Electrical equipment for measurement, control and laboratory use - EMC requirements - Part 2-7: Particular requirements - Test configurations, operational conditions, test levels and performance criteria for devices with Ethernet-APL interfaces (IEC 61326-2-7:2025)

In addition to the requirements of IEC 61326-1, this part of IEC 61326 specifies the EMC test
requirements for process automation equipment using at least one Ethernet-APL (Ethernet
ADVANCED PHYSICAL LAYER) compliant port according IEC TS 63444. The type of equipment
covered by this document includes INFRASTRUCTURE DEVICES such as switches as well as
measurement and control devices. This document provides requirements for the EMC test
setups of the APL interface for devices intended for use in process control and process
measurement.
The other functions of the equipment remain covered by other parts of the IEC 61326 series.
NOTE Ethernet-APL uses IEEE Std. 802.3-2022 Ethernet Physical Layer 10BASE-T1L, suitable to be used for full-
duplex communication over a single balanced pair of conductors.
The test levels are based on the intended environment as stated in the product’s specification
or user documentation and selected appropriately from IEC 61326-1.

Elektrische Mess-, Steuer-, Regel- und Laborgeräte - EMV-Anforderungen - Teil 2-7: Besondere Anforderungen - Prüfkonfigurationen, Betriebsbedingungen, Prüfstufen und Leistungskriterien für Geräte mit Ethernet-APL-Schnittstellen (IEC 61326-2-7:2025)

Električna oprema za merjenje, nadzor in laboratorijsko uporabo - Zahteve za elektromagnetno združljivost (EMC) - 2-7. del: Posebne zahteve - Preskusne konfiguracije, obratovalni pogoji, preskusne ravni in merila zmogljivosti za naprave z Ethernet-APL vmesniki

Poleg zahtev iz IEC 61326-1 ta del IEC 61326 določa zahteve za EMC preskuse za opremo za avtomatizacijo procesov, ki uporablja vsaj en priključek, skladen z Ethernet-APL (Ethernet ADVANCED PHYSICAL LAYER), v skladu z IEC TS 63444. Vrste opreme, ki jih zajema ta dokument, vključujejo INFRASTRUKTURNE NAPRAVE, kot so stikala, ter merilne in krmilne naprave. Ta dokument določa zahteve za EMC preskusne postavitve APL vmesnika za naprave, namenjene uporabi v procesnem krmiljenju in procesnem merjenju.
Druge funkcije opreme ostajajo pokrite z drugimi deli serije IEC 61326.
OPOMBA Ethernet-APL uporablja IEEE Std. 802.3-2022 Ethernet Physical Layer 10BASE-T1L, primeren za uporabo za polno-dupleks komunikacijo preko enega uravnoteženega para vodnikov. Preskusne ravni temeljijo na predvidenem okolju, kot je navedeno v specifikaciji izdelka ali uporabniški dokumentaciji, in so ustrezno izbrane iz IEC 61326-1.

General Information

Status
Not Published
Public Enquiry End Date
29-Jun-2026
Current Stage
4020 - Public enquire (PE) (Adopted Project)
Start Date
30-Apr-2026
Due Date
17-Sep-2026

Relations

Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026
Effective Date
28-Apr-2026

Buy Documents

Draft

oSIST prEN IEC 61326-2-7:2026

English language (44 pages)
Preview
Preview
e-Library read for
1 day

Get Certified

Connect with accredited certification bodies for this standard

DVS-ZERT GmbH

German welding certification society.

DAKKS Germany Verified

IMP NDT d.o.o.

Non-destructive testing services. Radiography, ultrasonic, magnetic particle, penetrant, visual inspection.

SA Slovenia Verified

Inštitut za kovinske materiale in tehnologije

Institute of Metals and Technology. Materials testing, metallurgical analysis, NDT.

SA Slovenia Verified

Sponsored listings

Frequently Asked Questions

oSIST prEN IEC 61326-2-7:2026 is a draft published by the Slovenian Institute for Standardization (SIST). Its full title is "Electrical equipment for measurement, control and laboratory use - EMC requirements - Part 2-7: Particular requirements - Test configurations, operational conditions, test levels and performance criteria for devices with Ethernet-APL interfaces (IEC 61326-2-7:2025)". This standard covers: In addition to the requirements of IEC 61326-1, this part of IEC 61326 specifies the EMC test requirements for process automation equipment using at least one Ethernet-APL (Ethernet ADVANCED PHYSICAL LAYER) compliant port according IEC TS 63444. The type of equipment covered by this document includes INFRASTRUCTURE DEVICES such as switches as well as measurement and control devices. This document provides requirements for the EMC test setups of the APL interface for devices intended for use in process control and process measurement. The other functions of the equipment remain covered by other parts of the IEC 61326 series. NOTE Ethernet-APL uses IEEE Std. 802.3-2022 Ethernet Physical Layer 10BASE-T1L, suitable to be used for full- duplex communication over a single balanced pair of conductors. The test levels are based on the intended environment as stated in the product’s specification or user documentation and selected appropriately from IEC 61326-1.

In addition to the requirements of IEC 61326-1, this part of IEC 61326 specifies the EMC test requirements for process automation equipment using at least one Ethernet-APL (Ethernet ADVANCED PHYSICAL LAYER) compliant port according IEC TS 63444. The type of equipment covered by this document includes INFRASTRUCTURE DEVICES such as switches as well as measurement and control devices. This document provides requirements for the EMC test setups of the APL interface for devices intended for use in process control and process measurement. The other functions of the equipment remain covered by other parts of the IEC 61326 series. NOTE Ethernet-APL uses IEEE Std. 802.3-2022 Ethernet Physical Layer 10BASE-T1L, suitable to be used for full- duplex communication over a single balanced pair of conductors. The test levels are based on the intended environment as stated in the product’s specification or user documentation and selected appropriately from IEC 61326-1.

oSIST prEN IEC 61326-2-7:2026 is classified under the following ICS (International Classification for Standards) categories: 17.220.20 - Measurement of electrical and magnetic quantities; 19.080 - Electrical and electronic testing; 25.040.40 - Industrial process measurement and control; 33.100.01 - Electromagnetic compatibility in general; 33.100.20 - Immunity. The ICS classification helps identify the subject area and facilitates finding related standards.

oSIST prEN IEC 61326-2-7:2026 has the following relationships with other standards: It is inter standard links to SIST EN 61000-4-4:2013, SIST EN IEC 61000-3-2:2019, SIST EN IEC 61000-3-11:2019, SIST EN 61000-3-3:2014, SIST EN IEC 61000-4-3:2021, SIST EN IEC 61000-4-11:2020, SIST EN 61000-3-12:2012, SIST EN 61000-4-29:2003, SIST EN IEC 55011:2025, SIST EN IEC 61000-4-6:2023, SIST EN IEC 61326-1:2021, SIST EN 61000-4-16:2016, SIST EN 61000-4-8:2010, SIST EN 61000-4-5:2014, SIST EN IEC 61000-4-2:2025. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.

oSIST prEN IEC 61326-2-7:2026 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)


SLOVENSKI STANDARD
01-junij-2026
Električna oprema za merjenje, nadzor in laboratorijsko uporabo - Zahteve za
elektromagnetno združljivost (EMC) - 2-7. del: Posebne zahteve - Preskusne
konfiguracije, obratovalni pogoji, preskusne ravni in merila zmogljivosti za
naprave z Ethernet-APL vmesniki
Electrical equipment for measurement, control and laboratory use - EMC requirements -
Part 2-7: Particular requirements - Test configurations, operational conditions, test levels
and performance criteria for devices with Ethernet-APL interfaces (IEC 61326-2-7:2025)
Elektrische Mess-, Steuer-, Regel- und Laborgeräte - EMV-Anforderungen - Teil 2-7:
Besondere Anforderungen - Prüfkonfigurationen, Betriebsbedingungen, Prüfstufen und
Leistungskriterien für Geräte mit Ethernet-APL-Schnittstellen (IEC 61326-2-7:2025)
Ta slovenski standard je istoveten z: prEN IEC 61326-2-7:2026
ICS:
19.080 Električno in elektronsko Electrical and electronic
preskušanje testing
25.040.40 Merjenje in krmiljenje Industrial process
industrijskih postopkov measurement and control
33.100.01 Elektromagnetna združljivost Electromagnetic compatibility
na splošno in general
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

EUROPEAN STANDARD DRAFT
prEN IEC 61326-2-7
NORME EUROPÉENNE
EUROPÄISCHE NORM
April 2026
ICS 17.220.20; 25.040.40; 33.100.20 -
English Version
Electrical equipment for measurement, control and laboratory
use - EMC requirements - Part 2-7: Particular requirements -
Test configurations, operational conditions, test levels and
performance criteria for devices with Ethernet-APL interfaces
(IEC 61326-2-7:2025)
To be completed Elektrische Mess-, Steuer-, Regel- und Laborgeräte - EMV-
(IEC 61326-2-7:2025) Anforderungen - Teil 2-7: Besondere Anforderungen -
Prüfkonfigurationen, Betriebsbedingungen, Prüfstufen und
Leistungskriterien für Geräte mit Ethernet-APL-
Schnittstellen
(IEC 61326-2-7:2025)
This draft European Standard is submitted to CENELEC members for enquiry.
Deadline for CENELEC: 2026-07-17.

The text of this draft consists of the text of IEC 61326-2-7:2025.

If this draft becomes a European Standard, CENELEC members are bound to comply with the CEN/CENELEC Internal Regulations which
stipulate the conditions for giving this European Standard the status of a national standard without any alteration.

This draft European Standard was established by CENELEC in three official versions (English, French, German).
A version in any other language made by translation under the responsibility of a CENELEC member into its own language and notified to
the CEN-CENELEC Management Centre has the same status as the official versions.

CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Türkiye and the United Kingdom.

Recipients of this draft are invited to submit, with their comments, notification of any relevant patent rights of which they are aware and to
provide supporting documentation.

Warning : This document is not a European Standard. It is distributed for review and comments. It is subject to change without notice and
shall not be referred to as a European Standard.

European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2026 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Project: 83224 Ref. No. prEN IEC 61326-2-7:2026 E

European foreword
This document (prEN IEC 61326-2-7:2026) consists of the text of IEC 61326-2-7:2025 prepared by
IEC/TC 65 "Industrial-process measurement, control and automation".
This document is currently submitted to the Enquiry.
The following dates are proposed:
• latest date by which the existence of this document (doa) dav + 6 months
has to be announced at national level
• latest date by which this document has to be (dop) dav + 12 months
implemented at national level by publication of an
identical national standard or by endorsement
• latest date by which the national standards (dow) dav + 36 months
conflicting with this document have to be withdrawn (to be confirmed or
modified when voting)
Annex ZA
(normative)
Normative references to international publications
with their corresponding European publications
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments)
applies.
NOTE 1  Where an International Publication has been modified by common modifications, indicated by (mod),
the relevant EN/HD applies.
NOTE 2  Up-to-date information on the latest versions of the European Standards listed in this annex is available
here: www.cencenelec.eu.
Publication Year Title EN/HD Year
IEC 60050-161 1990 International Electrotechnical Vocabulary. - -
Chapter 161: Electromagnetic compatibility
IEC 61000-3-2 - Electromagnetic compatibility (EMC) - Part EN IEC 61000-3-2 -
3-2: Limits - Limits for harmonic current
emissions (equipment input current ≤16 A
per phase)
IEC 61000-3-3 - Electromagnetic compatibility (EMC) - Part EN 61000-3-3 -
3-3: Limits - Limitation of voltage changes,
voltage fluctuations and flicker in public
low-voltage supply systems, for equipment
with rated current ≤16 A per phase and not
subject to conditional connection
IEC 61000-3-11 - Electromagnetic compatibility (EMC) - Part EN IEC 61000-3-11 -
3-11: Limits - Limitation of voltage
changes, voltage fluctuations and flicker in
public low-voltage supply systems -
Equipment with rated current ≤ 75 A and
subject to conditional connection
IEC 61000-3-12 - Electromagnetic compatibility (EMC) - Part EN 61000-3-12 -
3-12: Limits - Limits for harmonic currents
produced by equipment connected to
public low-voltage systems with input
current >16 A and ≤75 A per phase
IEC 61000-4-2 2025 Electromagnetic compatibility (EMC) - Part EN IEC 61000-4-2 2025
4-2: Testing and measurement techniques
- Electrostatic discharge immunity test
IEC 61000-4-3 2020 Electromagnetic compatibility (EMC) - Part EN IEC 61000-4-3 2020
4-3 : Testing and measurement techniques
- Radiated, radio-frequency,
electromagnetic field immunity test
IEC 61000-4-4 2012 Electromagnetic compatibility (EMC) - Part EN 61000-4-4 2012
4-4: Testing and measurement techniques
- Electrical fast transient/burst immunity
test
Publication Year Title EN/HD Year
IEC 61000-4-5 2014 Electromagnetic compatibility (EMC) - Part EN 61000-4-5 2014
4-5: Testing and measurement techniques
- Surge immunity test
IEC 61000-4-6 2023 Electromagnetic compatibility (EMC) - Part EN IEC 61000-4-6 2023
4-6: Testing and measurement techniques
- Immunity to conducted disturbances,
induced by radio-frequency fields
IEC 61000-4-8 2009 Electromagnetic compatibility (EMC) - Part EN 61000-4-8 2010
4-8: Testing and measurement techniques
- Power frequency magnetic field immunity
test
IEC 61000-4-11 2020 Electromagnetic compatibility (EMC) - Part EN IEC 61000-4-11 2020
4-11: Testing and measurement
techniques - Voltage dips, short
interruptions and voltage variations
immunity tests for equipment with input
current up to 16 A per phase
IEC 61000-4-16 2015 Electromagnetic compatibility (EMC) - Part EN 61000-4-16 2016
4-16: Testing and measurement
techniques - Test for immunity to
conducted, common mode disturbances in
the frequency range 0 Hz to 150 kHz
IEC 61000-4-29 2000 Electromagnetic compatibility (EMC) - Part EN 61000-4-29 2000
4-29: Testing and measurement
techniques - Voltage dips, short
interruptions and voltage variations on d.c.
input power port immunity tests
IEC 61326-1 2020 Electrical equipment for measurement, EN IEC 61326-1 2021
control and laboratory use - EMC
requirements - Part 1: General
requirements
IEC/TS 63444 2023 Industrial networks - Ethernet-APL port - -
profile specification
CISPR 11 2024 Industrial, scientific and medical equipment EN IEC 55011 2025
- Radio-frequency disturbance
characteristics - Limits and methods of
measurement
IEEE 802.3 2022 IEEE Standard for Ethernet - -

IEC 61326-2-7 ®
Edition 1.0 2025-12
INTERNATIONAL
STANDARD
Electrical equipment for measurement, control and laboratory use - EMC
requirements -
Part 2-7: Particular requirements - Test configurations, operational conditions,
test levels and performance criteria for devices with Ethernet-APL interfaces
ICS 17.220.20; 25.040.40; 33.100.20 ISBN 978-2-8327-0892-7

IEC 61326-2-7:2025-12(en)
IEC 61326-2-7:2025 © IEC 2025
CONTENTS
FOREWORD . 3
1 Scope . 5
2 Normative references . 5
3 Terms, definitions and abbreviated terms . 6
3.1 Terms and definitions . 6
3.2 Abbreviated terms. 9
4 General . 10
4.1 General . 10
4.2 General considerations on EMC testing of devices with APL interface . 10
4.3 Structure of an APL system . 10
4.4 Structure of the shield connection of an APL system . 11
5 EMC test plan . 12
5.1 General . 12
5.2 Configuration of EUT during testing . 14
5.3 Operating conditions of EUT during testing . 14
5.4 Specification of functional performance . 14
5.5 Test description . 14
6 Immunity requirements . 15
6.1 General . 15
6.2 Conditions during the test . 15
6.3 Immunity test requirements . 15
6.3.1 General. 15
6.3.2 EMC test setup . 18
6.4 Random aspects . 36
6.5 Performance criteria. 36
6.5.1 General. 36
6.5.2 Performance criterion A . 37
6.5.3 Performance criterion B . 37
6.5.4 Performance criterion C . 37
7 Emission requirements . 37
7.1 Conditions during measurements . 37
7.2 Emission limits . 38
8 Test results and test report . 38
9 Instruction for use . 38
Bibliography . 39

Figure 1 – APL system structure for APL FIELD SWITCHES with Ethernet UPLINK PORT(S) . 10
Figure 2 – APL system structure for APL FIELD SWITCHES with APL TRUNK powered port(s). 11
Figure 3 – APL infrastructure overview . 12
Figure 4 – APL EMC TEST MASTER communication . 13
Figure 5 – ESD test setup for an APL FIELD DEVICE with APL PORT and optional power
supply port . 19
Figure 6 – Radiated RF test setup for an APL FIELD DEVICE with APL PORT and optional
power supply port . 20
IEC 61326-2-7:2025 © IEC 2025
Figure 7 – Burst test setup for an APL FIELD DEVICE with APL PORT and optional
power port . 21
Figure 8 – Surge test setup for an APL FIELD DEVICE with APL PORT and optional
power port . 21
Figure 9 – Surge test setup for an APL FIELD DEVICE with APL PORT – detailed test setup
for shielded lines . 22
Figure 10 – Conducted RF test setup for an APL FIELD DEVICE with APL PORT and
optional power port . 22
Figure 11 – Conducted common mode voltage test setup for an APL FIELD DEVICE with
APL PORT and optional power port . 23
Figure 12 – ESD test setup for APL FIELD SWITCHES with Ethernet UPLINK PORT(S). 24
Figure 13 – ESD test setup for APL FIELD SWITCHES with APL TRUNK powered port(s) . 25
Figure 14 – ESD test setup for APL POWER SWITCHES . 26
Figure 15 – Radiated RF test setup for APL FIELD SWITCHES with Ethernet UPLINK
PORT(S) . 27
Figure 16 – Radiated RF test setup for APL FIELD SWITCHES with APL TRUNK powered
port(s) . 27
Figure 17 – Radiated RF test setup for APL POWER SWITCHES . 28
Figure 18 – Burst test setup for APL FIELD SWITCHES with Ethernet UPLINK PORT(S) . 29
Figure 19 – Burst test setup for APL FIELD SWITCHES with APL TRUNK powered port(s). 29
Figure 20 – Burst test setup for APL POWER SWITCHES . 30
Figure 21 – Surge test for APL PORTS . 31
Figure 22 – Conducted RF test setup for APL FIELD SWITCHES with Ethernet UPLINK
PORT(S) . 32
Figure 23 – Conducted RF test setup for APL FIELD SWITCHES with APL TRUNK powered
port(s) . 32
Figure 24 – Conducted RF test setup for APL POWER SWITCHES . 33
Figure 25 – Conducted common mode voltage test setup for APL FIELD SWITCHES with
Ethernet UPLINK PORT(s) . 34
Figure 26 – Conducted common mode voltage test setup for APL FIELD SWITCHES with
APL TRUNK powered port(s) . 35
Figure 27 – Conducted common mode voltage test setup for APL POWER SWITCHES . 36

Table 1 – Minimum required shielding options a port shall provide . 11
Table 2 – Cable type and length connected to the EUT ports . 14
Table 3 – Immunity test requirements for equipment intended to be used in an
INDUSTRIAL ELECTROMAGNETIC ENVIRONMENT . 16
Table 4 – Immunity test requirements for equipment intended to be used in a SPECIFIED
ELECTROMAGNETIC PROCESS CONTROL ENVIRONMENT . 17

IEC 61326-2-7:2025 © IEC 2025
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
Electrical equipment for measurement, control and laboratory use -
EMC requirements -
Part 2-7: Particular requirements - Test configurations, operational
conditions, test levels and performance criteria
for devices with Ethernet-APL interfaces

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote international
co-operation on all questions concerning standardization in the electrical and electronic fields. To this end and
in addition to other activities, IEC publishes International Standards, Technical Specifications, Technical Reports,
Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC Publication(s)”). Their
preparation is entrusted to technical committees; any IEC National Committee interested in the subject dealt with
may participate in this preparatory work. International, governmental and non-governmental organizations liaising
with the IEC also participate in this preparation. IEC collaborates closely with the International Organization for
Standardization (ISO) in accordance with conditions determined by agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence between
any IEC Publication and the corresponding national or regional publication shall be clearly indicated in the latter.
5) IEC itself does not provide any attestation of conformity. Independent certification bodies provide conformity
assessment services and, in some areas, access to IEC marks of conformity. IEC is not responsible for any
services carried out by independent certification bodies.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) IEC draws attention to the possibility that the implementation of this document may involve the use of (a)
patent(s). IEC takes no position concerning the evidence, validity or applicability of any claimed patent rights in
respect thereof. As of the date of publication of this document, IEC had not received notice of (a) patent(s), which
may be required to implement this document. However, implementers are cautioned that this may not represent
the latest information, which may be obtained from the patent database available at https://patents.iec.ch. IEC
shall not be held responsible for identifying any or all such patent rights.
IEC 61326-2-7 has been prepared by subcommittee 65A: System aspects, of IEC technical
committee 65: Industrial-process measurement, control and automation. It is an International
Standard.
The text of this International Standard is based on the following documents:
Draft Report on voting
65A/1190/FDIS 65A/1196/RVD
Full information on the voting for its approval can be found in the report on voting indicated in
the above table.
IEC 61326-2-7:2025 © IEC 2025
The language used for the development of this International Standard is English.
This document was drafted in accordance with ISO/IEC Directives, Part 2, and developed in
accordance with ISO/IEC Directives, Part 1 and ISO/IEC Directives, IEC Supplement, available
at www.iec.ch/members_experts/refdocs. The main document types developed by IEC are
described in greater detail at www.iec.ch/publications.
Words in SMALL CAPITALS in the text are defined in Clause 3.
A list of all parts of the IEC 61326 series, under the general title Electrical equipment for
measurement, control and laboratory use - EMC requirements, can be found on the IEC website.
The committee has decided that the contents of this document will remain unchanged until the
stability date indicated on the IEC website under webstore.iec.ch in the data related to the
specific document. At this date, the document will be
– reconfirmed,
– withdrawn, or
– revised.
IEC 61326-2-7:2025 © IEC 2025
1 Scope
In addition to the requirements of IEC 61326-1, this part of IEC 61326 specifies the EMC test
requirements for process automation equipment using at least one Ethernet-APL (Ethernet
ADVANCED PHYSICAL LAYER) compliant port according IEC TS 63444. The type of equipment
covered by this document includes INFRASTRUCTURE DEVICES such as switches as well as
measurement and control devices. This document provides requirements for the EMC test
setups of the APL interface for devices intended for use in process control and process
measurement.
The other functions of the equipment remain covered by other parts of the IEC 61326 series.
NOTE Ethernet-APL uses IEEE Std. 802.3-2022 Ethernet Physical Layer 10BASE-T1L, suitable to be used for full-
duplex communication over a single balanced pair of conductors.
The test levels are based on the intended environment as stated in the product’s specification
or user documentation and selected appropriately from IEC 61326-1.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies.
For undated references, the latest edition of the referenced document (including any
amendments) applies.
IEC 60050-161:1990, International Electrotechnical Vocabulary (IEV) - Part 161:
Electromagnetic compatibility
IEC 61000-3-2, Electromagnetic compatibility (EMC) - Part 3-2: Limits - Limits for harmonic
current emissions (equipment input current ≤16 A per phase)
IEC 61000-3-3, Electromagnetic compatibility (EMC) - Part 3-3: Limits - Limitation of voltage
changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment
with rated current ≤16 A per phase and not subject to conditional connection
IEC 61000-3-11, Electromagnetic compatibility (EMC) - Part 3-11: Limits - Limitation of voltage
changes, voltage fluctuations and flicker in public low-voltage supply systems - Equipment with
rated current ≤ 75 A and subject to conditional connection
IEC 61000-3-12, Electromagnetic compatibility (EMC) - Part 3-12: Limits - Limits for harmonic
currents produced by equipment connected to public low-voltage systems with input current >16
A and ≤ 75 A per phase
IEC 61000-4-2:2025, Electromagnetic compatibility (EMC) - Part 4-2: Testing and measurement
techniques - Electrostatic discharge immunity test
IEC 61000-4-3:2020, Electromagnetic compatibility (EMC) - Part 4-3: Testing and measurement
techniques - Radiated, radio-frequency, electromagnetic field immunity test
IEC 61000-4-4:2012, Electromagnetic compatibility (EMC) - Part 4-4: Testing and measurement
techniques - Electrical fast transient/burst immunity test
IEC 61000-4-5:2014, Electromagnetic compatibility (EMC) - Part 4-5: Testing and measurement
techniques - Surge immunity test
IEC 61000-4-6:2023, Electromagnetic compatibility (EMC) - Part 4-6: Testing and measurement
techniques - Immunity to conducted disturbances, induced by radio-frequency fields
IEC 61326-2-7:2025 © IEC 2025
IEC 61000-4-8:2009, Electromagnetic compatibility (EMC) - Part 4-8: Testing and measurement
techniques - Power frequency magnetic field immunity test
IEC 61000-4-11:2020, Electromagnetic compatibility (EMC) - Part 4-11: Testing and
measurement techniques - Voltage dips, short interruptions and voltage variations immunity
tests for equipment with input current up to 16 A per phase
IEC 61000-4-16:2015, Electromagnetic compatibility (EMC) - Part 4-16: Testing and
measurement techniques - Test for immunity to conducted, common mode disturbances in the
frequency range 0 Hz to 150 kHz
IEC 61000-4-29:2000, Electromagnetic compatibility (EMC) - Part 4-29: Testing and
measurement techniques - Voltage dips, short interruptions and voltage variations on d.c. input
power port immunity tests
IEC 61326-1:2020, Electrical equipment for measurement, control and laboratory use - EMC
requirements - Part 1: General requirements
IEC TS 63444:2023, Industrial networks - Ethernet-APL port profile specification
CISPR 11:2024, Industrial, scientific and medical equipment - Radio-frequency disturbance
characteristics - Limits and methods of measurement
IEEE Std 802.3-2022, IEEE Standard for Ethernet
3 Terms, definitions and abbreviated terms
3.1 Terms and definitions
For the purposes of this document, the terms and definitions given in IEC 60050-161 and the
following apply.
ISO and IEC maintain terminology databases for use in standardization at the following
addresses:
– IEC Electropedia: available at https://www.electropedia.org/
– ISO Online browsing platform: available at https://www.iso.org/obp
3.1.1
advanced physical layer
APL
physical layer, specified in IEC TS 63444, based on 10BASE-T1L according to
IEEE Std 802.3-2022 with additional optional features like intrinsic safety, power over 2 wires
3.1.2
APL EMC test master
device used for testing the communication as well as for testing the process date integrity of a
FIELD DEVICE
Note 1 to entry: It is providing an Ethernet port, which can be directly connected to the EUT or connected to the
EUT using an APL FIELD SWITCH or APL POWER SWITCH. Additionally, the APL EMC TEST MASTER will provide at least one
failure output to indicate a disturbed communication.
3.1.3
APL field device
device with one SPUR load port which sends or receives process values
Note 1 to entry: In addition, it can have an optional power supply port.
IEC 61326-2-7:2025 © IEC 2025
3.1.4
APL segment
segment that consists of two F ports, each containing a 10BASE-T1L compatible PHY,
connected at each end of a two-wire, shielded cable
Note 1 to entry: An APL SEGMENT can optionally be equipped with a maximum of two AUXILIARY DEVICES and can
contain up to 10 inline terminal CONNECTIONS. An AUXILIARY DEVICE corresponds to one inline CONNECTION; for
example, having two AUXILIARY DEVICES connected to one APL SEGMENT will reduce the number of inline CONNECTIONS
by two.
Note 2 to entry: An APL SEGMENT is either a TRUNK or a SPUR.
3.1.5
APL switch
Ethernet switch including at least one APL compliant port
3.1.6
APL port
electrical and mechanical interface of a device to an APL SEGMENT
3.1.7
auxiliary device
device that is connected within an APL SEGMENT and does not include a 10BASE-T1L PHY, e.g.
it could comprise a power load or introduce communication signal insertion losses
Note 1 to entry: A surge protector is an example of an AUXILIARY DEVICE.
3.1.8
connection
inline connection
mated device or combination of devices used to connect cables or cable elements to other
cables or application specific equipment
3.1.9
cascade port
APL PORT used in powered daisy chain networks
Note 1 to entry: If the CASCADE PORT is used in a powered ring network, it shall be either a power source port or a
power load port depending on the status of the ring.
3.1.10
degradation (in performance)
undesired departure in the operational performance of any device, equipment or system from
its intended performance
Note 1 to entry: The term "DEGRADATION" can apply to temporary or permanent failure.
[SOURCE: IEC 60050-161:1990, 161-01-19]
3.1.11
field switch
APL SWITCH having at least one port to which a SPUR can be connected
3.1.12
infrastructure device
SPUR port and at least one ethernet UPLINK PORT
device with at least one
IEC 61326-2-7:2025 © IEC 2025
3.1.13
industrial electromagnetic environment
environment existing at locations characterized by a separate power network, in most cases
supplied from a high- or medium-voltage transformer, dedicated for the supply of installations
feeding manufacturing or similar plants with one or more of the following conditions:
– frequent switching of heavy inductive or capacitive loads,
– high currents and associated magnetic fields,
– presence of Industrial, Scientific and Medical (ISM) equipment (for example, welding
machines)
3.1.14
laboratory
test and measurement area that is specifically used for analysis, testing and servicing and
where equipment is operated by trained personnel
3.1.15
loss of function
operation of equipment with one (or more) of the equipment’s functions unusable
3.1.16
performance level
specified operation of equipment under conditions of intended use
3.1.17
long-distance line
line within a building which are longer than 30 m, or which leave the building (including lines of
outdoor installations)
3.1.18
loss of performance
operation of equipment outside a specified PERFORMANCE LEVEL
3.1.19
PHY
physical layer circuitry required to implement physical layer functions
3.1.20
power switch
switch including at least one port feeding power into a TRUNK
3.1.21
specified electromagnetic process control environment
environments encompassed both indoor and outdoor, that are based on the requirements of the
process industry, specifically chemical/petrochemical/pharmaceutical manufacturing plants
EXAMPLE The difference between this electromagnetic environment compared to the general industrial
environment (see 3.1.13) is due to the mitigation measures employed against electromagnetic phenomena leading
to a specified electromagnetic environment with test values that have been proven in practice to gain high availability.
IEC 61326-2-7:2025 © IEC 2025
The environment of industrial application with a specified electromagnetic environment typically includes the
following characteristics:
– industrial area with limited access,
– limited use of mobile transmitters,
– dedicated cables for power supply and control, signal or communication lines,
– separation between power supply and control, signal or communication cables,
– factory building mostly consisting of metal construction,
– overvoltage/lightning protection by appropriate measures (for example, metal construction of the building or use
of protection devices),
– pipe heating systems driven by AC main power,
– no high-voltage substation close to sensitive areas,
– presence of CISPR 11 Group 2 ISM equipment using ISM frequencies only with low power,
– competent staff,
– periodical maintenance of equipment and systems,
– mounting and installation guidelines for equipment and systems.
3.1.22
spur
APL SEGMENT which connects a field device to a FIELD SWITCH
Note 1 to entry: An APL SPUR segment can have a maximum cable length of 200 m.
Note 2 to entry: An APL SPUR segment can optionally be equipped with a maximum of two AUXILIARY DEVICES and
up to four inline terminal CONNECTIONS.
3.1.23
trunk
APL SEGMENT which connects a POWER SWITCH to a FIELD SWITCH or a FIELD SWITCH to a FIELD
SWITCH
Note 1 to entry: An APL TRUNK segment can have a maximum cable length of 1 000 m.
Note 2 to entry: An APL TRUNK segment can optionally be equipped with a maximum of two AUXILIARY DEVICES and
up to 10 inline terminal CONNECTIONS.
3.1.24
uplink port
ethernet port of an APL INFRASTRUCTURE DEVICE used for CONNECTION to the Ethernet network
3.2 Abbreviated terms
AE auxiliary equipment
APL advanced physical layer
CCC capacitive coupling clamp
CDN coupling/decoupling network
CN coupling network
EMC electromagnetic compatibility
ESD electrostatic discharge
EUT equipment under test
FIELD DEVICE
FD
HCP horizontal coupling plate
GRP ground reference plate
ICMP internet control message protocol
IP internet protocol
RF radio frequency
IEC 61326-2-7:2025 © IEC 2025
4 General
4.1 General
This document specifies the requirements and test setups for testing APL infrastructure and
FIELD DEVICES.
4.2 General considerations on EMC testing of devices with APL interface
The following general rules apply when testing APL devices:
– EMC testing of INFRASTRUCTURE DEVICES and field devices with APL interface is based on the
IEC 61326 series.
– Test levels and test requirements for industrial environments are provided in Table 3 of this
document. These levels are the minimum requirements for EMC testing for an APL device.
– For processing industry environments, such as chemical/petrochemical/pharmaceutical
manufacturing plants, additional tests can be required. The higher test levels required for
these environments are provided in Table 4 of this document.
All tests may either be performed on a single EUT or the tests may be split between several
EUTs. In the latter case, each test result shall be traceable to the tested EUT. The testing
sequence with multiple EUTs is optional.
4.3 Structure of an APL system
APL allows different system configurations, using 10/100/1 000 Mbit/s Ethernet network
CONNECTIONS with powered APL TRUNKS.
Figure 1 illustrates an example of an APL network connected to a control network using an
Ethernet network. In such a case, the 10/100/1 000 MBit/s Ethernet backbone is directly
connected to the APL FIELD SWITCHES. For an Ethernet network, an APL system also supports
redundant ring topologies.
Key
FD APL FIELD DEVICE
a
In case of a ring topology
Figure 1 – APL system structure for APL FIELD SWITCHES with Ethernet UPLINK PORT(S)
Figure 2 illustrates an example of an APL network connected to a control network using a
powered APL TRUNK. The communication link between the control network and the APL SEGMENT
is performed through an APL POWER SWITCH, which additionally powers the APL TRUNK. For a
powered APL TRUNK, an APL system currently does not support redundant ring topologies.
IEC 61326-2-7:2025 © IEC 2025
Key
FD APL FIELD DEVICE
Figure 2 – APL system structure for APL FIELD SWITCHES with APL TRUNK powered port(s)
Each APL SPUR finally terminates at a FIELD DEVICE, which can also be powered in accordance
with the applicable hazardous area classification, so that FIELD DEVICES, which will typically be
intrinsically safe certified, can be located in an appropriately assessed hazardous area.
Each TRUNK cable length can be up to 1 000 m long, depending on the type of the cable used,
the power loss through the cable and the power consumption of the components connected to
the TRUNK. The SPUR cable length can be up to 200 m, depending on the type of the cable used.
4.4 Structure of the shield connection of an APL system
The Ethernet- APL PORT profile specification specifies required shielding options depending on
the type of port (see Table 1). While it is recommended to make a low impedance connection
to the equipotential bonding system at both ends of a cable shield to guarantee the highest
rejection of electromagnetic disturbances, in some installations this can not be practical or could
lead to current loops. For this kind of installations, one end of the cable shall be capacitively
grounded and the other end shall be directly grounded.
Table 1 – Minimum required shielding options a port shall provide
Port class Segment class
TRUNK SPUR
P Power source Direct Capacitive
L Power load Capacitive and direct Direct
C CASCADE PORT Capacitive and direct Not applicable

IEC 61326-2-7:2025 © IEC 2025
Key
P power source
L  power load
C CASCADE PORT power source
P
C CASCADE PORT power load
L
NOTE 1 If the equipotential bonding system is controlled and equalized, direct shield grounding on both sides can
be used.
NOTE 2 A C port is a CASCADE PORT operating as a source port, a C port is a CASCADE PORT operating as a power
p L
load port.
Figure 3 – APL infrastructure overview
5 EMC test plan
5.1 General
EMC tests of EUTs (APL INFRASTRUCTURE DEVICES and FIELD DEVICES) shall be applied using an
APL EMC TEST MASTER in combination with an APL FIELD SWITCH or APL POWER SWITCH, depending
on which EUT type is tested. Specific test setups for the different EUT types are provided in
6.3.2.
The APL EMC TEST MASTER shall provide an Ethernet port, which can be directly connected to the
EUT or connected to the EUT using an APL FIELD SWITCH or APL POWER SWITCH. Additionally, the
APL EMC TEST MASTER shall provide at least one failure output to indicate a disturbed
communication. Failure criteria for activating the failure output are provided in 6.5.
The APL EMC TEST MASTER may be used for testing the communication as well as for testing the
process data integrity of a FIELD DEVICE. Alternatively, two APL EMC TEST MASTERS may be used:
one for testing the communication and the second for testing the process data integrity.
IEC 61326-2-7:2025 © IEC 2025
To test communication, the APL EMC TEST MASTER shall continuously send ICMP ping request
packets to an IP-capable EUT and AUXILIARY EQUIPMENT devices (e.g. FIELD DEVICES or FIELD
SWITCHES) connected to the EUT to verify whether communication to these devices is valid or
disturbed. All connected APL communication ports of the EUT shall carry ICMP packets during
testing.
Figure 4 shows an example how the APL EMC TEST MASTER communicates with the EUT and the
AUXILIARY DEVICES sending ICMP ping request packets and receiving ICMP ping response
packets to check whether the communication links are active and continue to provide valid
communication during the EMC tests.

Key
Dashed lines:
ICMP ping request packets sent from APL test master to EUT and AUXILIARY DEVICES
ICMP ping response packets returned from EUT and AUXILIARY DEVICES to APL test master
Figure 4 – APL EMC TEST MASTER communication
The IPv4 ICMP ping request packets issued by the APL EMC TEST MASTER shall have a payload
data length of 1 472 bytes communicating with the EUT and each AUXILIARY DEVICE with a cycle
time of 16 ms (± 2 ms). The EUT and each AUXILIARY DEVICE shall respond with an IPv4 ICMP
response packet with a payload length of 1 472 bytes. This causes a link utilisation of minimum
7,6 %. If an alternative protocol is used, the same minimum link utilisation shall be reached.
The data packets should be equally distributed over time. If the minimum link utilisation cannot
be achieved, the test time or number of test events should be extended for all transient tests to
have the same statistical possibility to disturb the communication signal.
An IPv4 ICMP packet with a payload data length of 1 472 bytes results in the maximum allowed
Ethernet packet size of 1 518 bytes including Ethernet header and frame check sequence. For
IPv6 packets, the ICMP packet payload data length shall be reduced to 1 452 bytes, as the IPv6
IP header is 20 bytes longer than the IPv4 IP header.
In case a high number of AUXILIARY DEVICES (typically more than 10 to 12 devices) is used within
the EMC test setup, it can be necessary to reduce the ICMP packet length to get a link utilization
of less than 100 % for the APL EMC TEST MASTER. In such a case, reducing the ICMP packet
length complies with this specification.
For APL FIELD DEVICES, in addition to the ICMP ping packets, it is necessary to exchange
measurement or control data in a cyclic manner during the EMC tests. For this data exchange,
standard communication protocols may be used and shall be specified in the test plan.
IEC 61326-2-7:2025 © IEC 2025
An EMC test plan shall be established prior to testing. At a minimum, it shall contain the
elements specified in 5.2 to 5.5.
5.2 Configuration of EUT during testing
APL devices often are used in systems with no fixed configuration. Thus, it is reasonable to test
only a
...