ISO 22238
(Main)Design, construction and testing of high-pressure natural gas marine transfer arms
- Status
- Not Published
- Current Stage
- 6000 - International Standard under publication - 60 Publication
- Start Date
- 27-Oct-2026
Buy Documents
ISO/FDIS 22238 - Design, construction and testing of high-pressure natural gas marine transfer arms
REDLINE ISO/FDIS 22238 - Design, construction and testing of high-pressure natural gas marine transfer arms
ISO/FDIS 22238 - Conception, construction et essais de bras de transfert marins de gaz naturel à haute pression
ISO 22238 is an ISO standard for the design, construction and testing of high-pressure natural gas marine transfer arms. It covers ship-to-shore transfer arms for floating storage and regasification unit (FSRU), floating regasification unit (FRU) and floating storage unit (FSU) applications, and it is intended for owners, designers, manufacturers and test teams working on safe high-pressure gas transfer systems.
What does ISO 22238 specify?
ISO 22238 specifies the design, minimum safety requirements, inspection and testing procedures for high-pressure natural gas (HPNG) marine transfer arms. It also supplements ISO 28460 and can be applied to existing facilities, which matters when a terminal is being upgraded rather than built from new.
Clause 1 sets the scope around ship-to-shore systems that transfer pressurized gas from floating units to a gas grid. It says the document covers power and control systems, but not every detail for the design and fabrication of standard parts and fittings associated with transfer arms.
The document is organized into these main clauses and annexes:
| Part | What it covers |
|---|---|
| Clause 1 | Scope |
| Clause 2 | Normative references |
| Clause 3 | Terms and definitions |
| Clause 4 | Abbreviated terms |
| Clause 5 | Design of transfer arms |
| Clause 6 | Safety systems |
| Clause 7 | Connection with the ship |
| Clause 8 | Hydraulic and electric control systems for loading arms |
| Clause 9 | Inspection and tests |
| Clause 10 | Quality assurance and control |
| Clause 11 | Required documentation |
| Annex A | Design data sheets |
| Annex B | Reference table and figures |
| Annex C | Typical documentation requirements |
Annex A is normative, so it forms part of the technical requirements. Annexes B and C are informative and support design checking and documentation planning.
What are the key requirements of ISO 22238?
ISO 22238 requires the transfer arm to be designed as a complete system, not just as piping and joints. The main design, safety and test requirements are spread across Clauses 5 to 10, and they are tied to the project data recorded in Annex A.
Design basis, loads and configuration
Clause 5 requires the arm length, configuration, balancing, clearances and design basis to be defined. The design basis includes product line diameter, materials and grades, and a stress analysis that considers combinations of dead load, pressure load, fluid load, ice build-up, thermal load, wind load and earthquake load. In practice, this means the manufacturer must prove the arm is acceptable in stowed, manoeuvring, connected, emergency release, maintenance and hydrostatic test conditions, using the load cases in Table A.15.
Swivels, bearings and maintainability
Clause 5 also covers swivel joints, structural bearings, accessories, pipework, fittings, welding, corrosion protection and maintenance. The document requires sealing arrangements for product and external sealing, protection of structural bearings, and accessories such as a jack, nitrogen injection, stowing locking device, access arrangements and a blowdown line. Clause 5.9 adds a maintenance expectation that major components should be replaceable with minimum downtime and that critical parts should be reachable for inspection and replacement without dismantling major sections or using mobile cranes.
Safety systems and emergency release
Clause 6 covers the safety systems, including emergency shutdown (ESD), arm position monitoring, alarm stages and the emergency release system (ERS). The document distinguishes ESD I and ESD II and requires an ERS when the vessel cannot remain safely moored under expected operating conditions. The ERS may use an emergency disconnection coupler (EDC) or a powered emergency release coupling (PERC), depending on the project. In practice, the owner must decide whether disconnection capability is needed, and the control philosophy must keep the arm in a safe state if an emergency occurs.
Ship interface and connection details
Clause 7 says the connection to the vessel can be by bolted flange or by an EDC with a manifold connection unit (MCU), according to the owner’s standard. Seals, flange surface finish and gaskets must be compatible with the vessel manifold. This matters because the ship interface is one of the main sources of leakage, mismatch and mechanical incompatibility.
Hydraulic, electrical and control systems
Clause 8 requires an electro-hydraulic operating and control system for normal motion, emergency release and retraction after release. It specifies a dedicated main hydraulic unit, suitable manoeuvring modes, and control positions on the jetty side and near the vessel manifold. The arm control panel and remote control shall not be used at the same time, and simultaneous movement of more than one arm is not allowed during normal operation.
Clause 8.2 and 8.3 add practical hydraulic requirements such as flow regulation, pressure relief, filtration, dual hydraulic power sources, dedicated accumulators for emergency disconnection, and a design that allows all connected arms to disconnect and then raise clear. Clause 8.4 adds electrical protection, including intrinsic safety for cables on the arm, suitable IP degrees of protection, and flexible cables that resist hydrocarbons, salt water and UV light.
Inspection, tests and quality control
Clause 9 requires an inspection and test plan (ITP) and acceptance criteria to be approved before testing starts. It separates prototype tests, manufacturing inspection and tests, factory acceptance tests (FAT) and site acceptance tests (SAT). Clause 10 then requires a quality system and a project quality assurance plan that covers design, manufacturing, testing and records. In practice, this means the owner should expect traceable evidence for materials, welding, non-destructive testing, pressure testing, release performance and electrical resistance checks.
What terms does ISO 22238 define?
ISO 22238 defines the terms that are central to the arm geometry, motion and safety functions.
- High-pressure natural gas (HPNG) - gas in the transfer system at a working pressure exceeding 10 barg, which is important because this level can require controlled blowdown before emergency release.
- Emergency shutdown (ESD) - the method used to safely stop transfer between vessel and shore, so operators can stop product flow in a controlled way.
- Emergency release system (ERS) - the system that provides quick release and safe isolation between vessel and shore after a defined emergency procedure.
- Emergency disconnection coupler (EDC) - a hydraulic or mechanical device used to release the transfer arm from the vessel, typically as part of the ERS.
- Powered emergency release coupling (PERC) - a powered quick-release device used when emergency release is needed.
- Transfer arm - the articulated mechanical system used to transfer product from a vessel while accommodating tide, freeboard and vessel motion.
- Triple swivel assembly (TSA) - the group of three swivels and elbows at the outboard end of the arm, which helps the arm follow ship motion.
- Working pressure - the maximum internal pressure for normal steady-state service, excluding short transients.
Who uses ISO 22238?
ISO 22238 is used by owners, transfer arm manufacturers, marine terminal engineers, project contractors, and inspection and test teams working on LNG-related ship-to-shore transfer systems. It is especially relevant in the oil and gas industries including lower carbon energy, where floating LNG units, regasification units and related marine transfer systems need consistent design, safety and acceptance criteria.
It is also used when preparing project data sheets, interface drawings, operating envelopes, FAT and SAT procedures, and quality plans. For buyers and quality managers, it gives a common basis for comparing vendor offers and checking whether the delivered arm matches the terminal and vessel interface.
Which standards are used with ISO 22238?
ISO 22238 relies on several normative references for testing, safety and interface requirements.
| Reference | What it contributes |
|---|---|
| ISO 3452-1 | Penetrant testing principles for weld inspection |
| ISO 4406 | Coding of hydraulic fluid contamination levels |
| ISO 9934-1 | Magnetic particle testing principles |
| ISO 10474 | Inspection documents for steel and steel products |
| ISO 10497 | Fire type-testing requirements for valves |
| ISO 17636-1 | Film radiographic testing of welds |
| ISO 17636-2 | Digital radiographic testing of welds |
| ISO 28460:2010 | LNG ship-to-shore interface and port operations requirements that this document supplements |
| IEC 60034-5 | IP protection classification for rotating electrical machines |
| IEC 60079 series | Explosive atmospheres, area classification and explosion-protected equipment |
| IEC 60529 | IP code for enclosures and components |
| IEC 61508 (all parts) | Functional safety for safety-related electrical/electronic/programmable electronic systems |
| IEC 61511 | Functional safety for process industry safety instrumented systems |
| IEC 62305-3 | Lightning protection against physical damage and life hazard |
| ASME B16.5 | Pipe flanges and flanged fittings |
| ASME Boiler and Pressure Vessel Code Section IX | Welding and brazing qualification requirements |
What does the ISO 22238 document contain?
ISO 22238 contains design data sheets in Annex A, including vessel, berth, environmental and load-case tables, plus figures that show vessel details, motions, berth layout and transfer arm alarm zones. Those sheets are meant for project-specific completion by the owner and manufacturer.
Annex B gives reference tables and figures for clearance checkpoints, angle-detecting proximity switches and typical transfer arm arrangements with ERS. This supports movement checks, alarm logic and the physical layout of the arm.
Annex C lists typical documentation requirements for tender and contract stages, including design documents, control system documents, test procedures, test reports and quality documents. Clause 9 then uses those project records in prototype, manufacturing, FAT and SAT activities, including hydrostatic, pneumatic, leakage, release performance and electrical resistance tests.
Buy Documents
ISO/FDIS 22238 - Design, construction and testing of high-pressure natural gas marine transfer arms
REDLINE ISO/FDIS 22238 - Design, construction and testing of high-pressure natural gas marine transfer arms
ISO/FDIS 22238 - Conception, construction et essais de bras de transfert marins de gaz naturel à haute pression
Get Certified
Connect with accredited certification bodies for this standard

Element Materials Technology
Materials testing and product certification.
ABS Group Brazil
ABS Group certification services in Brazil.

ABS Quality Evaluations Inc.
American Bureau of Shipping quality certification.
Sponsored listings
Frequently Asked Questions
ISO 22238 is a draft published by the International Organization for Standardization (ISO). Its full title is "Design, construction and testing of high-pressure natural gas marine transfer arms". This standard covers: Design, construction and testing of high-pressure natural gas marine transfer arms
Design, construction and testing of high-pressure natural gas marine transfer arms
ISO 22238 is classified under the following ICS (International Classification for Standards) categories: 75.200 - Petroleum products and natural gas handling equipment. The ICS classification helps identify the subject area and facilitates finding related standards.
ISO 22238 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.
Standards Content (Sample)
Contents
- 1 Scope
- 2 Normative references
- 3 Terms and definitions
- 3.1 apex swivel
- 3.2 attitude
- 3.3 base riser
- 3.4 bottom swivel
- 3.5 brinelling
- 3.6 clash
- 3.7 contact angle
- 3.8 counterweight
- 3.9 design pressure
- 3.10 design temperature
- 3.11 drift
- 3.12 emergency disconnection coupler
- 3.13 emergency release system
- 3.14 emergency shutdown
- 3.15 freeboard
- 3.16 free wheel
- 3.17 heave
- 3.18 high-pressure natural gas
- 3.19 hydraulic power unit
- 3.20 inboard arm
- 3.21 included angle
- 3.22 insulating flange
- 3.23 jack
- 3.24 lowest anticipated service temperature
- 3.25 luffing
- 3.26 manifold connection unit
- 3.27 manifold setback
- 3.28 manifold spacing
- 3.29 middle swivel
- 3.30 operating envelope
- 3.31 outboard arm
- 3.32 owner
- 3.33 pantograph system
- 3.34 pitch
- 3.35 powered emergency release coupling
- 3.36 presentation flange
- 3.37 product
- 3.38 remote control
- 3.39 riser and trunnion swivel assembly
- 3.40 riser flange
- 3.41 riser swivel
- 3.42 roll
- 3.43 safety integrity level
- 3.44 slew
- 3.45 spool piece
- 3.46 spotting line
- 3.47 stress analysis
- 3.48 structural bearing
- 3.49 surge aft
- 3.50 surge fore
- 3.51 pressure surge
- 3.52 sway
- 3.53 swivel
- 3.54 top swivel
- 3.55 transfer
- 3.56 transfer arm
- 3.57 triple swivel assembly
- 3.58 trunnion swivel
- 3.59 UPS
- 3.60 vessel
- 3.61 vessel manifold
- 3.62 working pressure
- 3.63 yaw
- 4 Abbreviated terms
- 5 Design of transfer arms
- 5.1 Definition of the length and the configuration of the transfer arms
- 5.2 Design basis
- 5.3 Swivel joints
- 5.4 Structural bearings
- 5.5 Accessories
- 5.6 Pipework and fitting
- 5.7 Welding
- 5.8 Corrosion protection
- 5.9 Maintenance
- 6 Safety systems
- 6.1 General
- 6.2 Emergency shutdown (ESD) system
1 Scope
This document specifies the design, minimum safety requirements and inspection and testing procedures for high-pressure natural gas (HPNG) marine transfer arms intended for floating storage and regasification unit (FSRU), floating regasification unit (FRU) and floating storage unit (FSU) applications. High-pressure transfer arms are considered to be ship-to-shore systems transferring pressurized gas from floating units to any part of a gas grid.
This document provides the requirements for power or control systems, but it does not include all the details for the design and fabrication of standard parts and fittings associated with transfer arms. This document supplements the requirements of ISO 28460.
This document is applicable to general electrical-hydraulic systems. It can be applied to other control systems, for example, using only electrical or other power supplies, if they meet the functional safety and performance requirements of Clause 8 for the hydraulic and electrical control systems. This document can also be applied to existing facilities.
2 Normative references
The following referenced documents, in whole or in part, are normatively referenced in this document and are indispensable for its application. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies. ISO 3452-1, Non-destructive testing — Penetrant testing — Part 1: General principles ISO 4406, Hydraulic fluid power — Fluids — Method for coding the level of contamination by solid particles ISO 9934-1, Non-destructive testing — Magnetic particle testing — Part 1: General principles ISO 10474, Steel and steel products — Inspection documents ISO 10497, Testing of valves — Fire type-testing requirements ISO 17636-1, Non-destructive testing of welds — Radiographic testing — Part 1: X- and gamma-ray techniques with film ISO 17636-2, Non-destructive testing of welds — Radiographic testing — Part 2: X- and gamma-ray techniques with digital detectors ISO 28460:2010, Petroleum and natural gas industries — Installation and equipment for liquefied natural gas - Ship-to-shore interface and port operations IEC 60034-5, Rotating electrical machines — Part 5: Degrees of protection provided by the integral design of rotating electrical machines (IP code) — Classification IEC 60079-0, Explosive atmospheres — Part 0: Equipment — General requirements IEC 60079-1, Explosive atmospheres — Part 1: Equipment protection by flameproof enclosures “d” IEC 60079-2, Explosive atmospheres — Part 2: Equipment protection by pressurized enclosures “p”
ISO/FDIS 22238:2026(en) IEC 60079-5, Explosive atmospheres — Part 5: Equipment protection by powder filling “q” IEC 60079-6, Explosive atmospheres — Part 6: Equipment protection by oil immersion “o” IEC 60079-7, Explosive atmospheres — Part 7: Equipment protection by increased safety “e” IEC 60079-10-1, Explosive atmospheres — Part 10-1: Classification of areas — Explosive gas atmospheres IEC 60079-11, Explosive atmospheres — Part 11: Equipment protection by intrinsic safety “i” IEC 60079-14, Explosive atmospheres — Part 14: Electrical installations design, selection and erection IEC 60079-18, Explosive atmospheres — Part 18: Equipment protection by encapsulation “m” IEC 60079-25, Explosive atmospheres — Part 25: Intrinsically safe electrical systems IEC 60529, Degrees of protection provided by enclosures (IP Code) and IEC 60529/A1&A2, Amendment 1&2 IEC 61508 (all parts), Functional safety of electrical/electronic/programmable electronic safety-related systems IEC 61511, Functional Safety — Safety Instrumented Systems for the Process Industry Sector IEC 62305-3, Protection against lightning — Part 3: Physical damage to structures and life hazard ASME B16.5, Pipe Flanges and Flanged Fittings ASME Boiler and Pressure Vessel Code Section IX, Welding and Brazing Qualifications
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply. ISO and IEC maintain terminology databases for use in standardization at the following addresses:
- ISO Online browsing platform: available at https:// www .iso .org/ obp
- IEC Electropedia: available at https:// www .electropedia .org/
3.1 apex swivel
articulated, fluid-carrying joint located between the inboard arm (3.20) and outboard arm (3.31) Note 1 to entry: See Figures B.2 and B.3.
Note 2 to entry: It provides luffing (3.25) of the outboard arm relative to the inboard arm.
3.2 attitude
mode of use or location of the transfer arms (3.56) (i.e. manoeuvring, stowed, connected, hydrostatic test, and maintenance) Note 1 to entry: The transfer arm can take several positions for each attitude.
3.3 base riser
standpost vertical assembly which bolts to the loading platform and supports the articulated assembly of the transfer arm (3.56) Note 1 to entry: See Figures B.2 and B.3.
ISO/FDIS 22238:2026(en)
3.4 bottom swivel
swivel that accommodates the pitch (3.34) of a vessel (3.60) and is located adjacent to the presentation flange (3.36) in the horizontal part of a TSA (3.57) Note 1 to entry: See Figures B.2 and B.3.
3.5 brinelling
permanent indentation in swivel or structural bearing (3.48) raceways caused by excessive loading of balls or rollers Note 1 to entry: See Figures B.2 and B.3.
3.6 clash
contact during operational conditions, or as a result of an emergency separation, between any part of a transfer arm (3.56) and:
- adjacent transfer arm while both arms are operating or one arm is operating and the other arm is stowed [e.g. the counterweights (3.8)];
- adjacent section of the same transfer arms [e.g. triple swivel assembly (3.57) and outboard arm (3.31)];
- loading platform equipment [e.g. counterweight and piping or valves]
3.7 contact angle
α angle between the plane of the swivel joint (3.53) or structural bearing (3.48) balls or rollers and the centre of contact at the ball or roller raceway interface
3.8 counterweight
system of weights used to balance the inboard arm (3.20) and outboard arm (3.31) assemblies
3.9 design pressure
pressure for which the transfer arm (3.56) is designed Note 1 to entry: See Table A.1.
3.10 design temperature
range of temperatures for which the transfer arm (3.56) is designed Note 1 to entry: See Table A.1.
3.11 drift
longitudinal and/or lateral displacement of the vessel (3.60) under the influence of environmental forces Note 1 to entry: See also surge fore (3.50) or surge aft (3.49) and sway (3.52).
3.12 emergency disconnection coupler
EDC hydraulic, mechanical device used to release the transfer arm (3.56) from the vessel (3.60) Note 1 to entry: The EDC is a part of the emergency release system (3.13). Note 2 to entry: See Figure B.3.
ISO/FDIS 22238:2026(en)
3.13 emergency release system
ERS system that provides a positive means of quick release of transfer arm (3.56) and safe isolation between the vessel (3.60) and shore, following a predefined procedure including an emergency shutdown (ESD) (3.14) Note 1 to entry: See Figure B.2.
3.14 emergency shutdown
ESD method that safely and effectively stops the transfer (3.55) of high-pressure natural gas (3.18) between the vessel (3.60) and shore
3.15 freeboard
vertical distance between the ship's deck and the water level at the manifold location Note 1 to entry: See Table A.3 and Figure A.1.
3.16 free wheel
ability of a transfer arm (3.56) when connected to a vessel (3.60) to follow the vertical and horizontal motions of the vessel manifold (3.61) freely without restraint (draft changes and sway (3.52) and surge motions)
3.17 heave
vertical motion of the vessel (3.60) due to wave action Note 1 to entry: See Table A.4 and Figure A.2.
3.18 high-pressure natural gas
HPNG gas contained within the transfer system at a working pressure (3.62) exceeding 10 barg Note 1 to entry: Gas above this pressure threshold can contain sufficient stored compressible energy to require controlled depressurization (blowdown) prior to emergency release system (3.13) disconnection. Pressures below this threshold, such as typical low-pressure vapor return service, are not considered high-pressure for the purpose of ERS and blowdown requirements
3.19 hydraulic power unit
HPU unit that generates hydraulic power to ensure the normal operation and emergency release sequence of the systems
3.20 inboard arm
product-carrying pipe and any structural members contained between the apex swivel (3.1) and the trunnion swivel (3.58) Note 1 to entry: See Figures B.2 and B.3.
3.21 included angle
angle formed between inboard arm (3.20) and outboard arm (3.31) Note 1 to entry: See Figures B.2 and B.3.
Note 2 to entry: The maximum and minimum included angles are left to the transfer arm (3.56) manufacturer.
ISO/FDIS 22238:2026(en) Note 3 to entry: The included angle in the stowed position of the transfer arms is such, that the arms are parked with the triple swivel assembly (3.57) behind the berthing line.
3.22 insulating flange
electrical insulating system, usually dedicated, which is installed in the lower end of the outboard arm (3.31) or in the vertical part of the triple swivel assembly (3.57) Note 1 to entry: Its purpose is to prevent stray currents from causing an arc at the vessel’s (3.60) flange as the transfer arm (3.56) is connected or disconnected.
3.23 jack
permanent, adjustable load-carrying mechanism potentially installed in the triple swivel assembly (3.57) to transfer loads or momentum to the deck instead of the vessel manifold (3.61) Note 1 to entry: See Figures B.2 and B.3.
3.24 lowest anticipated service temperature
LAST reference temperature based on ambient and process conditions
3.25 luffing
rotary motion of the inboard arm (3.20) and outboard arm (3.31) in the vertical plane Note 1 to entry: See Figures B.2 and B.3.
3.26 manifold connection unit
MCU special spool piece (3.45) with ship-side ERS (3.13) valve for horizontal orientation or special connection frame with elbow, swivel joint and ERS valve for vertical orientation
3.27 manifold setback
horizontal distance between the vessel’s (3.60) side and the face of vessel manifold (3.61) Note 1 to entry: See Table A.3 and Figure A.1.
3.28 manifold spacing
horizontal distance between two adjacent vessel manifold (3.61) flange axes Note 1 to entry: See Table A.3 and Figure A.1.
3.29 middle swivel
swivel that accommodates the yaw (3.63) and surge of a vessel (3.60) and is located between the top swivel (3.54) and the bottom swivel (3.4) in the vertical part of a TSA (3.57) Note 1 to entry: See Figures B.2 and B.3.
3.30 operating envelope
space in which presentation flange(s) (3.36) of a (group of) transfer arms (3.56) is (are) required to operate in all directions
ISO/FDIS 22238:2026(en)
3.31 outboard arm
product-carrying pipe and any structural members contained between the apex swivel (3.1) and the triple swivel assembly (3.57) Note 1 to entry: See Figures B.2 and B.3.
3.32 owner
company or group of companies for whose use the transfer arms (3.56) are installed, responsible for the safe design and construction of the installation
3.33 pantograph system
system for transmitting balancing loads from the outboard arm (3.31) to the counterweight(s) (3.8) Note 1 to entry: The system comprises an assembly of linkages and pinned connections, or a cable and sheaves system (respectively, “rigid link pantograph” and “cables and sheaves pantograph”).
3.34 pitch
rotation of the vessel (3.60) around the transversal horizontal axis Note 1 to entry: See Table A.4 and Figure A.2.
3.35 powered emergency release coupling
PERC powered device to provide a means of quick release of the transfer arm (3.56) when such action is required only as an emergency measure
3.36 presentation flange
transfer arm (3.56) flange for connection to either the vessel manifold (3.61) or spool piece (3.45) Note 1 to entry: See Figures B.2 and B.3.
3.37 product
high-pressure natural gas (3.18) transferred using transfer arm (3.56)
3.38 remote control
device to facilitate the fine manoeuvring operation of the transfer arms (3.56) from a remote location, e.g. vessel manifold (3.61) area Note 1 to entry: The system can use a trailing wire (pendant) and/or radio-controlled system.
3.39 riser and trunnion swivel assembly
gas-carrying system consisting of a riser swivel (3.41), a trunnion swivel (3.58) and elbows mounted on top of the base riser (3.3) Note 1 to entry: See Figures B.2 and B.3.
3.40 riser flange
transfer arm (3.56) flange for connection to shore-side piping Note 1 to entry: See Figures B.2 and B.3.
ISO/FDIS 22238:2026(en)
3.41 riser swivel
swivel joint in the riser and trunnion swivel assembly (3.39) which permits slew (3.44) of the transfer arms (3.56) Note 1 to entry: See Figures B.2 and B.3.
3.42 roll
rotation of vessel (3.60) around the longitudinal horizontal axis Note 1 to entry: See Table A.4 and Figure A.2.
3.43 safety integrity level
SIL level of integrity required of a safety-related system Note 1 to entry: Safety-related systems shall be in accordance with the IEC 61508 series. Note 2 to entry: See Clause 6.
3.44 slew
horizontal, rotary motion of the transfer arm (3.56) around the base riser (3.3) Note 1 to entry: See Figures B.2 and B.3.
3.45 spool piece
adaptor short distance piece short length of pipe for the purpose of matching the vessel manifold (3.61) to the presentation flange (3.36)
3.46 spotting line
pre-determined location on the jetty used by the vessel (3.60) when berthing to align the vessel manifold(s) (3.61) Note 1 to entry: See Figure A.4.
3.47 stress analysis
detailed calculation of the structural loading in the transfer arm (3.56) and vessel manifold (3.61) for various positions and attitudes (3.2) to check the integrity of the transfer arm for the service intended
3.48 structural bearing
bearing in the load carrying components supporting the product (3.37) line that, in combination, allow the transfer arm (3.56) to follow freely the motion of the vessel (3.60)
3.49 surge aft
longitudinal vessel (3.60) afterward motion Note 1 to entry: See Table A.4 and Figure A.2.
3.50 surge fore
longitudinal vessel (3.60) forward motion Note 1 to entry: See Table A.4 and Figure A.2.
ISO/FDIS 22238:2026(en)
3.51 pressure surge
rapid change in pressure as a consequence of a change in flow rate in a pipeline and/or piping systems, including transfer arm (3.56)
3.52 sway
transverse vessel (3.60) motion Note 1 to entry: See Table A.4 and Figure A.2.
3.53 swivel
swivel joint rotating connection contained in the transfer arm (3.56) to permit the arm/system to follow freely the motion of the vessel (3.60)
3.54 top swivel
swivel that accommodates the roll (3.42), heave (3.17) and sway (3.52) of a vessel (3.60) and is located between the outboard arm (3.31) and the middle swivel (3.29) in the horizontal part of a TSA (3.57) Note 1 to entry: See Figures B.2 and B.3.
3.55 transfer
transmission of high-pressure natural gas (3.18) from the vessel (3.60) to any fixed part of a harbour or coastal locations
3.56 transfer arm
articulated mechanical system used for transmission of a product (3.37) from vessel (3.60) with the capability of accommodating differences in tides, freeboard (3.15) and vessel’s motions Note 1 to entry: See Figures B.2 and B.3.
3.57 triple swivel assembly
TSA group of three swivels (3.53) and elbows located at the end of the outboard arm (3.31) Note 1 to entry: See Figures B.2 and B.3.
3.58 trunnion swivel
swivel joint in the riser and trunnion swivel assembly (3.39) which permits the inboard arm (3.20) to rotate around the horizontal or vertical axis Note 1 to entry: See Figures B.2 and B.3.
3.59 UPS
uninterrupted power supply back-up of the electrical supply system providing power to critical control and safety systems so that the plant can be kept in safe conditions
3.60 vessel
floating unit for the storage and/ or regasification of LNG and for sending out high-pressure natural gas (3.18) (also known as FSRU/FSU/FRU)
ISO/FDIS 22238:2026(en)
3.61 vessel manifold
pipe assembly mounted onboard vessel (3.60) to which the presentation flange (3.36) or spool piece (3.45) of the transfer arm (3.56) is connected
3.62 working pressure
maximum internal pressure that a transfer system is designed to operate under during normal, steady-state service, including all expected process variations but excluding short-duration pressure transients associated with start-up, shutdown, or abnormal conditions
3.63 yaw
rotation of the vessel (3.60) around the vertical axis Note 1 to entry: See Table A.4 and Figure A.2.
4 Abbreviated terms
CPMS constant position monitoring system EMC electro-magnetic compatibility FL fluid load FMEDA failure mode and effects analysis HP high pressure LNG liquefied natural gas N nitrogen gas
OBE operating basis earthquake OEM original equipment manufacturer PL pressure load PQR performance quality records SSE safe shutdown earthquake TL thermal load WL wind load WPS welding procedure specifications ρ density v velocity
5 Design of transfer arms
5.1 Definition of the length and the configuration of the transfer arms
5.1.1 General
The general arrangement of the transfer arm is shown in Annex B (see Figures B.2 and B.3).
ISO/FDIS 22238:2026(en) The length and the configuration of the transfer arms shall allow for the connection of the on-shore piping to the vessel manifold. The connection shall allow for free movement within the operating envelope. The transfer arms are normally composed of the following:
- TSA;
- ERS including PERC or EDC;
- manifold connection unit mounted on-board the vessel, if required;
- outboard arm;
- apex swivel assembly between the outboard and inboard arm;
- pantograph system;
- inboard arm;
- riser and trunnion swivel assembly between the inboard arm and the base riser;
- base riser.
All piping supports shall be designed so that stresses in the piping and the structure are within allowable limits for all positions.
Any parts of a transfer arm, for example, seals, bolts and nuts, shall not come off or unfasten and drop into product piping under any circumstances.
5.1.2 Balancing
The complete TSA and outboard arm shall be balanced in the empty condition. It shall be balanced with the pantograph system around the apex swivel.
The complete, articulated assembly shall be balanced in the empty condition. It shall be balanced around the trunnion swivel.
In addition to normal operations, the transfer arms shall be designed to allow for the emergency release of the arms in the both the empty and full condition. There should be no clash between the arms and any other parts of the system, vessel or jetty.
5.1.3 Arms’ dimensions and clearances
5.1.3.1 Arms’ dimensions
Transfer arms’ dimensions shall be determined by the transfer arm manufacturer to ensure that the transfer arms satisfy all specified requirements. For the transfer arm dimensions, the design data in Annex A may be used.
5.1.3.2 Clearance study
The transfer arm design shall accommodate the following minimum clearances unless otherwise specified in Table A.6:
- 0,15 m minimum clearance between any part of an operating arm and a stowed arm;
- 0,3 m minimum clearance between any part of an operating arm and any adjacent structures, piping, equipment;
- 0,3 m minimum clearance between any part of adjacent operating arms;
- 0,15 m minimum clearance between counterweights of operating arms.
ISO/FDIS 22238:2026(en) Table B.1 shows the locations of main clearance checkpoints.
...
Contents
- 1 Scope
- 2 Normative references
- 3 Terms and definitions
- 4 Abbreviated terms
- 5 Design of transfer arms
- 5.1 Definition of the length and the configuration of the transfer arms
- 5.2 Design basis
- 5.3 Swivel joints
- 5.4 Structural bearings
- 5.5 Accessories
- 5.6 Pipework and fitting
- 5.7 Welding
- 5.8 Corrosion protection
- 5.9 Maintenance
- 6 Safety systems
- 6.1 General
- 6.2 Emergency shutdown (ESD) system
- 6.3 Transfer arm position monitoring and alarm systems
- 6.4 Emergency release system (ERS)
- 6.5 ERS
- 7 Connection with the ship
- 7.1 General
- 8 Hydraulic and electric control systems for loading arms
- 8.1 General
- 8.2 Arms’ operations
- 8.3 Hydraulic components
- 8.4 Electric components
- 8.5 Command and control system
- 9 Inspection and tests
- 9.1 General
- 9.2 Prototype test
- 9.3 Manufacturing inspection and tests
- 9.4 Factory acceptance tests
- 9.5 Site acceptance tests
- 10 Quality assurance and control
- 10.1 Quality system
- 10.2 Quality plan
- 11 Required documentation
- Annex A
- 1 Stowed D + W 1,2 S
- 2 Stowed DL + EL 1,2 Sd
- 3 Manoeuvring D + W 0,9 S
- 4 Connected DL + WLO 0,8 Sd
- 5 Connected D + F + P + W 0,8 S
- 6 Connected DL + FL + PL + WLO + TL 1,5 Sd
- 7 Emergency release D + W 1,1 S
- 8 Emergency release DL + FL + PL + WLO 1,1 Sd
- 9 Maintenance D + W 0,9 S
- 10 Hydrostatic test DL + FL + PLT (+ WLM) 1,3 Sd
- Annex B
- 16 PERC
- 25 EDC
- Annex C
- Bibliography
1 Scope
This document specifies the design, minimum safety requirements and inspection and testing procedures for high-pressure natural gas (HPNG) marine transfer arms intended for floating storage and regasification unit (FSRU) /), floating regasification unit (FRU) /and floating storage unit (FSU) applications. High-pressure transfer arms are considered to be ship-to-shore systems transferring pressurized gas from floating units to any part of a gas grid.
This document provides the requirements for power or control systems, but it does not include all the details for the design and fabrication of standard parts and fittings associated with transfer arms. This document supplements the requirements of ISO 28460.
This document is applicable to general electrical-hydraulic systems. It can be applied to other control systems, for example, using only electrical or other power supplies, if they meet the functional safety and performance requirements of Clause 8Clause 8 for the hydraulic and electrical control systems. This document can also be applied to existing facilities.
2 Normative references
The following referenced documents, in whole or in part, are normatively referenced in this document and are indispensable for its application. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies. ISO 3452--1, Non-destructive testing — Penetrant testing — Part 1: General principles ISO 4406, Hydraulic fluid power — Fluids — Method for coding the level of contamination by solid particles ISO 9934--1, Non-destructive testing — Magnetic particle testing — Part 1: General principles ISO 10474, Steel and steel products — Inspection documents ISO 10497, Testing of valves — Fire type-testing requirements ISO 17636--1, Non-destructive testing of welds — Radiographic testing — Part 1: X- and gamma-ray techniques with film ISO 17636--2, Non-destructive testing of welds — Radiographic testing — Part 2: X- and gamma-ray techniques with digital detectors ISO 28460:2010, Petroleum and natural gas industries — Installation and equipment for liquefied natural gas - Ship-to-shore interface and port operations IEC 60034--5, Rotating electrical machines — Part 5: Degrees of protection provided by the integral design of rotating electrical machines (IP code) — Classification IEC 60079--0, Explosive atmospheres — Part 0: Equipment — General requirements IEC 60079--1, Explosive atmospheres — Part 1: Equipment protection by flameproof enclosures “d”
ISO/FDIS 22238:2026(en) IEC 60079--2, Explosive atmospheres — Part 2: Equipment protection by pressurized enclosures “p” IEC 60079--5, Explosive atmospheres — Part 5: Equipment protection by powder filling “q” IEC 60079--6, Explosive atmospheres — Part 6: Equipment protection by oil immersion “o” IEC 60079--7, Explosive atmospheres — Part 7: Equipment protection by increased safety “e” IEC 60079--10--1, Explosive atmospheres — Part 10-1: Classification of areas — Explosive gas atmospheres IEC 60079--11, Explosive atmospheres — Part 11: Equipment protection by intrinsic safety “i” IEC 60079--14, Explosive atmospheres — Part 14: Electrical installations design, selection and erection IEC 60079--18, Explosive atmospheres — Part 18: Equipment protection by encapsulation “m” IEC 60079--25, Explosive atmospheres — Part 25: Intrinsically safe electrical systems IEC 60529, Degrees of protection provided by enclosures (IP Code) and IEC 60529/A1&A2, Amendment 1&2 IEC 61508 (all parts), Functional safety of electrical/electronic/programmable electronic safety-related systems IEC 61511, Functional Safety -— Safety Instrumented Systems for the Process Industry Sector IEC 62305--3, Protection against lightning — Part 3: Physical damage to structures and life hazard ASME B16.5, Pipe Flanges and Flanged Fittings ASME Boiler and Pressure Vessel Code Section IX, Welding and Brazing Qualifications
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply. ISO and IEC maintain terminology databases for use in standardization at the following addresses:
- — ISO Online browsing platform: available at https://www.iso.org/obp
- — IEC Electropedia: available at https://www.electropedia.org/ 3.1 3.1 apex swivel articulated, fluid-carrying joint located between the inboard arm (3.20(3.20)) and outboard arm (3.31(3.31)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
Note 2 to entry: It provides luffing (3.25(3.25)) of the outboard arm relative to the inboard arm.
3.2 3.2 attitude mode of use or location of the transfer arms (3.56(3.56)) (i.e. manoeuvring, stowed, connected, hydrostatic test, and maintenance) Note 1 to entry: The transfer arm can take several positions for each attitude.
ISO/FDIS 22238:2026(en) 3.3 3.3 base riser standpost vertical assembly which bolts to the loading platform and supports the articulated assembly of the transfer arm (3.56(3.56)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.4 3.4 bottom swivel swivel that accommodates the pitch (3.34(3.34)) of a vessel (3.60(3.60)) and is located adjacent to the presentation flange (3.36(3.36)) in the horizontal part of a TSA (3.57(3.57)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.5 3.5 brinelling permanent indentation in swivel or structural bearing (3.48(3.48)) raceways caused by excessive loading of balls or rollers Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.6 3.6 clash contact during operational conditions, or as a result of an emergency separation, between any part of a transfer arm (3.56(3.56)) and:
- — adjacent transfer arm while both arms are operating or one arm is operating and the other arm is stowed [e.g. the counterweights (3.8(3.8)];)];
- — adjacent section of the same transfer arms [e.g. triple swivel assembly (3.57(3.57)) and outboard arm (3.31(3.31)];)];
- — loading platform equipment [e.g. counterweight and piping or valves] 3.7 3.7 contact angle α angle between the plane of the swivel joint (3.53(3.53)) or structural bearing (3.48(3.48)) balls or rollers and the centre of contact at the ball or roller raceway interface 3.8 3.8 counterweight system of weights used to balance the inboard arm (3.20(3.20)) and outboard arm (3.31(3.31)) assemblies
3.9 3.9 design pressure pressure for which the transfer arm (3.56(3.56)) is designed Note 1 to entry: See Table A.1Table A.1..
3.10 3.10 design temperature range of temperatures for which the transfer arm (3.56(3.56)) is designed
ISO/FDIS 22238:2026(en) Note 1 to entry: See Table A.1Table A.1..
3.11 3.11 drift longitudinal and/or lateral displacement of the vessel (3.60(3.60)) under the influence of environmental forces Note 1 to entry: See also surge fore (3.50(3.50)) or surge aft (3.49(3.49)) and sway (3.52(3.52).). 3.12 3.12 emergency disconnection coupler EDC hydraulic, mechanical device used to release the transfer arm (3.56(3.56)) from the vessel (3.60(3.60)) Note 1 to entry: The EDC is a part of the emergency release system (3.13(3.13).). Note 2 to entry: See Figure B.3Figure B.3..
3.13 3.13 emergency release system ERS system that provides a positive means of quick release of transfer arm (3.56(3.56)) and safe isolation between the vessel (3.60(3.60)) and shore, following a predefined procedure including an emergency shutdown (ESD) (3.14(3.14)) Note 1 to entry: See Figure B.2Figure B.2..
3.14 3.14 emergency shutdown ESD method that safely and effectively stops the transfer (3.55(3.55)) of high-pressure natural gas (3.18(3.18)) between the vessel (3.60(3.60)) and shore 3.15 3.15 freeboard vertical distance between the ship's deck and the water level at the manifold location Note 1 to entry: See Table A.3Table A.3 and Figure A.1Figure A.1.. 3.16 3.16 free wheel ability of a transfer arm (3.56(3.56)) when connected to a vessel (3.60(3.60)) to follow the vertical and horizontal motions of the vessel manifold (3.61(3.61)) freely without restraint (draft changes and sway (3.52(3.52)) and surge motions) 3.17 3.17 heave vertical motion of the vessel (3.60(3.60)) due to wave action Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2.. 3.18 3.18 high-pressure natural gas HPNG Gasgas contained within the transfer system at a working pressure (3.62(3.62)) exceeding 10 barg. 10 barg
ISO/FDIS 22238:2026(en) Note 1 to entry: Gas above this pressure threshold may containscan contain sufficient stored compressible energy to require controlled depressurization (blowdown) prior to emergency release system (3.13(3.13)) disconnection. Pressures below this threshold, such as typical low--pressure vapor return service, are not considered high--pressure for the purpose of ERS and blowdown requirements 3.19 3.19 hydraulic power unit HPU unit that generates hydraulic power to ensure the normal operation and emergency release sequence of the systems 3.20 3.20 inboard arm product-carrying pipe and any structural members contained between the apex swivel (3.1(3.1)) and the trunnion swivel (3.58(3.58)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.21 3.21 included angle angle formed between inboard arm (3.20(3.20)) and outboard arm (3.31(3.31)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
Note 2 to entry: The maximum and minimum included angles are left to the transfer arm (3.56(3.56)) manufacturer. Note 3 to entry: The included angle in the stowed position of the transfer arms is such, that the arms are parked with the triple swivel assembly (3.57(3.57)) behind the berthing line.
3.22 3.22 insulating flange electrical insulating system, usually dedicated, which is installed in the lower end of the outboard arm (3.31(3.31)) or in the vertical part of the triple swivel assembly (3.57(3.57)) Note 1 to entry: Its purpose is to prevent stray currents from causing an arc at the vessel’s (3.60(3.60)) flange as the transfer arm (3.56(3.56)) is connected or disconnected.
3.23 3.23 jack permanent, adjustable load-carrying mechanism potentially installed in the triple swivel assembly (3.57(3.57)) to transfer loads or momentum to the deck instead of the vessel manifold (3.61(3.61)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.24 3.24 lowest anticipated service temperature LAST reference temperature based on ambient and process conditions
3.25 3.25 luffing rotary motion of the inboard arm (3.20(3.20)) and outboard arm (3.31(3.31)) in the vertical plane Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
ISO/FDIS 22238:2026(en) 3.26 3.26 manifold connection unit MCU special spool piece (3.45(3.45)) with ship-side ERS (3.13(3.13)) valve for horizontal orientation or special connection frame with elbow, swivel joint and ERS valve for vertical orientation 3.27 3.27 manifold setback horizontal distance between the vessel’s (3.60(3.60)) side and the face of vessel manifold (3.61(3.61)) Note 1 to entry: See Table A.3Table A.3 and Figure A.1Figure A.1.. 3.28 3.28 manifold spacing horizontal distance between two adjacent vessel manifold (3.61(3.61)) flange axes Note 1 to entry: See Table A.3Table A.3 and Figure A.1Figure A.1.. 3.29 3.29 middle swivel swivel that accommodates the yaw (3.63(3.63)) and surge of a vessel (3.60(3.60)) and is located between the top swivel (3.54(3.54)) and the bottom swivel (3.4(3.4)) in the vertical part of a TSA (3.57(3.57)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.30 3.30 operating envelope space in which presentation flange(s) (3.36(3.36)) of a (group of) transfer arms (3.56(3.56)) is (are) required to operate in all directions 3.31 3.31 outboard arm product-carrying pipe and any structural members contained between the apex swivel (3.1(3.1)) and the triple swivel assembly (3.57(3.57)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.32 3.32 owner company or group of companies for whose use the transfer arms (3.56(3.56)) are installed, responsible for the safe design and construction of the installation 3.33 3.33 pantograph system system for transmitting balancing loads from the outboard arm (3.31(3.31)) to the counterweight(s) (3.8(3.8)) Note 1 to entry: The system comprises an assembly of linkages and pinned connections, or a cable and sheaves system (respectively, “rigid link pantograph” and “cables and sheaves pantograph”). 3.34 3.34 pitch rotation of the vessel (3.60(3.60)) around the transversal horizontal axis Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2..
ISO/FDIS 22238:2026(en) 3.35 3.35 powered emergency release coupling PERC powered device to provide a means of quick release of the transfer arm (3.56(3.56)) when such action is required only as an emergency measure 3.36 3.36 presentation flange transfer arm (3.56(3.56)) flange for connection to either the vessel manifold (3.61(3.61)) or spool piece (3.45(3.45)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.37 3.37 product high-pressure natural gas (3.18(3.18)) transferred using transfer arm (3.56(3.56)) 3.38 3.38 remote control device to facilitate the fine manoeuvring operation of the transfer arms (3.56(3.56)) from a remote location [, e.g. vessel manifold (3.61(3.61)) area] Note 1 to entry: The system can use a trailing wire (pendant) and/or radio-controlled system. 3.39 3.39 riser and trunnion swivel assembly gas-carrying system consisting of a riser swivel (3.41(3.41),), a trunnion swivel (3.58(3.58)) and elbows mounted on top of the base riser (3.3(3.3)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.40 3.40 riser flange transfer arm (3.56(3.56)) flange for connection to shore-side piping Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.41 3.41 riser swivel swivel joint in the riser and trunnion swivel assembly (3.39(3.39)) which permits slew (3.44(3.44)) of the transfer arms (3.56(3.56) ) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.42 3.42 roll rotation of vessel (3.60(3.60)) around the longitudinal horizontal axis Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2..
ISO/FDIS 22238:2026(en) 3.43 3.43 safety integrity level SIL level of integrity required of a safety-related system Note 1 to entry: Safety-related systems shall be in accordance with the IEC 61508 series. Note 2 to entry: See Clause 6Clause 6..
3.44 3.44 slew horizontal, rotary motion of the transfer arm (3.56(3.56)) around the base riser (3.3(3.3)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.45 3.45 spool piece adaptor short distance piece short length of pipe for the purpose of matching the vessel manifold (3.61(3.61)) to the presentation flange (3.36(3.36)) 3.46 3.46 spotting line pre-determined location on the jetty used by the vessel (3.60(3.60)) when berthing to align the vessel manifold(s) (3.61(3.61)) Note 1 to entry: See Figure A.4Figure A.4..
3.47 3.47 stress analysis detailed calculation of the structural loading in the transfer arm (3.56(3.56)) and vessel manifold (3.61(3.61)) for various positions and attitudes (3.2(3.2)) to check the integrity of the transfer arm for the service intended 3.48 3.48 structural bearing bearing in the load carrying components supporting the product (3.37(3.37)) line that, in combination, allow the transfer arm (3.56(3.56)) to follow freely the motion of the vessel (3.60(3.60))
3.49 3.49 surge aft longitudinal vessel (3.60(3.60)) afterward motion Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2.. 3.50 3.50 surge fore longitudinal vessel (3.60(3.60)) forward motion Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2..
ISO/FDIS 22238:2026(en) 3.51 3.51 pressure surge rapid change in pressure as a consequence of a change in flow rate in a pipeline and/or piping systems [, including transfer arm (3.56(3.56)]) 3.52 3.52 sway transverse vessel (3.60(3.60)) motion Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2.. 3.53 3.53 swivel swivel joint rotating connection contained in the transfer arm (3.56(3.56)) to permit the arm/system to follow freely the motion of the vessel (3.60(3.60)) 3.54 3.54 top swivel swivel that accommodates the roll (3.42(3.42),), heave (3.17(3.17)) and sway (3.52(3.52)) of a vessel (3.60(3.60)) and is located between the outboard arm (3.31(3.31)) and the middle swivel (3.29(3.29)) in the horizontal part of a TSA (3.57(3.57)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.55 3.55 transfer transmission of high-pressure natural gas (3.18(3.18)) from the vessel (3.60(3.60)) to any fixed part of a harbour or coastal locations 3.56 3.56 transfer arm articulated mechanical system used for transmission of a product (3.37(3.37)) from vessel (3.60(3.60)) with the capability of accommodating differences in tides, freeboard (3.15(3.15)) and vessel’s motions Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.57 3.57 triple swivel assembly TSA group of three swivels (3.53(3.53)) and elbows located at the end of the outboard arm (3.31(3.31)) Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
3.58 3.58 trunnion swivel swivel joint in the riser and trunnion swivel assembly (3.39(3.39)) which permits the inboard arm (3.20(3.20)) to rotate around the horizontal or vertical axis Note 1 to entry: See Figures B.2Figures B.2 and B.3B.3..
ISO/FDIS 22238:2026(en) 3.59 3.59 UPS uninterrupted power supply back-up of the electrical supply system providing power to critical control and safety systems so that the plant can be kept in safe conditions 3.60 3.60 vessel floating unit for the storage and/ or regasification of LNG and for sending out high-pressure natural gas (3.18(3.18)) (also known as FSRU/FSU/FRU) 3.61 3.61 vessel manifold pipe assembly mounted onboard vessel (3.60(3.60)) to which the presentation flange (3.36(3.36)) or spool piece (3.45(3.45)) of the transfer arm (3.56(3.56)) is connected 3.62 3.62 working pressure the maximum internal pressure that a transfer system is designed to operate under during normal, steady--state service, including all expected process variations but excluding short--duration pressure transients associated with start--up, shutdown, or abnormal conditions 3.63 3.63 yaw rotation of the vessel (3.60(3.60)) around the vertical axis Note 1 to entry: See Table A.4Table A.4 and Figure A.2Figure A.2..
4 Abbreviated terms
CPMS constant position monitoring system EMC electro-magnetic compatibility FL fluid load FMEDA failure mode and effects analysis HP high pressure LNG liquefied natural gas N nitrogen gas
OBE operating basis earthquake OEM original equipment manufacturer PL pressure load PQR performance quality records SSE safe shutdown earthquake TL thermal load WL wind load WPS welding procedure specifications ρ density v velocity
ISO/FDIS 22238:2026(en)
5 Design of transfer arms
5.1 Definition of the length and the configuration of the transfer arms
5.1.1 General
The general arrangement of the transfer arm is shown in Annex BAnnex B (see Figures B.2Figures B.2 and B.3B.3).).
The length and the configuration of the transfer arms shall allow for the connection of the on-shore piping to the vessel manifold. The connection shall allow for free movement within the operating envelope. The transfer arms are normally composed of the following:
- — TSA;
- — ERS including PERC or EDC;
- — manifold connection unit mounted on-board the vessel, if required;
- — outboard arm;
- — apex swivel assembly between the outboard and inboard arm;
- — pantograph system;
- — inboard arm;
- — riser and trunnion swivel assembly between the inboard arm and the base riser;
- — base riser.
All piping supports shall be designed so that stresses in the piping and the structure are within allowable limits for all positions.
Any parts of a transfer arm, for example, seals, bolts and nuts, shall not come off or unfasten and drop into product piping under any circumstances.
...
Contents
- 1 Domaine d'application
- 2 Références normatives
- 3 Termes et définitions
- 3.1 rotation d’ouverture du compas (rotation médiane)
- 3.2 position de travail
- 3.3 embase
- 3.4 rotation inférieure
- 3.5 marquage (des chemins de roulement)
- 3.6 interférence
- 3.7 angle de contact
- 3.8 contrepoids
- 3.9 pression de calcul
- 3.10 température de calcul
- 3.11 dérive
- 3.12 coupleur de déconnexion d'urgence
- 3.13 système de déconnexion d’urgence
- 3.14 arrêt d'urgence (emergency shutdown)
- 3.15 franc-bord
- 3.16 roue libre
- 3.17 pilonnement
- 3.18 gaz naturel haute pression
- 3.19 centrale hydraulique
- 3.20 bras interne
- 3.21 angle d'ouverture
- 3.22 bride d'isolation
- 3.23 support
- 3.24 LAST
- 3.25 relevage
- 3.26 unité de connexion de la traverse
- 3.27 recul de la traverse
- 3.28 espacement des traverses
- 3.29 rotation moyenne
- 3.30 enveloppe de fonctionnement
- 3.31 bras externe
- 3.32 propriétaire
- 3.33 système de pantographe
- 3.34 tangage
- 3.35 déconnecteur d'urgence énergisé (power emergency release coupler)
- 3.36 bride de présentation
- 3.37 produit
- 3.38 dispositif de commande à distance
- 3.39 ensemble embase et rotation horizontale d'embase
- 3.40 bride d'embase
- 3.41 rotation de l’embase
- 3.42 roulis
- 3.43 niveau d'intégrité de sécurité
- 3.44 pivotement
- 3.45 manchette de raccordement
- 3.46 repère d’alignement du navire
- 3.47 analyse des contraintes
- 3.48 articulations de structure
- 3.49 cavalement arrière
- 3.50 cavalement avant
- 3.51 coup de bélier
- 3.52 balancement
- 3.53 joint articulé/rotation
- 3.54 rotation supérieure
- 3.55 transfert
- 3.56 bras de transfert
- 3.57 ensemble articulé triple
- 3.58 rotation horizontale d'embase
- 3.59 dispositif d’alimentation continue (uninterrupted power supply)
- 3.60 navire
- 3.61 traverse du navire
- 3.62 pression de service
- 3.63 lacet
- 4 Abréviations
- 5 Conception des bras de transfert
- 5.1 Définition de la longueur et de la configuration des bras de transfert
- 5.2 Base de modélisation
- 5.3 Joints articulés
- 5.4 Articulations de structure
- 5.5 Accessoires
- 5.6 Tuyauterie et raccord
- 5.7 Soudage
- 5.8 Protection contre la corrosion
- 5.9 Maintenance
- 6 Systèmes de sécurité
- 6.1 Généralités
- 6.2 Système d'arrêt d'urgence (ESD)
1 Domaine d'application
La présente Norme internationale spécifie la conception, les exigences minimales de sécurité et les procédures d'inspection et d'essai pour les bras de transfert marins de gaz naturel à haute pression (HPNG) destinés aux applications unité flottante de stockage et regazéification (FSRU), unité flottante de regazéification (FRU) et unité flottante de stockage (FSU). Les bras de transfert haute pression sont considérés comme des systèmes terre-navire qui transfèrent du gaz sous pression depuis des unités flottantes vers toute partie d'un réseau de gaz.
Bien que les exigences relatives aux systèmes d'alimentation/de commande soient couvertes, la présente Norme internationale n'inclut pas tous les détails relatifs à la conception et à la fabrication des pièces et accessoires standards associés aux bras de transfert.
La présente Norme internationale complète les normes et réglementations locales ou nationales et s'ajoute aux exigences de l'ISO 28460.
La présente norme était basée sur le système hydraulique général. D'autres systèmes de commande, par exemple ceux utilisant uniquement de l'électricité ou toute autre production d'électricité, peuvent être acceptables s'ils ont été développés, soumis à essai et qualifiés pour les normes correspondantes et s'ils garantissent toutes les fonctions de sécurité et les performances fonctionnelles décrites à l'Article 8 pour le système de commande hydraulique et électrique.
La présente Norme internationale peut également être utilisée pour les installations existantes.
2 Références normatives
Les documents suivants, dans leur intégralité ou non, sont des références normatives indispensables à l’application du présent document. Pour les références datées, seule l'édition citée s'applique. Pour les références non datées, la dernière édition du document de référence s'applique (y compris les éventuels amendements).
ISO 3452-1, Essais non destructifs — Examen par ressuage — Partie 1: Principes généraux ISO 4406, Transmissions hydrauliques — Fluides — Méthode de codification du niveau de pollution particulaire solide ISO 9606-1, Épreuve de qualification des soudeurs — Soudage par fusion — Partie 1: Aciers ISO 9934-1, Essais non destructifs — Magnétoscopie — Partie 1: Principes généraux du contrôle ISO 10474:2013, Aciers et produits sidérurgiques — Documents de contrôle ISO 10497, Essais des appareils de robinetterie — Exigences de l'essai au feu ISO 15614-1:2017, Descriptif et qualification d'un mode opératoire de soudage pour les matériaux métalliques - Épreuve de qualification d'un mode opératoire de soudage — Partie 1: Soudage à l'arc et aux gaz des aciers et soudage à l'arc du nickel et des alliages de nickel ISO/TR 17177:2015, Pétrole et industries du gaz naturel — Lignes directrices pour les interfaces de terminaux hybrides de GNL
ISO/FDIS 22238:2026(fr) ISO 17636-1, Essais non destructifs des assemblages soudés — Contrôle par radiographie — Partie 1: Techniques par rayons X ou gamma à l'aide de film ISO 17636-2, Essais non destructifs des assemblages soudés — Contrôle par radiographie — Partie 2: Techniques par rayons X ou gamma à l'aide de détecteurs numériques ISO 28460, Industries du pétrole et du gaz naturel — Installations et équipements relatifs au gaz naturel liquéfié - Interface terre-navire et opérations portuaires IEC 31010:2019, Management du risque — Techniques d'appréciation du risque IEC 60034-5, Machines électriques tournantes — Partie 5: Degrés de protection procurés par la conception intégrale de machines électriques tournantes (code IP) — Classification IEC 60079-0, Atmosphères explosives — Partie 0: Matériel — Exigences générales IEC 60079-1, Atmosphères explosives — Partie 1: Protection du matériel par enveloppes antidéflagrantes «d» IEC 60079-2, Atmosphères explosives — Partie 2: Protection du matériel par enveloppe à surpression interne «p» IEC 60079-5, Atmosphères explosives — Partie 5: Protection du matériel par remplissage pulvérulent «q» IEC 60079-6, Atmosphères explosives — Partie 6: Protection du matériel par immersion dans le liquide «o» IEC 60079-7, Atmosphères explosives — Partie 7: Protection du matériel par sécurité augmentée «e» IEC 60079-10-1, Atmosphères explosives — Partie 10-1: Classification des emplacements — Atmosphères explosives gazeuses IEC 60079-11, Atmosphères explosives — Partie 11: Protection de l’appareil par sécurité intrinsèque «i» IEC 60079-14, Atmosphères explosives — Partie 14: Conception, sélection et construction des installations électriques IEC 60079-18, Atmosphères explosives — Partie 18: Protection de l’appareil par encapsulage «m» IEC 60079-25, Atmosphères explosives — Partie 25: Systèmes électriques de sécurité intrinsèque IEC 60529, Degrés de protection procurés par les enveloppes (Code IP) et IEC 60529/A1&A2, Amendement 1&2 IEC 61508 (toutes les parties), Sécurité fonctionnelle des systèmes électriques/électroniques/électroniques programmables relatifs à la sécurité IEC 61511, Sécurité fonctionnelle — Systèmes instrumentés de sécurité pour le secteur des industries de transformation IEC 62305-3, Protection contre la foudre — Partie 3: Dommages physiques sur les structures et risques humains ASME B16.5, Pipe Flanges and Flanged Fittings ASME Boiler and Pressure Vessel Code Section IX, Welding and Brazing Qualifications OCIMF, Design and Construction Specification for Marine Loading Arms ATEX Atmosphères Explosives SIGTTO Society of International Gas Tanker and Terminal Operators
3 Termes et définitions
Pour les besoins du présent document, les termes et définitions suivants s'appliquent.
ISO/FDIS 22238:2026(fr) L'ISO et l'IEC tiennent à jour des bases de données terminologiques destinées à être utilisées en normalisation, consultables aux adresses suivantes:
- ISO Online browsing platform: disponible à l’adresse https:// www .iso .org/ obp
- IEC Electropedia: disponible à l'adresse https:// www .electropedia .org/
3.1 rotation d’ouverture du compas (rotation médiane)
raccord articulé, conçu pour le transfert des liquides et situé entre le bras interne (3.20) et le bras externe (3.31) Note 1 à l'article: Voir Figures B.2.
Note 2 à l'article: Il permet le relevage (3.25) du bras externe par rapport au bras interne.
3.2 position de travail
divers modes d'utilisation et/ou de positionnement des bras de transfert (3.56) (manœuvre, stockage, connexion, essai hydrostatique et maintenance) Note 1 à l'article: Le bras de transfert peut avoir différentes positions pour chaque position de travail.
3.3 embase
fût du bras qui est assemblé à la plate-forme de chargement et qui supporte l'ensemble articulé du bras de transfert (3.56) Note 1 à l'article: Voir Figures B.2.
Note 2 à l'article: Cet ensemble est parfois désigné par le terme «colonne support».
3.4 rotation inférieure
supporte le mouvement de tangage (3.34) d'un navire et est située de façon contiguë à la bride de présentation (3.36) dans la partie horizontale du TSA (3.57) Note 1 à l'article: Voir Figures B.2.
3.5 marquage (des chemins de roulement)
toute empreinte permanente située sur les chemins de roulement ou les articulations de structure (3.48) provoquée par le chargement excessif des billes ou des galets Note 1 à l'article: Voir Figures B.2.
3.6 interférence
tout contact, dans des conditions opérationnelles de conception ou suite à une déconnexion d'urgence, entre tout ou partie d'un bras de transfert (3.56) et:
- le bras de transfert contigu, alors que tous deux sont en service, ou lorsque l'un est en service et l'autre en position de stockage [par exemple les contrepoids (3.8)];
- la section contiguë des mêmes bras de transfert [par exemple l'ensemble articulé triple (3.57) et le bras externe (3.31)];
- l'équipement de la plate-forme de chargement [par exemple le contrepoids (3.8) ou les vannes]
ISO/FDIS 22238:2026(fr)
3.7 angle de contact
α angle entre le plan du chemin des billes ou des galets du joint articulé (3.53) ou de l’articulation de structure (3.48) et le point de contact de la bille ou du galet sur le chemin de roulement
3.8 contrepoids
système de poids utilisés pour équilibrer les ensembles bras interne (3.20) et bras externe (3.31)
3.9 pression de calcul
pression pour laquelle est conçu le bras de transfert (3.56) Note 1 à l'article: Voir le Tableau A.1.
3.10 température de calcul
plage des températures pour lesquelles le bras de transfert (3.56) est conçu Note 1 à l'article: Voir le Tableau A.1.
3.11 dérive
déplacement longitudinal et/ou latéral du navire (3.60) sous l'influence des facteurs environnementaux Note 1 à l'article: Voir également cavalement avant (3.50) ou arrière (3.49) et balancement (3.52).
3.12 coupleur de déconnexion d'urgence
EDC coupleur dispositif mécanique hydraulique utilisé pour déconnecter le bras de transfert (3.56) du navire (3.60). Fait partie du système de déconnexion d'urgence Note 1 à l'article: Voir Figures B.2.
3.13 système de déconnexion d’urgence
ERS (emergency release system) système permettant la déconnexion positive rapide des bras de transfert (3.56) et garantissant une isolation sûre entre le navire et la terre, selon une procédure prédéfinie comprenant un arrêt d’urgence (ESD) (3.14) Note 1 à l'article: Voir Figures B.2.
3.14 arrêt d'urgence (emergency shutdown)
ESD méthode permettant d'interrompre de manière sûre et efficace le transfert de HPNG entre le navire et la terre
3.15 franc-bord
élévation du pont du navire au-dessus du niveau de la mer à l'endroit des traverses Note 1 à l'article: Voir le Tableau A.3 et la Figure A.1.
3.16 roue libre
capacité d'un bras de transfert (3.56) lorsqu'il est connecté à un navire à suivre librement les mouvements verticaux et horizontaux des traverses du navire, (changements de tirant d'eau, ainsi que balancement (3.52) et cavalement)
ISO/FDIS 22238:2026(fr)
3.17 pilonnement
mouvement vertical du navire provoqué par l'action des vagues Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
3.18 gaz naturel haute pression
HPNG gaz contenu dans le système de transfert à une pression de service (3.62) supérieure à 10 barg Note 1 à l'article: Le gaz dont la pression dépasse ce seuil peut contenir suffisamment d’énergie compressible stockée pour nécessiter une dépressurisation contrôlée (purge) avant la déconnexion du système de déconnexion d’urgence (3.13). Les pressions inférieures à ce seuil, telles que celles typiquement observées dans les circuits de retour de vapeur à basse pression, ne sont pas considérées comme des pressions élevées au regard des exigences relatives au système de déconnexion d’urgence (ERS) et à la purge
3.19 centrale hydraulique
HPU centrale qui génère la puissance hydraulique pour assurer le fonctionnement normal et la séquence de déconnexion d’urgence des systèmes
3.20 bras interne
tuyauterie transportant le produit et toute structure porteuse située entre la rotation d’ouverture du compas (3.1) et la rotation horizontale d'embase (3.58) Note 1 à l'article: Voir Figures B.2.
3.21 angle d'ouverture
angle formé entre le bras interne (3.20) et le bras externe (3.31) Note 1 à l'article: Voir Figures B.2.
Note 2 à l'article: Les angles d'ouverture minimaux et maximaux sont laissés à la discrétion du fabricant du bras de transfert.
Note 3 à l'article: Lorsque les bras de transfert (3.56) sont en position de stockage, il est nécessaire que l'angle d'ouverture soit tel que l'ensemble articulé triple (3.57) se trouve derrière la ligne d'accostage.
3.22 bride d'isolation
système d'isolation électrique, généralement dédié, installé sur l'extrémité inférieure du bras externe (3.31) ou dans la partie verticale de l'ensemble articulé triple (3.57) Note 1 à l'article: Ce système permet d'éviter que les courants vagabonds ne créent un arc électrique au niveau de la bride du navire lors de la connexion ou de la déconnexion du bras de transfert (3.56)
3.23 support
mécanisme de reprise de charge, permanent et ajustable, potentiellement installé sur l'ensemble articulé triple (3.57) pour transférer des charges ou un mouvement sur le pont et non sur la traverse du navire (3.61) Note 1 à l'article: Voir Figures B.2 et B3.
3.24 LAST
température de service anticipée la plus basse cabine de commande située sur la jetée ou à proximité, essentiellement pour diriger et/ou contrôler les
ISO/FDIS 22238:2026(fr)
3.25 relevage
mouvements rotatifs du bras interne (3.20) et du bras externe (3.31) dans le plan vertical Note 1 à l'article: Voir Figures B.2.
3.26 unité de connexion de la traverse
MCU manchette de raccordement spéciale avec vanne du système de déconnexion d'urgence côté bateau pour l'orientation horizontale, ou cadre de connexion spécial avec coude, joint articule et vanne du système de déconnexion d'urgence pour l'orientation verticale
3.27 recul de la traverse
distance horizontale qui sépare la muraille du navire et la face de la traverse du navire (3.61) Note 1 à l'article: Voir le Tableau A.3 et la Figure A.1.
3.28 espacement des traverses
distance horizontale qui sépare les axes de deux traverses du navire (3.61) contiguës Note 1 à l'article: Voir le Tableau A.3 et la Figure A.1.
3.29 rotation moyenne
supporte le lacet (3.62) et le cavalement du navire (3.60) et est située entre la rotation supérieure (3.54) et la rotation inférieure (3.4) dans la partie verticale du TSA (3.57) Note 1 à l'article: Voir Figures B.2.
3.30 enveloppe de fonctionnement
espace dans lequel doit ou doivent fonctionner la ou les brides de présentation (3.36) d'un bras de transfert individuel ou d’un groupe de bras de transfert (3.56)
3.31 bras externe
tuyauterie de transport du produit et toute structure porteuse située entre la rotation d'ouverture du compas (3.1) et l'ensemble articulé triple (3.57) Note 1 à l'article: Voir Figures B.2.
3.32 propriétaire
société ou groupe de sociétés pour lesquels les bras de transfert (3.56) sont installés pour utilisation. Le propriétaire est responsable de la conception de la sécurité et de la construction de l’installation
3.33 système de pantographe
système utilisé pour transmettre au(x) contrepoids (3.8) les charges d'équilibrage du bras externe (3.31) Note 1 à l'article: Le système est constitué d'un ensemble de tringleries et de connexions articulées, ou bien d'un système de câbles et de poulies (respectivement «pantographe par liaison rigide» et «câbles et poulies pantographes»).
3.34 tangage
rotation du navire (3.60) autour de l'axe horizontal transversal Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
ISO/FDIS 22238:2026(fr)
3.35 déconnecteur d'urgence énergisé (power emergency release coupler)
PERC dispositif énergisé permettant de déconnecter rapidement les bras de transfert (3.56) lorsqu’une telle action est requise uniquement en cas d'urgence
3.36 bride de présentation
bride d'un bras de transfert (3.56) pour connexion à la traverse du navire (3.61) ou à la manchette de raccordement (3.45) Note 1 à l'article: Voir Figures B.2.
3.37 produit
gaz naturel haute pression (3.18) transféré par le bras de transfert (3.56)
3.38 dispositif de commande à distance
commande à distance dispositif destiné à faciliter les opérations délicates de connexion et/ou de déconnexion des brides des bras de transfert (3.56) à distance (par exemple zone de traverse du navire (3.61)) Note 1 à l'article: La commande peut être à fil ou radiocommandée.
3.39 ensemble embase et rotation horizontale d'embase
système de transport du gaz composé de la rotation de l’embase (3.41), la rotation horizontale d'embase (3.58) et de coudes et monté au sommet de l'embase (3.3) Note 1 à l'article: Voir Figures B.2.
3.40 bride d'embase
bride d'un bras de transfert (3.56) pour le raccordement aux tuyauteries côte terre Note 1 à l'article: Voir Figures B.2.
3.41 rotation de l’embase
joint articulé de l'ensemble embase et rotation horizontale d'embase (3.39) qui permet le pivotement (3.44) des bras de transfert (3.56) Note 1 à l'article: Voir Figures B.2.
3.42 roulis
rotation du navire (3.60) autour de l'axe horizontal longitudinal Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
3.43 niveau d'intégrité de sécurité
SIL niveau d'intégrité requis d'un système relatif à la sécurité dans les termes de l'IEC 61508 Note 1 à l'article: Voir l'Article 6.
3.44 pivotement
mouvement de rotation horizontal du bras de transfert (3.56) autour de l'embase (3.3) Note 1 à l'article: Voir Figures B.2.
ISO/FDIS 22238:2026(fr)
3.45 manchette de raccordement
courte longueur de tuyauterie destinée à faire concorder la traverse du navire (3.61) et la bride de présentation (3.36) Note 1 à l'article: Ces dispositifs sont parfois appelés «adaptateurs» ou «réductions».
3.46 repère d’alignement du navire
marquage utilisé par le navire (3.60) au moment de l'accostage pour aligner la ou les traverses du navire Note 1 à l'article: Voir la Figure A.4.
3.47 analyse des contraintes
calcul détaillé des charges structurelles exercées sur le bras de transfert (3.56) et la traverse du navire (3.61) en fonction des différentes conditions et positions de travail (3.2), permettant de vérifier l'intégrité du bras de transfert pour les différents modes d'utilisation prévus
3.48 articulations de structure
roulements des organes porteurs qui soutiennent la canalisation de produit et qui, associés à d'autres éléments, permettent au bras de transfert (3.56) de suivre librement le mouvement du navire (3.60)
3.49 cavalement arrière
déplacement longitudinal du navire (3.60) vers l’arrière Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
3.50 cavalement avant
déplacement longitudinal du navire (3.60) vers l’avant Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
3.51 coup de bélier
modification rapide de la pression provoquée par un changement du débit dans une canalisation et/ou dans des systèmes de canalisations (ce qui inclut les bras de transfert (3.56))
3.52 balancement
mouvement transversal du navire (3.60) Note 1 à l'article: Voir le Tableau A.4 et la Figure A.2.
3.53 joint articulé/rotation
joint articulé contenu dans le bras de transfert (3.56) qui permet au bras/système de suivre librement le mouvement du navire (3.60)
3.54 rotation supérieure
supporte le mouvement de roulis (3.42), de pilonnement et de balancement du navire (3.60) et est située entre le bras externe (3.31) et la rotation moyenne (3.29) dans la partie horizontale du TSA (3.57) Note 1 à l'article: Voir Figures B.2.
3.55 transfert
transfert de HPNG depuis le navire vers toute partie fixe du terminal d'importation
ISO/FDIS 22238:2026(fr)
3.56 bras de transfert
bras de transfert articulé en métal utilisé pour transférer un produit (3.37) depuis le navire (3.60) avec la capacité de supporter des différences de marées, le franc-bord (3.15) et les mouvements du navire Note 1 à l'article: Voir Figures B.2.
3.57 ensemble articulé triple
TSA ensemble de trois rotations (3.53) et coudes situé à l'extrémité du bras externe (3.31) Note 1 à l'article: Voir la Figure B.2.
3.58 rotation horizontale d'embase
joint articulé dans l'ensemble embase et rotation horizontale d'embase (3.39) qui permet la rotation du bras interne (3.20) autour de l'axe horizontal Note 1 à l'article: Voir la Figure B.2.
3.59 dispositif d’alimentation continue (uninterrupted power supply)
UPS source de secours du système principal d'alimentation électrique fournissant l'énergie nécessaire aux commandes critiques et aux systèmes de sécurité afin que les installations puissent être maintenues dans des conditions de sécurité
...