’s Supplemental Instructions and Field Directives; Construction
Change Directives, and; Change Orders;
(2) Influence of enclosure-related design, detailing, and integration on total building performance, including at a minimum
consideration of the performance attributes listed in 1.5 and Annex A1 of this practice;
(3) Influence of product selection, allowable construction tolerances, and dimensional requirements to accommodate
environmental and service loads on detailing at interface conditions between enclosure-related materials, components, systems, and
assemblies, and; the corresponding influence on sequencing, phasing, and coordination of trades during the Construction Phase of
the BECx process;
(4) Importance of material compatibility and continuity of primary heat, air, and moisture control layers throughout the
building enclosure on total building performance and the appropriate mitigation of risks associated with improperly managed heat,
air, and moisture transport across the building enclosure;
(5) Importance of the timely preparation and distribution of subject-direct, technically sound, and actionable documentation
and feedback to the Owner, design, and construction teams throughout the Construction Phase of the BECx process.
4.2.1.4 Performance Test Standards and Methodology, including, at a minimum, demonstrated knowledge of the:
(1) Pre-construction laboratory and field-applied test standards and methodology referenced in this practice (see Annex A2) and
their intended use and application in evaluating the durability, performance, constructability, and anticipated service-life of
enclosure-related materials, components, systems, and assemblies;
(2) Importance of establishing appropriate and quantifiable thresholds of performance and clear and unambiguous definitions
of failure for enclosure-related materials, components, systems, and assemblies to validate the OPR and BOD, and to to allow
for proper enforcement of the contract documents;
(3) Influence of modifications to the intended use and application of pre-construction laboratory and field test standards and
methodology on the appropriate interpretation of test results and their relevance to the requirements of the contract documents;
(4) Importance of ensuringconfirming the timely, clear, and unambiguous translation of all modifications to the design,
construction, and integration of enclosure-related materials, components, systems, and assemblies arising from pre-construction
laboratory testing to the field during the Construction Phase of the BECx process;
(5) Importance of recognizing the distinction between errors and omissions in architectural or product design, or both, versus
defective installation or workmanship, or both, when interpreting field test results, and; the techniques available during the
development and implementation of field testing protocols that will minimize the risk for confusion and misinterpretation relative
to the requirements of the contract documents;
(6) Distinction between test standards and methodologies “recognized in the industry” or otherwise developed by industry or
trade associations versus test standards developed by independent standards-writing organizations and the impact, if any, on the
enforcement of the contract documents when both are included in the project specifications.
5. Procedure
5.1 This practice establishes that the BECx process shall be as outlined in ASHRAEANSI/ASHRAE/IES Standard 202 and
Guide E2947 and include, at a minimum, the following:
5.1.1 Pre-Design Phase:
5.1.1.1 Attend a project planning conference (“Kick-Off Meeting”);
5.1.1.2 Review the functional and programmatic requirements for the project established by the Owner and AOR;
5.1.1.3 Review and discuss factors influencing enclosure design, construction, long-term durability, serviceability, and
performance with the Owner and AOR (if retained), including at a minimum (see also Annex A1):
(1) Anticipated construction type, importance factor, and occupancy/use classification;
(2) Geographic location and climate;
(3) Site orientation, massing, and options for enclosure material selection, integration, and relative distribution at each building
exposure that will consider:
(a) Identification and apportionment of initial enclosure costs;
(b) Occupant comfort, productivity, and rate of return on initial investment;
As defined by the Construction Specifications Institute (CSI).
Including, but not limited to integration with base building structural and environmental control systems.
Including the limitations associated with each test standard.
Including remedial action required in the event of failure and the nature and extent of re-testing necessary to verifyevaluate compliance of the repair(s) with the
requirements of the contract documents.
The Pre-Design Phase is the BECxP minimum point-of-engagement required to qualify as Enhanced BECx under this practice. Refer to ASHRAEANSI/ASHRAE/IES
Standard 202 and Guide E2947 for additional steps associated with this phase of the BECx process.
E2813 − 18
(c) Enclosure long-term durability and performance;
(d) Costs associated with routine maintenance and energy use;
(e) Sustainable design objectives with long-term durability and performance;
(f) Optimize acoustical requirements; and
(g) Safety and security requirements.
(4) Consideration of exemplars that may exist in the same region or climate for which actual as-built enclosure performance
can be quantifiably evaluated.
5.1.1.4 Provide technical assistance to the Owner during the development of a written OPR for enclosure materials, components,
systems, and assemblies in accordance with Annex A1 of this practice, including at a minimum an evaluation of the
interrelationship between the following performance attributes and the relative influence of each on enclosure durability, enclosure,
performance, and total cost of ownership:
(1) Energy
(2) Environment
(3) Safety
(4) Security
(5) Durability
(6) Sustainability
(7) Operation
5.1.1.5 Provide a summary of the preliminary BECx Plan scope and budget to the Owner.
5.1.2 Design Phase:
5.1.2.1 Review and document the OPR and preliminary BECx Plan developed during the Pre-Design phase of the BECx
process;
5.1.2.2 Review and provide technical assistance during the development of the preliminary enclosure BOD;
5.1.2.3 Provide or otherwise coordinate the completion of an independent, third-party independent design peer review of
enclosure-related construction document drawings and specifications based on the following sub-phases of the design process:
(1) Schematic Design
(2) Design Development
(3) Construction Documents
5.1.2.4 Update, refine, and document the OPR, enclosure BOD, and BECx Plan at the conclusion of each sub-phase of the
design process;
5.1.2.5 Establish appropriate and quantifiable enclosure-related performance metrics, test standards, and test methodology in
accordance with Annex A2 for incorporation into the contract documents, including:
(1) Preconstruction laboratory mockups;
(2) Field-constructed “off-structure” mockups;
(3) Field-constructed “on-structure,” first-installation mockups;
(4) Field testing at milestone intervals during construction;
(5) Post-occupancy evaluation and performance testing.
5.1.2.6 Provide a formal, written response to the position(s) taken by the AOR and other contracted parties to the project in
response to BECxPBECxP/BECxG comments and recommendations, including BECxPBECxP/BECxG recommendations not
accepted by the AOR and a summary discussion of the relative advantages, disadvantages, and potential risks associated with each
of those decisions on building enclosure durability, performance, and total cost of ownership.
5.1.2.7 Document Confirm documentation of the Design Phase OPR, enclosure BOD, and BECx Plan for review and approval
by the Owner.
5.1.3 Pre-Construction Bidding and Negotiation Phase:
5.1.3.1 Attend a Pre-Bid Conference to review the BECx specification with prospective bidders;
5.1.3.2 Review and assist with the by providing Owner requested evaluation of enclosure-related bidder requests for
information or clarification and assist the AOR and Owner with the development of Addenda as appropriate;
5.1.3.3 Review and assist with the evaluation of enclosure-related contractor/subcontractor bids, including at a minimum:
(1) Scheduling, phasing, and coordination of trades;
(2) Quality Assurance (QA) and Quality Control (QC) programs;
(3) Qualifications and Exclusions; and
Refer also to Guide E2947 for additional information regarding development of the OPR document.
The Design Phase is the BECxP minimum point-of-engagement required to qualify as Fundamental BECx under this practice. Refer to ASHRAEANSI/ASHRAE/IES
Standard 202 and Guide E2947 for additional steps associated with this phase of the BECx process.
Including retro-active development of a written OPR document based on input provided by the Owner in circumstances where a formal written OPR may not exist but
is required to qualify as Fundamental BECx under this practice.
Required to qualify for Enhanced BECx under this practice (optional for Fundamental BECx).
Required to qualify for both Fundamental and Enhanced BECx.
Documentation shall be provided as part of the updated OPR.
E2813 − 18
(4) Substitutions and “Value Engineering” options.
5.1.3.4 Document Confirm documentation of the Pre-Construction Phase OPR, enclosure BOD, and BECx Plan for review and
approval by the Owner.
5.1.4 Construction Phase:
5.1.4.1 Technical assistance during the review of enclosure-related shop drawings and technical submittals for compliance with
the contract documents;
5.1.4.2 Direct and substantive Substantive participation in a Pre-Construction Meeting and Pre-Installation Meetings with the
GC, CM, and enclosure-related subcontractors and trades to review and document, at a minimum:
(1) Final approved OPR, enclosure BOD, and BECx Plan;
(2) Status of all outstanding shop drawings and technical submittals;
(3) Schedule, phasing, and coordination of enclosure-related subcontractors and trades;
(4) GC, CM, subcontractor, and enclosure-related trade QA, QC, QA and safetyQC programs;
(5) Subcontractor qualifications, exclusions, and conditions associated with the construction of a fully integrated building
enclosure that may influence product, material, or installation warranties;
(6) Test standards and methodologies, performance thresholds, appropriate interpretation of test results, and definitions of
failure required in the contract documents;
(7) On-site construction observation and documentation protocol established for the timely identification and remediation of
hidden/concealed or otherwise unanticipated conditions in the field, enclosure-related product or installation defects, and
non-conforming work;
(8) Modification or refinement of enclosure-related detailing, fabrication, installation requirements, or sequencing and
coordination of trades, or a combination thereof, arising from pre-construction mock-up assembly and testing.
5.1.4.3 Direct and substantive Substantive participation during in-plant QA and QC reviews including, at a minimum, review
and documentation of the methodology of:
(1) Industry standard quality control criteria that may be applicable to the procurement or manufacture, or both, of the
materials, components, systems, and assemblies specified for the project;
(2) Methodology established to identify, track, and remediate, at milestone intervals during production, all defective and
nonconforming work;
(3) Product or project-specific in-house technical training programs;
(4) In-house performance testing capabilities available for application to completed components and assemblies at milestone
intervals during production.
5.1.4.4 On-site construction observation and documentation, including:
(1) Periodic observation, evaluation, and documentation of enclosure-related work in progress at representative locations on
the project for compliance with the contract documents;
(2) Development and distribution of field observation reports, field test reports, and related documentation as required for
timely and effective review and remedial action by the GC, CM, and appropriate subcontractors and trades;
(3) Coordination of and attendance at regularly scheduled BECx meetings with the GC, CM, and appropriate subcontractors
and trades;
(4) Review and documentation of enclosure-related field performance testing at milestone intervals throughout construction
for compliance with the requirements of the contract documents, including at a minimum:
(a) Review and documentation of the design and construction of all field-constructed test chambers and verification of current
calibration of all test equipment as required by the governing industry standard for the test method specified;
(b) Review and clarification of test procedures and methodology, performance thresholds, and definition(s) of “non-
compliance” or “failure” as required in the contract documents.
Reference ASHRAEANSI/ASHRAE/IES Standard 202 and Guide E2947 for additional information.
Including, but not limited to, meetings in preparation for pre-construction laboratory or field-construc
...








Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.
Loading comments...