ASTM D6773-22
(Test Method)Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester
Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester
SIGNIFICANCE AND USE
5.1 Reliable, controlled flow of bulk solids from bins and hoppers is essential in almost every industrial facility. Unfortunately, flow stoppages due to arching and ratholing are common. Additional problems include uncontrolled flow (flooding) of powders, segregation of particle mixtures, usable capacity which is significantly less than design capacity, caking and spoilage of bulk solids in stagnant zones, and structural failures.
5.2 By measuring the flow properties of bulk solids, and designing bins and hoppers based on these flow properties, most flow problems can be prevented or eliminated (1).3
5.3 For bulk solids with a significant percentage of particles (typically, one third or more) finer than about 6 mm (1/4 in.), the unconfined yield strength is governed by the fines (−6 mm fraction). For such bulk solids, strength and wall friction tests may be performed on the fine fraction only.
Note 1: The quality of the result produced by this standard is dependent on the competence of personnel performing it, and the suitability of the equipment and facilities used. Agencies that meet the criteria of Practice D3740 are generally considered capable of competent and objective testing/sampling/inspection/etc. Users of this standard are cautioned that compliance with Practice D3740 does not in itself ensure reliable results. Reliable results depend on many factors; Practice D3740 provides a means of evaluating some of those factors. Practice D3740 was developed for agencies engaged in the testing or inspection (or both) of soil and rock. As such it is not totally applicable to agencies performing this standard. However, users of this standard should recognize that the framework of Practice D3740 is appropriate for evaluating the quality of an agency performing this standard. Currently there is no known qualifying national authority that inspects agencies that perform this standard.
SCOPE
1.1 This test method covers the apparatus and procedures for measuring the unconfined yield strength of bulk solids during both continuous flow and after storage at rest. In addition, measurements of internal friction, bulk density, and wall friction on various wall surfaces are included.
1.2 This test method covers operation of the manually-controlled Schulze Ring Shear Tester. An automated version of this tester is also available. Its method of testing bulk solids is similar in principle to that described in this test method.
1.3 The most common use of this information is in the design of storage bins and hoppers to prevent flow stoppages due to arching and ratholing, including the slope and smoothness of hopper walls to provide mass flow. Parameters for structural design of such equipment may also be derived from this data. Another application is the measurement of the flowability of bulk solids, for example, for comparison of different products or optimization.
1.4 All observed and calculated values shall conform to the guidelines for significant digits and rounding established in Practice D6026.
1.4.1 The procedures used to specify how data are collected/recorded or calculated in this standard are regarded as the industry standard. In addition, they are representative of the significant digits that generally should be retained. The procedures used do not consider material variation, purpose for obtaining the data, special purpose studies, or any considerations for the user’s objectives: and it is common practice to increase or reduce significant digits of reported data to be commensurate with these considerations. It is beyond the scope of this standard to consider significant digits used in analysis methods for engineering design.
1.5 Units—The values stated in SI units are to be regarded as standard. No other units of measure are included in this standard.
1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the respons...
General Information
- Status
- Published
- Publication Date
- 14-Oct-2022
- Technical Committee
- D18 - Soil and Rock
- Drafting Committee
- D18.24 - Characterization and Handling of Powders and Bulk Solids
Relations
- Effective Date
- 01-Feb-2024
- Effective Date
- 01-Nov-2023
- Effective Date
- 01-Oct-2019
- Effective Date
- 01-Mar-2019
- Effective Date
- 01-May-2015
- Refers
ASTM D6128-14 - Standard Test Method for Shear Testing of Bulk Solids Using the Jenike Shear Cell - Effective Date
- 01-Sep-2014
- Effective Date
- 01-Aug-2014
- Effective Date
- 01-May-2014
- Effective Date
- 01-May-2013
- Effective Date
- 01-May-2013
- Effective Date
- 01-May-2012
- Effective Date
- 01-Mar-2012
- Effective Date
- 01-Nov-2011
- Effective Date
- 01-Sep-2011
- Effective Date
- 01-Sep-2011
Overview
ASTM D6773-22: Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester is a widely recognized ASTM International standard that specifies the procedures and apparatus for measuring the flow properties of bulk solids. This standard is essential for understanding how materials such as powders and granules behave during handling and storage, particularly in bins and hoppers. The Schulze Ring Shear Tester provides reliable measurements of unconfined yield strength, internal friction, bulk density, and wall friction, informing design decisions to avoid common flow issues in industrial facilities.
Key Topics
- Bulk Solid Flow Properties: The standard outlines methodologies for quantifying the strength and flow characteristics of bulk solids, which are critical parameters in storage and process engineering.
- Schulze Ring Shear Tester: Describes apparatus setup, operational procedures, and testing protocols for both manually-controlled and automated versions of the tester.
- Unconfined Yield Strength Measurement: Focuses on assessing a bulk solid’s ability to resist deformation and flow under various load conditions.
- Wall Friction and Bulk Density: Includes procedures for measuring how bulk solids interact with hopper and bin surfaces, impacting flow and potential for blockages.
- Flow Problem Prevention: Guidance for preventing flow stoppages such as arching, ratholing, caking, and uncontrolled flow (flooding) through proper measurement and design.
- Test Results Significance: Stresses the importance of competent personnel, suitable equipment, and adherence to significant digits and rounding conventions as per ASTM guidelines.
Applications
ASTM D6773-22 is used across a range of industries where the handling of bulk solids is routine, such as:
- Storage Design: Informing the design of bins, hoppers, silos, and other storage vessels to ensure consistent mass flow and to prevent common issues such as flow stoppages, arching, and ratholing.
- Material Comparison: Comparing the flowability of different powders and granulates to select optimum materials for specific processes.
- Process Optimization: Supporting optimization of handling, storage, and transport processes for powders, grains, pharmaceuticals, chemicals, and food products.
- Segregation and Caking Prevention: Helps in identifying and mitigating risks of particle mixture segregation, caking, spoilage in stagnant zones, and even structural failures.
- Product Development and Quality Control: Assessing material flow properties during product development or routine quality checks.
The standard is especially valuable for materials where the fine fraction (particles <6 mm) significantly influences flow behavior. For these materials, the strength and wall friction tests may focus on the finer particle fraction.
Related Standards
Bulk solids testing and geotechnical material characterization often reference several complementary ASTM standards:
- ASTM D653 - Terminology Relating to Soil, Rock, and Contained Fluids
- ASTM D2216 - Test Methods for Laboratory Determination of Water Content of Soil and Rock
- ASTM D3740 - Practice for Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock
- ASTM D4753 - Guide for Evaluating, Selecting, and Specifying Balances and Standard Masses for Use in Soil, Rock, and Construction Materials Testing
- ASTM D6026 - Practice for Using Significant Digits and Data Records in Geotechnical Data
- ASTM D6128 - Shear Testing of Bulk Solids Using the Jenike Shear Tester
- ASTM E177 - Practice for Use of the Terms Precision and Bias
- ASTM E691 - Practice for Interlaboratory Study to Determine Precision of a Test Method
Practical Value
The methodologies described in ASTM D6773-22 enable:
- Selection of optimal storage and conveyance system designs
- Prevention of costly downtime due to flow interruptions
- Improved safety and structural stability of bulk storage systems
- Enhanced product quality by maintaining material integrity during handling
By adopting the practices in ASTM D6773-22, facilities can ensure reliable, efficient, and safe handling of bulk solids – minimizing operational risks and maximizing productivity.
Buy Documents
ASTM D6773-22 - Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester
REDLINE ASTM D6773-22 - Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester
Get Certified
Connect with accredited certification bodies for this standard

Control Union Certifications
Global certification for agriculture and sustainability.

Bureau Veritas Bangladesh
Bureau Veritas certification services in Bangladesh.

ECOCERT France
Leader in organic and sustainability certification worldwide.
Sponsored listings
Frequently Asked Questions
ASTM D6773-22 is a standard published by ASTM International. Its full title is "Standard Test Method for Bulk Solids Using Schulze Ring Shear Tester". This standard covers: SIGNIFICANCE AND USE 5.1 Reliable, controlled flow of bulk solids from bins and hoppers is essential in almost every industrial facility. Unfortunately, flow stoppages due to arching and ratholing are common. Additional problems include uncontrolled flow (flooding) of powders, segregation of particle mixtures, usable capacity which is significantly less than design capacity, caking and spoilage of bulk solids in stagnant zones, and structural failures. 5.2 By measuring the flow properties of bulk solids, and designing bins and hoppers based on these flow properties, most flow problems can be prevented or eliminated (1).3 5.3 For bulk solids with a significant percentage of particles (typically, one third or more) finer than about 6 mm (1/4 in.), the unconfined yield strength is governed by the fines (−6 mm fraction). For such bulk solids, strength and wall friction tests may be performed on the fine fraction only. Note 1: The quality of the result produced by this standard is dependent on the competence of personnel performing it, and the suitability of the equipment and facilities used. Agencies that meet the criteria of Practice D3740 are generally considered capable of competent and objective testing/sampling/inspection/etc. Users of this standard are cautioned that compliance with Practice D3740 does not in itself ensure reliable results. Reliable results depend on many factors; Practice D3740 provides a means of evaluating some of those factors. Practice D3740 was developed for agencies engaged in the testing or inspection (or both) of soil and rock. As such it is not totally applicable to agencies performing this standard. However, users of this standard should recognize that the framework of Practice D3740 is appropriate for evaluating the quality of an agency performing this standard. Currently there is no known qualifying national authority that inspects agencies that perform this standard. SCOPE 1.1 This test method covers the apparatus and procedures for measuring the unconfined yield strength of bulk solids during both continuous flow and after storage at rest. In addition, measurements of internal friction, bulk density, and wall friction on various wall surfaces are included. 1.2 This test method covers operation of the manually-controlled Schulze Ring Shear Tester. An automated version of this tester is also available. Its method of testing bulk solids is similar in principle to that described in this test method. 1.3 The most common use of this information is in the design of storage bins and hoppers to prevent flow stoppages due to arching and ratholing, including the slope and smoothness of hopper walls to provide mass flow. Parameters for structural design of such equipment may also be derived from this data. Another application is the measurement of the flowability of bulk solids, for example, for comparison of different products or optimization. 1.4 All observed and calculated values shall conform to the guidelines for significant digits and rounding established in Practice D6026. 1.4.1 The procedures used to specify how data are collected/recorded or calculated in this standard are regarded as the industry standard. In addition, they are representative of the significant digits that generally should be retained. The procedures used do not consider material variation, purpose for obtaining the data, special purpose studies, or any considerations for the user’s objectives: and it is common practice to increase or reduce significant digits of reported data to be commensurate with these considerations. It is beyond the scope of this standard to consider significant digits used in analysis methods for engineering design. 1.5 Units—The values stated in SI units are to be regarded as standard. No other units of measure are included in this standard. 1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the respons...
SIGNIFICANCE AND USE 5.1 Reliable, controlled flow of bulk solids from bins and hoppers is essential in almost every industrial facility. Unfortunately, flow stoppages due to arching and ratholing are common. Additional problems include uncontrolled flow (flooding) of powders, segregation of particle mixtures, usable capacity which is significantly less than design capacity, caking and spoilage of bulk solids in stagnant zones, and structural failures. 5.2 By measuring the flow properties of bulk solids, and designing bins and hoppers based on these flow properties, most flow problems can be prevented or eliminated (1).3 5.3 For bulk solids with a significant percentage of particles (typically, one third or more) finer than about 6 mm (1/4 in.), the unconfined yield strength is governed by the fines (−6 mm fraction). For such bulk solids, strength and wall friction tests may be performed on the fine fraction only. Note 1: The quality of the result produced by this standard is dependent on the competence of personnel performing it, and the suitability of the equipment and facilities used. Agencies that meet the criteria of Practice D3740 are generally considered capable of competent and objective testing/sampling/inspection/etc. Users of this standard are cautioned that compliance with Practice D3740 does not in itself ensure reliable results. Reliable results depend on many factors; Practice D3740 provides a means of evaluating some of those factors. Practice D3740 was developed for agencies engaged in the testing or inspection (or both) of soil and rock. As such it is not totally applicable to agencies performing this standard. However, users of this standard should recognize that the framework of Practice D3740 is appropriate for evaluating the quality of an agency performing this standard. Currently there is no known qualifying national authority that inspects agencies that perform this standard. SCOPE 1.1 This test method covers the apparatus and procedures for measuring the unconfined yield strength of bulk solids during both continuous flow and after storage at rest. In addition, measurements of internal friction, bulk density, and wall friction on various wall surfaces are included. 1.2 This test method covers operation of the manually-controlled Schulze Ring Shear Tester. An automated version of this tester is also available. Its method of testing bulk solids is similar in principle to that described in this test method. 1.3 The most common use of this information is in the design of storage bins and hoppers to prevent flow stoppages due to arching and ratholing, including the slope and smoothness of hopper walls to provide mass flow. Parameters for structural design of such equipment may also be derived from this data. Another application is the measurement of the flowability of bulk solids, for example, for comparison of different products or optimization. 1.4 All observed and calculated values shall conform to the guidelines for significant digits and rounding established in Practice D6026. 1.4.1 The procedures used to specify how data are collected/recorded or calculated in this standard are regarded as the industry standard. In addition, they are representative of the significant digits that generally should be retained. The procedures used do not consider material variation, purpose for obtaining the data, special purpose studies, or any considerations for the user’s objectives: and it is common practice to increase or reduce significant digits of reported data to be commensurate with these considerations. It is beyond the scope of this standard to consider significant digits used in analysis methods for engineering design. 1.5 Units—The values stated in SI units are to be regarded as standard. No other units of measure are included in this standard. 1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the respons...
ASTM D6773-22 is classified under the following ICS (International Classification for Standards) categories: 59.080.01 - Textiles in general. The ICS classification helps identify the subject area and facilitates finding related standards.
ASTM D6773-22 has the following relationships with other standards: It is inter standard links to ASTM D4753-24, ASTM D3740-23, ASTM D3740-19, ASTM D2216-19, ASTM D4753-15, ASTM D6128-14, ASTM D653-14, ASTM E177-14, ASTM E177-13, ASTM E691-13, ASTM D3740-12a, ASTM D3740-12, ASTM E691-11, ASTM D653-11, ASTM D3740-11. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.
ASTM D6773-22 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.
Standards Content (Sample)
This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the
Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
Designation: D6773 − 22
Standard Test Method for
Bulk Solids Using Schulze Ring Shear Tester
This standard is issued under the fixed designation D6773; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision.Anumber in parentheses indicates the year of last reapproval.A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope* 1.6 This standard does not purport to address all of the
safety concerns, if any, associated with its use. It is the
1.1 This test method covers the apparatus and procedures
responsibility of the user of this standard to establish appro-
for measuring the unconfined yield strength of bulk solids
priate safety, health, and environmental practices and deter-
during both continuous flow and after storage at rest. In
mine the applicability of regulatory limitations prior to use.
addition, measurements of internal friction, bulk density, and
1.7 This international standard was developed in accor-
wall friction on various wall surfaces are included.
dance with internationally recognized principles on standard-
1.2 This test method covers operation of the manually-
ization established in the Decision on Principles for the
controlledSchulzeRingShearTester.Anautomatedversionof
Development of International Standards, Guides and Recom-
this tester is also available. Its method of testing bulk solids is
mendations issued by the World Trade Organization Technical
similar in principle to that described in this test method.
Barriers to Trade (TBT) Committee.
1.3 The most common use of this information is in the
2. Referenced Documents
design of storage bins and hoppers to prevent flow stoppages
2.1 ASTM Standards:
due to arching and ratholing, including the slope and smooth-
D653Terminology Relating to Soil, Rock, and Contained
ness of hopper walls to provide mass flow. Parameters for
Fluids
structural design of such equipment may also be derived from
D2216Test Methods for Laboratory Determination ofWater
this data. Another application is the measurement of the
(Moisture) Content of Soil and Rock by Mass
flowability of bulk solids, for example, for comparison of
D3740Practice for Minimum Requirements for Agencies
different products or optimization.
Engaged in Testing and/or Inspection of Soil and Rock as
1.4 All observed and calculated values shall conform to the
Used in Engineering Design and Construction
guidelines for significant digits and rounding established in
D4753Guide for Evaluating, Selecting, and Specifying Bal-
Practice D6026.
ances and Standard Masses for Use in Soil, Rock, and
1.4.1 Theproceduresusedtospecifyhowdataarecollected/
Construction Materials Testing
recorded or calculated in this standard are regarded as the
D6026Practice for Using Significant Digits and Data Re-
industry standard. In addition, they are representative of the
cords in Geotechnical Data
significant digits that generally should be retained. The proce-
D6128Test Method for Shear Testing of Bulk Solids Using
dures used do not consider material variation, purpose for
the Jenike Shear Tester
obtaining the data, special purpose studies, or any consider-
E177Practice for Use of the Terms Precision and Bias in
ations for the user’s objectives: and it is common practice to
ASTM Test Methods
increase or reduce significant digits of reported data to be
E691Practice for Conducting an Interlaboratory Study to
commensuratewiththeseconsiderations.Itisbeyondthescope
Determine the Precision of a Test Method
of this standard to consider significant digits used in analysis
methods for engineering design. 3. Terminology
3.1 Definitions—For definitions of common technical terms
1.5 Units—The values stated in SI units are to be regarded
in this standard, refer to Terminology D653.
as standard. No other units of measure are included in this
standard.
4. Summary of Test Method
4.1 A representative specimen of bulk solid is placed in a
shear cell of specific dimensions.
ThistestmethodisunderthejurisdictionofASTMCommitteeD18onSoiland
Rock and is the direct responsibility of Subcommittee D18.24 on Characterization
and Handling of Powders and Bulk Solids. For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Current edition approved Oct. 15, 2022. Published January 2023. Originally contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
approved in 2002. Last previous edition approved in 2016 as D6773–16. DOI: Standards volume information, refer to the standard’s Document Summary page on
10.1520/D6773-22. the ASTM website.
*A Summary of Changes section appears at the end of this standard
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
D6773 − 22
4.2 When running an instantaneous or time shear test, a 6.2 Thedrivingaxle5(withdetachableplasticcap6)causes
normal load is applied to the cover, and the specimen is theshearcell4torotate.Thedriverpinsattheundersideofthe
presheared until a steady state shear value has been reached. shear cell must set in the toothed wheel at the driving axle 5 to
The shear stress is then immediately reduced to zero. enable a close connection between shear cell and driving axle.
The driving axle is driven by an electric motor and can rotate
4.3 An instantaneous test is run by shearing the specimen
to the right or to the left. In order to shear the bulk solid
under a reduced normal load until the shear force goes through
specimen, the driving axle 5 along with the shear cell 4 rotate
a maximum value and then begins to decrease.
clockwise (as seen from the top). The electric motor is
4.4 A time shear test is run similarly to an instantaneous
controlled from the front panel 35 at the front side of casing 2
sheartest,exceptthatthespecimenisplacedinaconsolidation
(Fig. 3). The motor and drive system cause the shear cell to
bench for the specified time between the preshear and shear
rotate at a speed adjustable between 0.007 and 0.13 rad/min.
steps.
6.3 The shear cell lid 7 as well as the bottom of the shear
4.5 A wall friction test is run by sliding the specimen over
cell 4 has bent bars made of stainless steel (Fig. 4) to prevent
a coupon of wall material and measuring the frictional resis-
slipping of the bulk solid at the lid or the bottom of the shear
tance as a function of normal, compressive load.
cell.
NOTE 2—The standard cell has 20 bars, each of which is 4 mm tall
4.6 A wall friction time test involves sliding the specimen
(h =4 mm, Fig. 7).
Mit
overthecouponofwallmaterial,stoppingandleavingtheload
6.4 The crossbeam 8 sits on the lid 7 and is fixed with two
on the specimen for a predetermined period, and then sliding it
knurledscrews9.Thecrossbeam8hasseveralfunctions:Inthe
again to see if the shearing force has changed.
center of the crossbeam 8 is a fixed axis 10 with a hook to
5. Significance and Use append the hanger 11 (in Figs. 3 and 4 only the handle of the
hangerstandingoutfromthedrivingaxlecanbeseen).Rollers
5.1 Reliable, controlled flow of bulk solids from bins and
attheendsofthecrossbeamandtheremovableguiderollers12
hoppers is essential in almost every industrial facility.
prevent movement of lid 7 from the centered position.
Unfortunately, flow stoppages due to arching and ratholing are
common. Additional problems include uncontrolled flow 6.5 A hook 14 at the upper end of the axis 10 of the
(flooding) of powders, segregation of particle mixtures, usable crossbeam 8 is fastened to the balance arm 15. This arm along
capacitywhichissignificantlylessthandesigncapacity,caking with counterbalance 29 (Fig. 6) serves to compensate for the
and spoilage of bulk solids in stagnant zones, and structural masses of lid 7, crossbeam 8, hanger 11, and tie rods 13. The
failures. counterbalance 29 is found at the rear side of the balance arm
15.
5.2 By measuring the flow properties of bulk solids, and
6.6 A digital displacement indicator 31 (Fig. 8) is used for
designing bins and hoppers based on these flow properties,
most flow problems can be prevented or eliminated (1). the measurement of the height of the bulk solid specimen.
6.7 Bolts at the ends of the crossbeam 8 are used to append
5.3 For bulk solids with a significant percentage of particles
the tie rods 13. Therefore, a circular hole is at one end of each
(typically,onethirdormore)finerthanabout6mm( ⁄4in.),the
tierod13.Theoppositeendisprovidedwithanelongatedhole
unconfined yield strength is governed by the fines (−6 mm
for suspending in the adjustable seating 16 attached to the load
fraction). For such bulk solids, strength and wall friction tests
beam 17.
may be performed on the fine fraction only.
NOTE 1—The quality of the result produced by this standard is
6.8 The rotation of the lid 7 is prevented by the tie rods 13
dependent on the competence of personnel performing it, and the
which transfer the tensile force to the load beams 17.
suitability of the equipment and facilities used. Agencies that meet the
criteria of Practice D3740 are generally considered capable of competent
6.9 The bottom part of the hanger 11, which hangs on the
and objective testing/sampling/inspection/etc. Users of this standard are
crossbeam 8 and serves for exerting a normal load N on the
cautioned that compliance with Practice D3740 does not in itself ensure
bulksolid,islocatedwithinthebase1(Fig.1).Thehangerhas
reliable results. Reliable results depend on many factors; Practice D3740
acircularplate19atitslowerendforholdingtheappliedmass
providesameansofevaluatingsomeofthosefactors.PracticeD3740was
developed for agencies engaged in the testing or inspection (or both) of
pieces.
soil and rock. As such it is not totally applicable to agencies performing
6.10 For control of the motor drive a front panel 35 (Fig. 3)
this standard. However, users of this standard should recognize that the
is at the front side of the casing 2.
framework of Practice D3740 is appropriate for evaluating the quality of
an agency performing this standard. Currently there is no known quali-
6.11 The load beams 17 are connected parallel. Each load
fying national authority that inspects agencies that perform this standard.
beam must be capable of measuring a force up to 200 N with
a precision of 0.02% of full scale. Thus, the total measuring
6. Apparatus
range,whichistwicethemeasuringrangeofoneloadbeam,is
6.1 The Schulze Ring Shear Tester (Figs. 1-6) is composed
400 N. The signal from the force transducer is conditioned by
of a base 1 and a casing 2. The casing 2 contains the driving
an amplifier and shown on a recorder. (Warning—To avoid
and measuring units and carries the working table38.
overloading of the load beams, the indicated maximum normal
load must not be exceeded.)
6.12 For the Schulze Ring ShearTester RST-01.01 different
Theboldfacenumbersinparenthesesrefertothelistofreferencesattheendof
this standard. shear cells are available. The dimensions of the Standard cell
D6773 − 22
FIG. 1 Ring Shear Tester (overall view)
and a smaller cell can be taken from Table 2 and Fig. 7. For consolidationasshownintheleftpartofFig.9.Thelowerend
special purposes (for example, reduced internal volume) other of the loading rod Z4 is equipped with a central tip.
dimensions are also available. The following table provides a
6.13.3 The transparent cylindrical plastic cap Z3, when
rough indication of the applicability of various cell sizes based
pressedonplateZ2,protectsthespecimensfromthesurround-
on maximum particle size of the bulk solid (monodisperse =
ing atmosphere (for example, to reduce changes of the mois-
narrow particle size distribution, for example, plastics pellets,
ture(water)ofthebulksolidspecimens).ThiscapZ3isjoined
grain). Values in parentheses are valid if particles are not
to the loading rod Z4 through a rubber bellows Z8.
brittle.
6.13.4 At the upper end of the loading rod Z4 a disk Z5 is
maximum particle size, x fastened for supporting applied mass pieces by which the
max
Shear cell type monodisperse broad distribution, 0 .
vertical load for time consolidation is applied.
x
max
6.13.5 The fixing screw Z6 serves for the fixation of the
M 5 mm 10 mm
S 2.5 mm 5 mm
loading rod Z4 in the upper position (Fig. 9, on the right).
MV10 1 (1.5) mm 2 (3) mm
SV10 0.75 (1) mm 1.5 (2) mm 6.14 The wall friction shear cells allow the measurement of
wall yield loci from which wall friction angles can be calcu-
6.13 The time consolidation bench serves for the storage of
lated.
shear cells with bulk solid specimens under load.
6.14.1 Thebottomring48ofthewallfrictionshearcell(see
6.13.1 Thetimeconsolidationbench(Fig.9)iscomposedof
Fig. 10) contains the wall material coupon to be tested.
a frame Z1, on which are fastened three supporting plates Z2.
One small shear cell (type S, volume approx. 200 cm ) can be 6.14.2 To prevent any relative circumferential displacement
placed on each plate. The shape of the plate Z2 centers the between the bottom ring 48 and the wall material coupon, four
shear cell. drivingpins50areinstalledattheouterwallofthebottomring
6.13.2 Through the central depression of the time consoli- 48. The annular wall material coupon has to be provided with
dation crossbeam 26 the normal load is exerted during time notches for these driving pins so that bottom ring and wall
D6773 − 22
FIG. 2 Shear Cell (in principle)
ance 29 on the balance arm.
material coupon are interlocked. The required dimensions of
the wall material coupon are shown in Fig. 11.
7.2.1.1 After unscrewing the knurled screw, which is the
6.14.3 Thelid49(Fig.12)hasbentbarsfromstainlesssteel
major part of the movable mass 30, shift the movable mass 30
to prevent slipping of the bulk solid at the lid of the shear cell.
along the balance arm, if necessary, for more precise adjust-
Additionally, the lid of a wall friction shear cell is provided
ment of the force caused by the counterbalance mass.
withdownwardsprotrudingedgesattheinnerandouterradius.
NOTE 5—When the counterbalance mass is well adjusted, the lid,
6.14.4 The dimensions of the wall friction shear cell are
crossbeam, tie rods, and hanger do not press on the bulk solid; that is, the
shown in Table 1 and Fig. 13.
vertical stress at the surface of the bulk solid is equal to zero.
6.15 A spatula having a rigid, sharp, straight blade at least
7.2.2 Adjust the seatings 16 to level the lid 7.
50%longerthanthewidthoftheannulusoftheshearcell,and
7.2.3 Adjust the four adjustable stands 3 on base 1 (Fig. 5)
at least 20 mm wide, is needed.
to level the Ring Shear Tester.
7.2.4 Unscrew the fixing screw sufficiently so as to be able
6.16 Alaboratory balance having a maximum capacity of at
tomovetheloadingrodupwardsordownwards.Intheloading
least 5 kg with a precision of 0.01% or better is required.
position (Fig. 9, on the left) the fixing screw must remain
7. Specimen Preparation
unscrewed.
7.2.5 Beforestartingwithtimeconsolidationmeasurements,
7.1 The laboratory used for powder testing must be free of
make sure that the time consolidation bench is level. Use the
vibrations caused by traffic or heavy machinery. Ideally, the
four adjustable feet Z7 (Fig. 9), if necessary
room is temperature and humidity controlled, or, if this is not
possible, maintain it at nearly constant ambient conditions.
7.3 Filling the Cell (Fig. 14):
Direct sunlight, especially on the time consolidation bench, is
7.3.1 Fill the shear cell 4 uniformly in small horizontal
to be avoided.
layers by a spoon or spatula without applying force to the
NOTE 3—Temperature- and humidity-sensitive materials may need to
surface of the material until the cell is slightly overfilled with
be tested at different temperatures and moisture (water) contents, because
material. Fill the cell in such a way as to make sure that there
thisoftenhappensinindustrialenvironments.Thelaboratoryenvironment
are no voids within it.
must approximate production for meaningful testing.
7.3.2 Remove excess material in small quantities by scrap-
7.2 Setup:
ingoffwithablade1untilflushwiththetopoftheannulus.At
7.2.1 Shiftthemovablecounterbalance29alongthebalance
first, scrape the blade counterclockwise across the ring one or
arm to adjust the force caused by the counterbalance mass.
two times in a zigzag motion. Then, scrape the blade around
NOTE 4—The fixation screw 18 (knurled screw) fixes the counterbal- the annulus counterclockwise, as shown in Fig. 14a, whereby
D6773 − 22
FIG. 3 Ring Shear Tester (upper part)
the blade is inclined by an angle α=15 to 30° to the radial 7.4.1 When measuring the friction between the particulate
direction.Holdthebladeverticallyortiltedbyafewdegreesto
solid and a coupon of silo wall material in a wall friction test,
the vertical (angle β=0° to 10°) as shown in Fig. 14b. Do not
add spacers and a coupon of wall material to the shear cell
exert a downward force on the material with the blade.
bottom ring. Shear the specimen contained in bottom ring over
7.3.3 If coarse particles are present, scraping may tear them
the wall material coupon under different wall normal stresses
fromthesurfaceandalterthestructure.Insuchcasesitisbetter
σ and measure the resulting wall shear stresses τ .
w w
to attempt to fill the cell so that the material surface is flush
7.4.2 Selection of Wall Friction Normal Stress Levels:
with the annulus after filling.
7.4.2.1 Select six wall friction normal stress levels σ to
w1
7.3.4 If necessary, clean the outside of the shear cell. Then
σ whereσ isthesmallestnormalstress.Thelargestnormal
w6 w1
determine the mass of the shear cell with contents. Note the
stress σ must be approximately equal to the major principal
total mass m . w6
tot
stress σ of the second preshear normal stress, σ . The
1,2 p,2
7.4 Wall Friction:
D6773 − 22
FIG. 4 Upper Part of the Ring Shear Tester, Shear Cell Removed
smallest normal stress σ will normally include the hanger inapositionturnedafewdegreescounterclockwisetoitsshear
w1
without applied masses.
position(shearposition:longitudinalaxisofthecrossbeam8is
7.4.3 Wall Coupon and Material Specimen Preparation: perpendiculartothefrontedgeofthecasing2).Directtheopen
7.4.3.1 Wash the wall material coupon and dry thoroughly
sideofthehook25inthecenterofthecrossbeam8totheright.
before the test. Do not touch the surface after washing with
Locate handle 24 of the hanger 11 on the right side of
bare hands.
crossbeam 8 (in analogy to Fig. 16).
7.4.3.2 Insert the spacer rings 51 and the wall material
7.4.3.10 Put the tie rods 13 on both the bolts at the ends of
coupon in the bottom ring 48 (Fig. 10). The distance between
crossbeam 8 (circular holes of tie rods 13) and the seatings 16
upper edge of the bottom ring 48 and upper surface of the wall
at the load beams 17 (long hole of the tie rod 13).
material coupon must total about 8 to 10 mm.
(1)Ensure that the tie rods 13 have some clearance in the
seatings 16; that is, the tie rods must not be stressed at that
NOTE 6—The thickness of each spacer ring is 2 mm.
stage. Important: If it is not possible to connect the tie rods as
7.4.3.3 Determine the mass of the bottom ring 48 with
described above, do not move the lid manually! This would
content (note total mass m ).
wall
influence the test result. Only use the motor drive to turn the
7.4.3.4 Connect crossbeam 8 and lid 49 using the knurled
shear cell with the lid in a position where it is possible to
screws 9.
connect the tie rods to the load beams.
7.4.3.5 Fill the bottom ring 48 with the bulk solid to be
tested. See 7.3. 7.4.3.11 Append hanger 11 at hook 25 on the lower side of
7.4.3.6 If necessary, clean the bottom ring 48 from outside. crossbeam 8.
Then determine the mass of the bottom ring 48 with content
7.4.3.12 Carefully put appropriate applied mass pieces on
(note total mass m ).
W,tot the circular plate 19 of the hanger.
7.4.3.7 Ascertain that the power supply is switched on.
NOTE 7—The total mass of the applied mass pieces on the hanger must
7.4.3.8 Put the filled bottom ring 48 on driving axle 5 (in
be less than or equal to the maximum normal load to be used for the wall
analogy to Fig. 15). The driver pins at the underside of the
friction measurement.
shear cell must engage in the toothed wheel at the driving axle
5. 7.4.3.13 Remove hook 14, which is connected to the bal-
ance arm, from its off-position mounting 32 and append it to
7.4.3.9 Carefully place the lid 49 concentrically on the
bottom ring 48 on the bulk solid specimen. The lid 49 must be the central axis 10 (in analogy to Fig. 16).To do this, the front
D6773 − 22
FIG. 5 View on the Reverse Side of the Ring Shear Tester
endofthebalancearmmustbepulleddownattheblackhandle 8.1.1.2 Put the filled shear cell 4 on the driving axle 5 (Fig.
46 provided for this (the handle is not shown in all figures; see 15). Make sure that the driver pins on the underside of the
Fig. 6). shear cell engage the toothed wheel of the driving axle 5.
(1)If the lid sinks down very much, the lower edge of the
8.1.1.3 Select the first preshear normal stress σ on the
p,1
lid may touch directly the upper surface of the wall material
basisofthebulkdensityofthetestmaterial,inaccordancewith
coupon, thus causing incorrect measurement results. If this
the following table:
happens, remove the shear cell from the tester, remove the lid
ρ (kg/m ) σ (kPa)
b p,1
from the bottom ring, and add additional bulk solid into the < 300 approximately 1.5
300 to 800 approximately 2.0
bottom ring following procedure starting at 7.4.3.5.
800 to 1600 approximately 2.5
7.4.3.14 Check the adjustment of the rotational velocity
1600 to 2400 approximately 3.0
(front panel 35). The circumferential velocity at the mean
> 2400 approximately 4.0
specimen diameter must be 1 to 2 mm/min.
8.1.1.4 Follow 8.1.1.5 – 8.1.1.10 only if the normal load at
preshear is greater than 15 N. Otherwise go to 8.1.1.12.
8. Procedure
NOTE8—Thelatterprocedureisnecessarysoastonotover-consolidate
8.1 Procedure for Instantaneous Shear Test
a bulk solid specimen at small normal loads.
8.1.1 Preshear:
8.1.1.1 Ascertain that the power supply has been turned on 8.1.1.5 Connect crossbeam 8 and lid 7 using the knurled
at least 15 min to ensure that the unit is properly warmed up. screws 9. Fasten screws only very slightly. Position the lid
D6773 − 22
FIG. 6 Counterbalance System
TABLE 1 Wall Friction Shear Cell Dimensions
8.1.1.6 Put tie rods 13 on both the bolts at the ends of
Standard Wall Friction crossbeam 8 (circular holes of tie rods 13) and seatings 16 at
Shear Cell,
load beams 17 (long hole of the tie rod 13).
Type WM
2 8.1.1.7 Ensure that the tie rods 13 have some clearance in
Cross-section (lid) A 226 cm
D
r 51 mm the seatings 16; that is, the tie rods must not be stressed at this
iD
r 99 mm
aD
stage. If it is not possible to connect the tie rods as described
r 42.5 mm
iSZ
above,donotmovethelidmanuallysincethiswouldinfluence
r 107.5 mm
aSZ
h 24 mm
the test result. Only use the motor drive to turn the shear cell
SZ
h 4mm
Mit
with the lid in a position where it is possible to connect the tie
Material Aluminum
rods to the load beams.
8.1.1.8 Append hanger 11 at hook 25 at the lower side of
crossbeam 8.
8.1.1.9 Carefully put an applied mass piece on the circular
concentrically on the shear cell and turned a few degrees
plate 19 of hanger 11 (mass needed for preshear or smaller
counterclockwise to its shear position (shear position: longitu-
mass).
dinal axis of the crossbeam is perpendicular to the front edge
of the casing 2). Direct the open side of hook 25 in the center 8.1.1.10 Remove hook 14, which is connected to the bal-
of crossbeam 8 to the right. Locate handle 24 of hanger 11 on ance arm, from its off-position mounting 32 and append it to
the right side of crossbeam 8 (Fig. 16). the central axis 10 (this already has been done in Fig. 16). To
D6773 − 22
FIG. 7 Main Dimensions of Shear Cell
do this, pull down the front end of the balance arm at the black 8.1.1.14 Holdthelidinitsliftedpositionwithonehandand
handle 46 provided for this (the handle is not shown in all append hanger 11 at hook 25 at the lower side of crossbeam 8.
figures; see Fig. 6).
8.1.1.15 Carefully place the lid concentrically on the shear
8.1.1.11 Follow 8.1.1.12 – 8.1.1.16 if the normal load at
cell on the bulk solid specimen. The lid must be in a position
preshear is less than 15 N. (These steps can also be used
turned a few degrees counterclockwise to its shear position
alternatively to 8.1.1.5 – 8.1.1.10.)
(shear position: longitudinal axis of the crossbeam is perpen-
8.1.1.12 Connect crossbeam 8 and lid 7 using the knurled
dicular to the front edge of the casing 2). Direct the open side
screws 9. Fasten screws only very slightly. Remove hook 14,
of hook 25 in the center of crossbeam 8 to the right. Locate
which is connected to the balance arm, from its off-position at
handle 24 of hanger 11 on the right side of crossbeam 8 (Fig.
mounting32andappendittothecentralaxis10.Thelidisthen
16).
in a “lifted position.”
8.1.1.16 Put tie rods 13 on both the bolts at the ends of
8.1.1.13 Put at least one applied mass piece on the circular
crossbeam 8 (circular holes of tie rods 13) and the seatings 16
plate 19 of the hanger 11.
at load beams 17 (long hole of the tie rod 13). Ensure that the
tie rods 13 have some clearance in the seatings 16; that is, the
NOTE 9—The mass on the hanger can be less than or equal to that
needed for preshear, but must not exceed 1 kg. tie rods must not be stressed at this stage. If it is not possible
D6773 − 22
FIG. 8 Determination of the Height of the Specimen
TABLE 2 Shear Cell Dimensions
NOTE 10—At the beginning of preshear, some powder may escape,
which is one reason why the lid may sink. Provided that 8.1.1.17 is
Standard Cell, Type
Small Cell, Type S
followed, loss of powder can be neglected.
M
3 A 3 A
Internal volume V ca. 900 cm ca. 200 cm
SZ
8.1.1.18 Check the adjustment of the rotational velocity
2 2
Cross-section (lid) A 226 cm 79 cm
D
(front panel 35). The circumferential velocity at the mean
r 51 mm 31 mm
iD
r 99 mm 59 mm diameter must be 1 to 2 mm/min.
aD
r 50 mm 30 mm
iSZ
8.1.1.19 Start the motor (front panel 35).
r 100 mm 60 mm
aSZ
h 40 mm 24 mm
SZ
NOTE 11—After some time both tie rods 13 are transferring tensile
h 4mm 4 mm
Mit
forces. The total force F (“shear force”) is then measured.
Material Aluminum or Aluminum or
Stainless Steel Stainless Steel
8.1.1.20 As soon as the shear force F stops increasing
A
Exact volume to be determined for each cell.
(steady-state flow is reached), Fig. 17, reverse the direction of
rotation of the shear cell. After both load beams are relieved
(shearforce F=0), continuerotatingtheshearcelluntilthetie
rods 13 have about 1 mm clearance in the seatings 16. Then
to connect the tie rods in this manner, use the motor drive to
stop the motor.
turn the shear cell with the lid to an appropriate position.
8.1.1.17 If not already done (at 8.1.1.9 or 8.1.1.13, 8.1.1.21 Record the force F measured at steady-state flow.
respectively), put additional applied mass pieces on the hanger (1)If the shear force does not reach a constant value,
11 for adjusting the normal force required for preshear. If the steady-state flow can be assumed if, after 30 mm of shear
lid sinks down more than around 10 mm, refill the shear cell displacement (measured at the mean radius of the shear cell
(remove the shear cell from the tester and go back to 7.3). annulus), this force does not increase more than 0.05% per
D6773 − 22
FIG. 9 Time Consolidation Bench
then begins to decrease (Fig. 17). This part of the test is called shear.
mm of shear displacement. If this condition has not been
NOTE 13—The value τ is the shear stress at failure (peak shear point)
achieved after 30 mm of displacement, continue preshear until
s
for the selected shear normal stress σ at the selected preshear normal
s
it is met. If the technician decides to terminate preshear before
stress σ . Metal-to-powder friction, which may occur at the side walls of
p
this condition is met, it must be noted before continuing with
the shear cell and at the tips of the bars under the lid, is assumed to be
the test.
negligiblebecausetheareaswheremetal-to-powderfrictionmayoccurare
(2)The shear force should not decrease during preshear. If
very small compared to the cross-section of the shear plane, and therefore
ignored.
it starts to do so after a period of constant value, stop preshear
immediately and begin the steps starting with 8.1.2.
8.1.2.2 Switch on the digital displacement indicator 31.
(3)Constancy of the values of the steady state shear stress
After the display of the indicator shows “0.00 mm,” set the
τ obtainedafterpreshearisanindicationofthereproducibility
p
indicator on the crossbeam 8. Position the probe tip through a
of consolidation. With correctly consolidated specimens indi-
hole in the crossbeam 8 in such a way that it presses on top of
vidualvaluesofthesteadystateshearstressshouldnotdeviate
the inner side wall of the shear cell 4 and the spacer tube 36 is
by more than 65% from the average steady state shear stress
in contact with the upper surface of the crossbeam 8 (Fig. 8).
for the given preshear normal stress. With some particulate
Note the displacement indicated on the display.
solids (particularly coarser particles), however, this tolerance
8.1.2.3 Repeat the measurement at the opposite side of the
cannot be achieved. If this happens it must be noted by the
crossbeam.
technician performing the test.
8.1.2.4 Remove the indicator 31.
8.1.2 Shear:
8.1.2.5 Calculate the mean value of both measured
8.1.2.1 Selectashearnormalstresslevelσ withintherange
s
displacements, which is the mean decrease in height ∆h of the
of 25 to 80% of the preshear normal stress level σ , and
p
bulk solid specimen. Note this mean value.
replace the mass m by a smaller mass m . Switch on the
Wp Ws
motor again in the forward direction.
8.1.2.6 Drive back the shear cell 4 until tie rods 13 are
relieved. Then switch off the motor.
NOTE12—Afterthetierods13aretensedagain,theshearforcerapidly
increases,goesthroughamaximumrepresentingtheyieldshearforce,and 8.1.2.7 Remove tie rods 13.
D6773 − 22
FIG. 10 Wall Friction Shear Cell (bottom ring)
wouldjumpagainandagainfrom8.1.2.1backto8.1.1.19untilalldesired
8.1.2.8 Unhook hook 14 from the central axis 10 thus
measuring points are determined. Only then would 8.1.2.2 and the
deactivating the counterbalance system.
following steps be performed.
8.1.2.9 Remove applied mass pieces from the hanger 11.
Procedure B is generally the preferred procedure, since it is less time
8.1.2.10 Unhook hanger 11 from the hook 25 at the lower
consuming than Procedure A. Unfortunately, some bulk solids are sensi-
side of the crossbeam 8.
tivetosheardeformationand,asaresult,theirshearstressvaluesdecrease
8.1.2.11 Take off the shear cell 4 along with the lid 7.
with large shear deformation. Sometimes a result of this can be that
8.1.2.12 Empty the shear cell; if necessary clean the shear Procedure B yields too small values of the unconfined yield strength (3).
TodetermineifProcedureBisappropriate,examineanewbulksolidfirst
cell, the lid and the driving axle.
with this procedure. Repeat the first measuring point at the end. If the
8.1.3 Additional Tests:
prorated shear stress is noticeably smaller than at the first measurement
8.1.3.1 Repeat 7, 8.1.1, and 8.1.2.
(say, a difference greater than 2.5%), use Procedure A for the product
8.1.3.2 Select 3 to 5 shear normal stress levels σ within the
s
under consideration, or at least limit the number of shear points measured
range of 25 to 80% of the preshear normal stress level σ , and
using Procedure B.
p
repeat 7, 8.1.1, and 8.1.2. If Procedure B is applicable, shear the specimen only until the shear
force becomes constant. Frequently, if the shear displacement is large at
8.1.3.3 Select higher preshear normal stress levels so that:
the first preshearing of a bulk solid specimen, the shear force passes over
σ =2σ
p,2 p,1
a product dependent, weak maximum (3). Afterwards, a constant shear
σ =4σ
p,3 p,1
force somewhat smaller than the maximum shear force is reached. Do not
σ =8σ
p,4 p,1
waituntilthislowerlevelisreached.Thepreshearingisfinishedwhenthe
NOTE 14—Some adjustment in preshear normal stress levels may be
maximum is reached; that is, the shear force no longer increases, and the
necessary in order to cover the range of major principal stresses σ
shear force does not yet start to decrease again. One can ascertain this
necessary to accurately calculate critical arching and/or ratholing dimen-
condition easily, if the shearing velocity is not too high.
sions.
In principle, all measurement results, as those of other shear testers,
havetobeconsideredcriticallyandappliedwiththenecessarycautionand
8.1.3.4 Repeat 7, 8.1.1, 8.1.2, and 8.1.3.2 for each selected
care.
preshear normal stress level.
8.2 Shear Testing Procedure for Time Consolidation
NOTE 15—Following the procedure given in 7, 8.1.1, and 8.1.2
(Procedure A) requires a new filling of the shear cell for each measure-
8.2.1 When a particulate solid is exposed to a normal or
ment; that is, each point on a yield locus. In the literature a second
compressive stress for some time it may gain strength. This
measuring procedure (Procedure B) is frequently recommended (for
gaininstrengthcanbemeasuredusingtheSchulzeRingShear
example, in (2)), where several points of a yield locus are determined
using the identical bulk solid specimen several times. In this case, one Tester, and the effect is called time consolidation.
D6773 − 22
FIG. 11 Dimensions of Wall Material Coupon
NOTE 17—For a selected preshear normal stress, specimen preparation
8.2.2 Timeconsolidationiscarriedoutusingaconsolidating
and preshear are the same as for the instantaneous test.
bench which consists of several shear cells which can be
independently loaded.The time that the specimens sit at rest is
8.2.4 Time Consolidation:
specified according to the application.
8.2.4.1 Perform each test for time consolidation in the
8.2.2.1 As an alternative to using a consolidation bench,
following way. Using the shear tester, prepare and preshear
consider the following: a critically consolidated specimen is
specimens with applied mass m in the normal manner and
Wp
preparedbypreshearingwithappliedmass m .Afterattaining
Wp
then reverse the rotation of the shear cell after preshear.
steady state flow, the rotation of the shear cell is stopped but
8.2.4.2 Remove the already relieved tie rods 13.
the direction is not reversed. The shear zone formed thus
8.2.4.3 Carefully unhook hook 14 of the counterbalance
remains under the normal and shear stresses corresponding to
system from the central axis 10 of the crossbeam 8. For this
steady state flow and is kept in this state for a defined time t.
stepaswellasthefollowingthrough8.2.4.11,becarefulnotto
If the shear cell rotation is then reversed, the shear force will
bump or jar the lid or cell; otherwise the results will be
drop to zero and the actual shear test may be performed in the
incorrect.
usual way.
8.2.4.4 Removetheappliedmasspiecesfromthehanger11.
NOTE 16—If the effect of time consolidation in the Schulze Ring Shear
8.2.4.5 Unhook hanger 11 from the hook 25 on the lower
Tester were measured as described above, one test would monopolize the
side of the crossbeam 8.
shear tester for a very long time. Creep of the specimen could also cause
a decrease in the applied shear force during the resting phase. 8.2.4.6 Completely unscrew the knurled screws 9, which
join the crossbeam 8 with the lid 7.
8.2.3 Specimen Preparation and Preshear Time Effect:
8.2.4.7 Carefully remove crossbeam 8 from lid 7.
8.2.3.1 After completion of instantaneous testing and
evaluation, perform time tests at the same preshear normal 8.2.4.8 Carefully put time consolidation crossbeam 26 cen-
stress levels. trally on the lid 7.
D6773 − 22
FIG. 12 Wall Friction Shear Cell Placed on the Ring Shear Tester
FIG. 13 Main Dimensions of Wall Friction Shear Cell
8.2.4.9 Fix plastic cap Z3 of time consolidation bench in its cell on a free supporting plate Z2 of the prepared time
upper position with the help of the fixing screw Z6 (Fig. 9, consolidation bench (Fig. 9, medium position).
right position). 8.2.4.11 Hold plastic cap Z3 with one hand, and loosen the
8.2.4.10 Remove the shear cell 4 along with the lid 7 from fixing screw Z6 with the other hand. Then let down the plastic
driving axle 5 carefully and without vibrations. Put the shear cap slowly, thereby leading loading rod Z4 with one hand so
D6773 − 22
FIG. 14 Scraping Off Excess Powder
FIG. 15 Ring Shear Tester with Shear Cell on Driving Axle 5
that it runs against the centric tip (or pit) of the time 8.2.4.13 TheMohrcircleshowninFig.18isdrawnthrough
consolidation crossbeam 26. Push plastic cap Z3 over plate Z2 point P (steady state flow) and is tangential to the yield locus.
(Fig. 9, left position). During time consolidation, the specimen is loaded with the
(1)The plastic cap must not hit against shear cell or lid. major principal stress σ of that Mohr circle as shown in Fig.
Any shocks can influence the bulk solid specimen and lead to 18.
incorrect measurement results.
NOTE 18—During preshear a normal stress as well as a shear stress is
8.2.4.12 Select the applied mass m in such a way that the
Wt
acting, although on the consolidating bench only normal stresses can be
stress state in the specimen during time consolidation is the
applied. Through nearly 40 years of industrial practice with the Jenike
same as during preshear (that is, steady state flow). Shear Tester (see Standard D6128), it has been found that the stress state
D6773 − 22
FIG. 16 Shear Cell 4 and Lid 7 Connected to Hanger 11, Counterbalance System and Tie Rods 12
developed by the application of normal stress alone can successfully magnitude of 10 to 50 Pa (depending on the bulk density of the bulk
approximate that developed in steady state flow.
solid).
When using a time consolidation bench, the masses of the lid 7 (mass
8.2.4.14 Calculate the force, which must act on the bulk
m ) and the time consolidation crossbeam 26 (mass m ) as well as the
L CB
solid at time consolidation, from:
massesoftheloadingrodZ4withthediskZ5(mass m )areactingonthe
C
bulk solid specimen. Thus, for an exact adjustment of the load one has to
F 5σ A (1)
t 1 D
determine the masses of lid 4, time consolidation crossbeam 26, and
NOTE 19—The mass of the bulk solid in the area of the bars of the lid
is neglected here, because it only produces a normal stress on the order of loadingrodZ4withdiskZ5.Toobtainmass m ofthemasseswhichhave
Wt
D6773 − 22
FIG. 17 Stress-Strain Curves—Preshear and Shear
FIG. 18 Yield Locus Showing Valid Shear Points
tobeplacedondiskZ5ofthetimeconsolidationbench,thesemasseshave
8.2.4.15 Since the shear strength after time consolidation is
to be subtracted from mass m = F/g, which would exert the force F as
t t t
not very sensitive to the force σ , it is sufficient to select m
1 Wt
determined following equation (2) :
to satisfy Eq 2 to within 65%.
m 5 F /g 2 m 2 m 2 m (2)
~ !
Wt t L CB C
NOTE 20—To reduce the danger of falling masses, put the applied mass
The remaining mass m is to be exerted through applied mass pieces
Wt
pieces one after the other on disk Z5, turning each applied mass piece by
on the bulk solid specimen; that is, corresponding applied masses have to
about 90° relative to the applied mass piece below.
be placed on disk Z5 of the time consolidation bench when the specimen
under consideration is loaded.
8.2.4.16 Store the specimen under load for the time interval
OftenonecanneglectthemassesofloadingrodZ4anddiskZ5,sothat
specified by the requesting agency or client.
one subtracts only the masses of lid 7 and time consolidation crossbeam
(1)The time consolidation bench may not be subjected to
26 from mass m = F/g:
t t
shocks or vibrations during this time. Also pay attention to
m 5 ~F /g! 2 m 2 m (3)
Wt t L CB
constant temperature. Do not expose the specimens in the time
When Eq 3 is used, the results of the time consolidation measurements
consolidation bench to direct sunlight.
gain some additional safety with regard to silo design for flow, since the
8.2.4.17 After the chosen time t has elapsed, remove the
massesoftheloadingrodZ4andthediskZ5willcauseasomewhatlarger
time consolidation. guide rollers 12 (see Figs. 2 and 3) from the ring shear tester.
D6773 − 22
8.2.4.18 Carefully remove the applied mass pieces from 8.3.10 Empty the bottom ring 48; if necessary clean the
disk Z5 of the time consolidation bench. For this step as well bottom ring 48, the lid 49, and the driving axle 5.
asthefollowingthrough8.2.4.23,becarefulnottobumporjar
8.3.11 Repeatwallfrictionteststwotothreetimeswithnew
the lid or cell; otherwise the results will be incorrect.
specimens of the particulate solid.
8.2.4.19 CarefullyliftuploadingrodZ4withplasticcapZ3
NOTE 23—Sometimes there will be a rapid oscillation of the indicated
and fix the loading rod Z4 in its upper position with fixing
shear force because of slip-stick behavior. Use the shear stress maxima
screw Z6 (Fig. 9, medium position).
recorded during shear to evaluate the wall friction angle ϕ'.
(1)The plastic cap must not hit against shear cell or lid. NOTE 24—In many cases, there is no distinct difference between static
and kinematic friction. However, the shear force may pass through a
Any shocks can influence the bulk solid specimen and lead to
maximum when starting a wall friction test; that is, there is a peak shear
incorrect measurement results.
stress at τ .
w6
8.2.4.20 Remove the shear cell 4 along with the lid 7 from
8.3.12 If static friction is suspected, the static angle of wall
the supporting plate Z2 carefully and without vibrations. Put
friction can be determined as follows: A test is performed as
the shear cell on driving axle 5 of the ring shear tester.
described above but when the shear force has passed through
8.2.4.21 Remove time consolidation crossbeam 26 from lid
the maximum, the direction of rotation is reversed. After the
7.
shear force has fallen to zero, the applied mass on the hanger
8.2.4.22 Carefully put crossbeam 8 on lid 7 and fix it into
is reduced and the motor is started again. The shear force will
position with knurled screws 9. Tighten knurled screws 9 only
again pass through a maximum and the procedure of reversing
loosely.
the direction of rotation and reducing the applied mass is
8.2.4.23 Append hanger 11 carefully at hook 25 which is
repeated. The peak values of τ are used to evaluate the static
w
located on the lower side of the crossbeam 8.
angle of wall friction.
8.2.5 Shear of Specimen After Time Consolidation:
8.4 Wall Friction Time Tests
8.2.5.1 Select a mass m . Perform shear in the same
Ws
8.4.1 Static wall friction tests with time consolidation are
mannerasforinstantaneousflow.Fortimetests,selectnomore
also known as adhesion tests.
than three shear normal stress levels for each preshear stress.
8.4.2 Cut three coupons of the same wall material and wash
NOTE 21—Due to the scatter obtained in time shear tests, it is
and dry them thoroughly.
recommended that they be performed at least twice at each shear normal
8.4.3 Perform a wall friction test using wall friction normal
stress. Only use the higher (highest) value.
stresses σ to σ , to obtain a defined compaction of the
w6 w1
8.3 Procedure for Wall Friction:
particulatesolidparticles.Increasetheloadtoσ andperform
w6
8.3.1 Start the motor.
a shear test until the shear stress attains a constant value.
Withoutstopping,reducetheloadtoσ .Whentheshearstress
w5
NOTE 22—After some time, both tie rods 13 are transferring tensile
againreachesaconstantvalue,
...
This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Because
it may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current version
of the standard as published by ASTM is to be considered the official document.
Designation: D6773 − 16 D6773 − 22
Standard Test Method for
Bulk Solids Using Schulze Ring Shear Tester
This standard is issued under the fixed designation D6773; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope*
1.1 This test method covers the apparatus and procedures for measuring the unconfined yield strength of bulk solids during both
continuous flow and after storage at rest. In addition, measurements of internal friction, bulk density, and wall friction on various
wall surfaces are included.
1.2 This test method covers operation of the manually-controlled Schulze Ring Shear Tester. An automated version of this tester
is also available. Its method of testing bulk solids is similar in principle to that described in this test method.
1.3 The most common use of this information is in the design of storage bins and hoppers to prevent flow stoppages due to arching
and ratholing, including the slope and smoothness of hopper walls to provide mass flow. Parameters for structural design of such
equipment may also be derived from this data. Another application is the measurement of the flowability of bulk solids, for
example, for comparison of different products or optimization.
1.4 All observed and calculated values shall conform to the guidelines for significant digits and rounding established in Practice
D6026.
1.4.1 The procedures used to specify how data are collected/recorded or calculated in this standard are regarded as the industry
standard. In addition, they are representative of the significant digits that generally should be retained. The procedures used do not
consider material variation, purpose for obtaining the data, special purpose studies, or any considerations for the user’s objectives:
and it is common practice to increase or reduce significant digits of reported data to be commensurate with these considerations.
It is beyond the scope of this standard to consider significant digits used in analysis methods for engineering design.
1.5 Units—The values stated in SI units are to be regarded as standard. No other units of measure are included in this standard.
1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility
of the user of this standard to establish appropriate safety safety, health, and healthenvironmental practices and determine the
applicability of regulatory limitations prior to use.
1.7 This international standard was developed in accordance with internationally recognized principles on standardization
established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued
by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
This test method is under the jurisdiction of ASTM Committee D18 on Soil and Rock and is the direct responsibility of Subcommittee D18.24 on Characterization and
Handling of Powders and Bulk Solids.
Current edition approved Feb. 1, 2016Oct. 15, 2022. Published March 2016January 2023. Originally approved in 2002. Last previous edition approved in 20082016 as
D6773 – 08.D6773 – 16. DOI: 10.1520/D6773-16.10.1520/D6773-22.
*A Summary of Changes section appears at the end of this standard
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
D6773 − 22
2. Referenced Documents
2.1 ASTM Standards:
D653 Terminology Relating to Soil, Rock, and Contained Fluids
D2216 Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
D3740 Practice for Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in
Engineering Design and Construction
D4753 Guide for Evaluating, Selecting, and Specifying Balances and Standard Masses for Use in Soil, Rock, and Construction
Materials Testing
D6026 Practice for Using Significant Digits and Data Records in Geotechnical Data
D6128 Test Method for Shear Testing of Bulk Solids Using the Jenike Shear Tester
E177 Practice for Use of the Terms Precision and Bias in ASTM Test Methods
E691 Practice for Conducting an Interlaboratory Study to Determine the Precision of a Test Method
3. Terminology
3.1 Definitions—For common definitions of common technical terms in this standard, refer to Terminology D653.
4. Summary of Test Method
4.1 A representative specimen of bulk solid is placed in a shear cell of specific dimensions.
4.2 When running an instantaneous or time shear test, a normal load is applied to the cover, and the specimen is presheared until
a steady state shear value has been reached. The shear stress is then immediately reduced to zero.
4.3 An instantaneous test is run by shearing the specimen under a reduced normal load until the shear force goes through a
maximum value and then begins to decrease.
4.4 A time shear test is run similarly to an instantaneous shear test, except that the specimen is placed in a consolidation bench
for the specified time between the preshear and shear steps.
4.5 A wall friction test is run by sliding the specimen over a coupon of wall material and measuring the frictional resistance as
a function of normal, compressive load.
4.6 A wall friction time test involves sliding the specimen over the coupon of wall material, stopping and leaving the load on the
specimen for a predetermined period, and then sliding it again to see if the shearing force has changed.
5. Significance and Use
5.1 Reliable, controlled flow of bulk solids from bins and hoppers is essential in almost every industrial facility. Unfortunately,
flow stoppages due to arching and ratholing are common. Additional problems include uncontrolled flow (flooding) of powders,
segregation of particle mixtures, usable capacity which is significantly less than design capacity, caking and spoilage of bulk solids
in stagnant zones, and structural failures.
5.2 By measuring the flow properties of bulk solids, and designing bins and hoppers based on these flow properties, most flow
problems can be prevented or eliminated (1).
5.3 For bulk solids with a significant percentage of particles (typically, one third or more) finer than about 6 mm ( ⁄4 in.), the
unconfined yield strength is governed by the fines (−6 mm fraction). For such bulk solids, strength and wall friction tests may be
performed on the fine fraction only.
NOTE 1—The quality of the result produced by this standard is dependent on the competence of personnel performing it, and the suitability of the
For referenced ASTM standards, visit the ASTM website, www.astm.org, or contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Standards
volume information, refer to the standard’s Document Summary page on the ASTM website.
The boldface numbers in parentheses refer to the list of references at the end of this standard.
D6773 − 22
equipment and facilities used. Agencies that meet the criteria of Practice D3740 are generally considered capable of competent and objective
testing/sampling/inspection/etc. Users of this standard are cautioned that compliance with Practice D3740 does not in itself ensure reliable results.
Reliable results depend on many factors; Practice D3740 provides a means of evaluating some of those factors. Practice D3740 was developed for
agencies engaged in the testing or inspection (or both) of soil and rock. As such it is not totally applicable to agencies performing this standard. However,
users of this standard should recognize that the framework of Practice D3740 is appropriate for evaluating the quality of an agency performing this
standard. Currently there is no known qualifying national authority that inspects agencies that perform this standard.
6. Apparatus
6.1 The Schulze Ring Shear Tester (Figs. 1-6) is composed of a base 1 and a casing 2. The casing 2 contains the driving and
measuring units and carries the working table 38.
6.2 The driving axle 5 (with detachable plastic cap 6) causes the shear cell 4 to rotate. The driver pins at the underside of the shear
cell must set in the toothed wheel at the driving axle 5 to enable a close connection between shear cell and driving axle. The driving
axle is driven by an electric motor and can rotate to the right or to the left. In order to shear the bulk solid specimen, the driving
axle 5 along with the shear cell 4 rotate clockwise (as seen from the top). The electric motor is controlled from the front panel
35 at the front side of casing 2 (Fig. 3). The motor and drive system cause the shear cell to rotate at a speed adjustable between
0.007 and 0.13 rad/min.
6.3 The shear cell lid 7 as well as the bottom of the shear cell 4 has bent bars made of stainless steel (Fig. 4) to prevent slipping
of the bulk solid at the lid or the bottom of the shear cell.
NOTE 2—The standard cell has 20 bars, each of which is 4 mm tall (h = 4 mm, Fig. 7).
Mit
FIG. 1 Ring Shear Tester (overall view)
D6773 − 22
FIG. 2 Shear Cell (in principle)
6.4 The crossbeam 8 sits on the lid 7 and is fixed with two knurled screws 9. The crossbeam 8 has several functions: In the center
of the crossbeam 8 is a fixed axis 10 with a hook to append the hanger 11 (in Figs. 3 and 4 only the handle of the hanger standing
out from the driving axle can be seen). Rollers at the ends of the crossbeam and the removable guide rollers 12 prevent movement
of lid 7 from the centered position.
6.5 A hook 14 at the upper end of the axis 10 of the crossbeam 8 is fastened to the balance arm 15. This arm along with
counterbalance 29 (Fig. 6) serves to compensate for the masses of lid 7, crossbeam 8, hanger 11, and tie rods 13. The
counterbalance 29 is found at the rear side of the balance arm 15.
6.6 A digital displacement indicator 31 (Fig. 8) is used for the measurement of the height of the bulk solid specimen.
6.7 Bolts at the ends of the crossbeam 8 are used to append the tie rods 13. Therefore, a circular hole is at one end of each tie
rod 13. The opposite end is provided with an elongated hole for suspending in the adjustable seating 16 attached to the load beam
17.
6.8 The rotation of the lid 7 is prevented by the tie rods 13 which transfer the tensile force to the load beams 17.
6.9 The bottom part of the hanger 11, which hangs on the crossbeam 8 and serves for exerting a normal load N on the bulk solid,
is located within the base 1 (Fig. 1). The hanger has a circular plate 19 at its lower end for holding the applied mass pieces.
6.10 For control of the motor drive a front panel 35 (Fig. 3) is at the front side of the casing 2.
6.11 The load beams 17 are connected parallel. Each load beam shouldmust be capable of measuring a force up to 200 N with
a precision of 0.02 % of full scale. Thus, the total measuring range, which is twice the measuring range of one load beam, is 400
N. The signal from the force transducer is conditioned by an amplifier and shown on a recorder. (Warning—To avoid overloading
of the load beams, the indicated maximum normal load must not be exceeded.)
D6773 − 22
FIG. 3 Ring Shear Tester (upper part)
6.12 For the Schulze Ring Shear Tester RST-01.01 different shear cells are available. The dimensions of the Standard cell and a
smaller cell can be taken from Table 2 and Fig. 7. For special purposes (for example, reduced internal volume) other dimensions
are also available. The following table provides a rough indication of the applicability of various cell sizes based on maximum
particle size of the bulk solid (monodisperse = narrow particle size distribution, for example, plastics pellets, grain). Values in
parentheses are valid if particles are not brittle.
maximum particle size, x
max
Shear cell type monodisperse broad distribution, 0 .
x
max
M 5 mm 10 mm
S 2.5 mm 5 mm
MV10 1 (1.5) mm 2 (3) mm
SV10 0.75 (1) mm 1.5 (2) mm
6.13 The time consolidation bench serves for the storage of shear cells with bulk solid specimens under load.
D6773 − 22
FIG. 4 Upper Part of the Ring Shear Tester, Shear Cell Removed
6.13.1 The time consolidation bench (Fig. 9) is composed of a frame Z1, on which are fastened three supporting plates Z2. One
small shear cell (type S, volume approx. 200 cm ) can be placed on each plate. The shape of the plate Z2 centers the shear cell.
6.13.2 Through the central depression of the time consolidation crossbeam 26 the normal load is exerted during time consolidation
as shown in the left part of Fig. 9. The lower end of the loading rod Z4 is equipped with a central tip.
6.13.3 The transparent cylindrical plastic cap Z3, when pressed on plate Z2, protects the specimens from the surrounding
atmosphere (for example, to reduce changes of the moisture (water) of the bulk solid specimens). This cap Z3 is joined to the
loading rod Z4 through a rubber bellows Z8.
6.13.4 At the upper end of the loading rod Z4 a disk Z5 is fastened for supporting applied mass pieces by which the vertical load
for time consolidation is applied.
6.13.5 The fixing screw Z6 serves for the fixation of the loading rod Z4 in the upper position (Fig. 9, on the right).
6.14 The wall friction shear cells allow the measurement of wall yield loci from which wall friction angles can be calculated.
6.14.1 The bottom ring 48 of the wall friction shear cell (see Fig. 10) contains the wall material coupon to be tested.
6.14.2 To prevent any relative circumferential displacement between the bottom ring 48 and the wall material coupon, four driving
pins 50 are installed at the outer wall of the bottom ring 48. The annular wall material coupon has to be provided with notches
for these driving pins so that bottom ring and wall material coupon are interlocked. The required dimensions of the wall material
coupon are shown in Fig. 11.
6.14.3 The lid 49 (Fig. 12) has bent bars from stainless steel to prevent slipping of the bulk solid at the lid of the shear cell.
Additionally, the lid of a wall friction shear cell is provided with downwards protruding edges at the inner and outer radius.
D6773 − 22
FIG. 5 View on the Reverse Side of the Ring Shear Tester
6.14.4 The dimensions of the wall friction shear cell are shown in Table 1 and Fig. 13.
6.15 A spatula having a rigid, sharp, straight blade at least 50 % longer than the width of the annulus of the shear cell, and at least
20 mm wide, is needed.
6.16 A laboratory balance having a maximum capacity of at least 5 kg with a precision of 0.01 % or better is required.
7. Specimen Preparation
7.1 The laboratory used for powder testing shouldmust be free of vibrations caused by traffic or heavy machinery. Ideally, the room
should be is temperature and humidity controlled, or, if this is not possible, it should be maintained maintain it at nearly constant
ambient conditions. Direct sunlight, especially on the time consolidation bench, is to be avoided.
NOTE 3—Temperature- and humidity-sensitive materials may need to be tested at different temperatures and moisture (water) contents, because this often
happens in industrial environments. The laboratory environment must approximate production for meaningful testing.
7.2 Setup:
D6773 − 22
FIG. 6 Counterbalance System
TABLE 1 Wall Friction Shear Cell Dimensions
Standard Wall Friction
Shear Cell,
Type WM
Cross-section (lid) A 226 cm
D
r 51 mm
iD
r 99 mm
aD
r 42.5 mm
iSZ
r 107.5 mm
aSZ
h 24 mm
SZ
h 4 mm
Mit
Material Aluminum
7.2.1 Shift the movable counterbalance 29 along the balance arm to adjust the force caused by the counterbalance mass.
NOTE 4—The fixation screw 18 (knurled screw) fixes the counterbalance 29 on the balance arm.
7.2.1.1 After unscrewing the knurled screw, which is the major part of the movable mass 30, shift the movable mass 30 along the
balance arm, if necessary, for more precise adjustment of the force caused by the counterbalance mass.
D6773 − 22
FIG. 7 Main Dimensions of Shear Cell
NOTE 5—When the counterbalance mass is well adjusted, the lid, crossbeam, tie rods, and hanger do not press on the bulk solid; that is, the vertical stress
at the surface of the bulk solid is equal to zero.
7.2.2 Adjust the seatings 16 to level the lid 7.
7.2.3 Adjust the four adjustable stands 3 on base 1 (Fig. 5) to level the Ring Shear Tester.
7.2.4 Unscrew the fixing screw sufficiently so as to be able to move the loading rod upwards or downwards. In the loading position
(Fig. 9, on the left) the fixing screw must remain unscrewed.
7.2.5 Before starting with time consolidation measurements, make sure that the time consolidation bench is level. Use the four
adjustable feet Z7 (Fig. 9), if necessary
7.3 Filling the Cell (Fig. 14):
D6773 − 22
FIG. 8 Determination of the Height of the Specimen
TABLE 2 Shear Cell Dimensions
Standard Cell, Type
Small Cell, Type S
M
3 A 3 A
Internal volume V ca. 900 cm ca. 200 cm
SZ
2 2
Cross-section (lid) A 226 cm 79 cm
D
r 51 mm 31 mm
iD
r 99 mm 59 mm
aD
r 50 mm 30 mm
iSZ
r 100 mm 60 mm
aSZ
h 40 mm 24 mm
SZ
h 4 mm 4 mm
Mit
Material Aluminum or Aluminum or
Stainless Steel Stainless Steel
A
Exact volume to be determined for each cell.
7.3.1 Fill the shear cell 4 uniformly in small horizontal layers by a spoon or spatula without applying force to the surface of the
material until the cell is slightly overfilled with material. The filling should be conducted Fill the cell in such a way as to make
sure that there are no voids within the cell.it.
7.3.2 Remove excess material in small quantities by scraping off with a blade 1 until flush with the top of the annulus. At first
first, scrape the blade should be scraped counterclockwise across the ring one or two times in a zigzag motion. Then Then, scrape
D6773 − 22
FIG. 9 Time Consolidation Bench
the blade should be scraped around the annulus counterclockwise, as shown in Fig. 14a, whereby the blade should be is inclined
by an angle α = 15 to 30° to the radial direction. The blade should always be held Hold the blade vertically or tilted by a few
degrees to the vertical (angle β = 0° to 10°) as shown in Fig. 14b. Do not exert a downward force on the material with the blade.
7.3.3 If coarse particles are present, scraping may tear them from the surface and alter the structure. In such cases it is better to
attempt to fill the cell so that the material surface is flush with the annulus after filling.
7.3.4 If necessary, clean the outside of the shear cell. Then determine the mass of the shear cell with contents. Note the total mass
m .
tot
7.4 Wall Friction:
7.4.1 When measuring the friction between the particulate solid and a coupon of silo wall material in a wall friction test, add
spacers and a coupon of wall material to the shear cell bottom ring. Shear the specimen contained in bottom ring over the wall
material coupon under different wall normal stresses σ and measure the resulting wall shear stresses τ .
w w
7.4.2 Selection of Wall Friction Normal Stress Levels:
7.4.2.1 Select six wall friction normal stress levels σ to σ where σ is the smallest normal stress. The largest normal stress
w1 w6 w1
σ shouldmust be approximately equal to the major principal stress σ of the second preshear normal stress, σ . The smallest
w6 1,2 p,2
normal stress σ will normally include the hanger without applied masses.
w1
7.4.3 Wall Coupon and Material Specimen Preparation:
D6773 − 22
FIG. 10 Wall Friction Shear Cell (bottom ring)
7.4.3.1 Wash the wall material coupon and dry thoroughly before the test. Do not touch the surface after washing with bare hands.
7.4.3.2 Insert the spacer rings 51 and the wall material coupon in the bottom ring 48 (Fig. 10). The distance between upper edge
of the bottom ring 48 and upper surface of the wall material coupon shouldmust total about 8 to 10 mm.
NOTE 6—The thickness of each spacer ring is 2 mm.
7.4.3.3 Determine the mass of the bottom ring 48 with content (note total mass m ).
wall
7.4.3.4 Connect crossbeam 8 and lid 49 using the knurled screws 9.
7.4.3.5 Fill the bottom ring 48 with the bulk solid to be tested. See 7.3.
7.4.3.6 If necessary, clean the bottom ring 48 from outside. Then determine the mass of the bottom ring 48 with content (note total
mass m ).
W,tot
7.4.3.7 Ascertain that the power supply is switched on.
7.4.3.8 Put the filled bottom ring 48 on driving axle 5 (in analogy to Fig. 15). The driver pins at the underside of the shear cell
must engage in the toothed wheel at the driving axle 5.
7.4.3.9 Carefully place the lid 49 concentrically on the bottom ring 48 on the bulk solid specimen. The lid 49 must be in a position
turned a few degrees counterclockwise to its shear position (shear position: longitudinal axis of the crossbeam 8 is perpendicular
to the front edge of the casing 2). The Direct the open side of the hook 25 in the center of the crossbeam 8 should be directed to
the right. Locate handle 24 of the hanger 11 on the right side of crossbeam 8 (in analogy to Fig. 16).
D6773 − 22
FIG. 11 Dimensions of Wall Material Coupon
7.4.3.10 Put the tie rods 13 on both the bolts at the ends of crossbeam 8 (circular holes of tie rods 13) and the seatings 16 at the
load beams 17 (long hole of the tie rod 13).
(1) The Ensure that the tie rods 13 should have some clearance in the seatings 16; that is, the tie rods must not be stressed at
that stage. Important: If it is not possible to connect the tie rods as described above, do not move the lid manually! This would
influence the test result. Only use the motor drive to turn the shear cell with the lid in a position where it is possible to connect
the tie rods to the load beams.
7.4.3.11 Append hanger 11 at hook 25 on the lower side of crossbeam 8.
7.4.3.12 Carefully put appropriate applied mass pieces on the circular plate 19 of the hanger.
NOTE 7—The total mass of the applied mass pieces on the hanger must be less than or equal to the maximum normal load to be used for the wall friction
measurement.
7.4.3.13 Remove hook 14, which is connected to the balance arm, from its off-position mounting 32 and append it to the central
axis 10 (in analogy to Fig. 16). To do this, the front end of the balance arm must be pulled down at the black handle 46 provided
for this (the handle is not shown in all figures; see Fig. 6).
(1) If the lid sinks down very much, the lower edge of the lid may touch directly the upper surface of the wall material coupon,
thus causing incorrect measurement results. If this happens, remove the shear cell from the tester, remove the lid from the bottom
ring, and add additional bulk solid into the bottom ring following procedure starting at 7.4.3.5.
D6773 − 22
FIG. 12 Wall Friction Shear Cell Placed on the Ring Shear Tester
FIG. 13 Main Dimensions of Wall Friction Shear Cell
7.4.3.14 Check the adjustment of the rotational velocity (front panel 35). The circumferential velocity at the mean specimen
diameter shouldmust be 1 to 2 mm/min.
D6773 − 22
FIG. 14 Scraping Off Excess Powder
FIG. 15 Ring Shear Tester with Shear Cell on Driving Axle 5
8. Procedure
8.1 Procedure for Instantaneous Shear Test
8.1.1 Preshear:
8.1.1.1 Ascertain that the power supply has been turned on at least 15 min to ensure that the unit is properly warmed up.
D6773 − 22
FIG. 16 Shear Cell 4 and Lid 7 Connected to Hanger 11, Counterbalance System and Tie Rods 12
8.1.1.2 Put the filled shear cell 4 on the driving axle 5 (Fig. 15). Make sure that the driver pins on the underside of the shear cell
engage the toothed wheel of the driving axle 5.
8.1.1.3 Select the first preshear normal stress σ on the basis of the bulk density of the test material, in accordance with the
p,1
following table:
D6773 − 22
ρ (kg/m ) σ (kPa)
b p,1
< 300 approximately 1.5
300 to 800 approximately 2.0
800 to 1600 approximately 2.5
1600 to 2400 approximately 3.0
> 2400 approximately 4.0
8.1.1.4 Follow 8.1.1.5 – 8.1.1.10 only if the normal load at preshear is greater than 15 N. Otherwise go to 8.1.1.12.
NOTE 8—The latter procedure is necessary so as to not over-consolidate a bulk solid specimen at small normal loads.
8.1.1.5 Connect crossbeam 8 and lid 7 using the knurled screws 9. Fasten screws only very slightly. Position the lid concentrically
on the shear cell and turned a few degrees counterclockwise to its shear position (shear position: longitudinal axis of the crossbeam
is perpendicular to the front edge of the casing 2). The Direct the open side of hook 25 in the center of crossbeam 8 should be
directed to the right. Locate handle 24 of hanger 11 on the right side of crossbeam 8 (Fig. 16).
8.1.1.6 Put tie rods 13 on both the bolts at the ends of crossbeam 8 (circular holes of tie rods 13) and seatings 16 at load beams
17 (long hole of the tie rod 13).
8.1.1.7 The Ensure that the tie rods 13 should have some clearance in the seatings 16; that is, the tie rods must not be stressed
at this stage. If it is not possible to connect the tie rods as described above, do not move the lid manually since this would influence
the test result. Only use the motor drive to turn the shear cell with the lid in a position where it is possible to connect the tie rods
to the load beams.
8.1.1.8 Append hanger 11 at hook 25 at the lower side of crossbeam 8.
8.1.1.9 Carefully put an applied mass piece on the circular plate 19 of hanger 11 (mass needed for preshear or smaller mass).
8.1.1.10 Remove hook 14, which is connected to the balance arm, from its off-position mounting 32 and append it to the central
axis 10 (this already has been done in Fig. 16). To do this, pull down the front end of the balance arm must be pulled down at the
black handle 46 provided for this (the handle is not shown in all figures; see Fig. 6).
8.1.1.11 Follow 8.1.1.12 – 8.1.1.16 if the normal load at preshear is less than 15 N. (These steps can also be used alternatively
to 8.1.1.5 – 8.1.1.10.)
8.1.1.12 Connect crossbeam 8 and lid 7 using the knurled screws 9. Fasten screws only very slightly. Remove hook 14, which is
connected to the balance arm, from its off-position at mounting 32 and append it to the central axis 10. The lid is then in a “lifted
position.”
8.1.1.13 Put at least one applied mass piece on the circular plate 19 of the hanger 11.
NOTE 9—The mass on the hanger can be less than or equal to that needed for preshear, but shouldmust not exceed 1 kg.
8.1.1.14 Hold the lid in its lifted position with one hand and append hanger 11 at hook 25 at the lower side of crossbeam 8.
8.1.1.15 Carefully place the lid concentrically on the shear cell on the bulk solid specimen. The lid must be in a position turned
a few degrees counterclockwise to its shear position (shear position: longitudinal axis of the crossbeam is perpendicular to the front
edge of the casing 2). The Direct the open side of hook 25 in the center of crossbeam 8 should be directed to the right. Locate
handle 24 of hanger 11 on the right side of crossbeam 8 (Fig. 16).
8.1.1.16 Put tie rods 13 on both the bolts at the ends of crossbeam 8 (circular holes of tie rods 13) and the seatings 16 at load beams
17 (long hole of the tie rod 13). The Ensure that the tie rods 13 should have some clearance in the seatings 16; that is, the tie rods
must not be stressed at this stage. If it is not possible to connect the tie rods in this manner, use the motor drive to turn the shear
cell with the lid to an appropriate position.
8.1.1.17 If not already done (at 8.1.1.9 or 8.1.1.13, respectively), put additional applied mass pieces on the hanger 11 for adjusting
the normal force required for preshear. If the lid sinks down more than around 10 mm, refill the shear cell (remove the shear cell
from the tester and go back to 7.3).
D6773 − 22
NOTE 10—At the beginning of preshear, some powder may escape, which is one reason why the lid may sink. Provided that 8.1.1.17 is followed, loss
of powder can be neglected.
8.1.1.18 Check the adjustment of the rotational velocity (front panel 35). The circumferential velocity at the mean diameter
shouldmust be 1 to 2 mm/min.
8.1.1.19 Start the motor (front panel 35).
NOTE 11—After some time both tie rods 13 are transferring tensile forces. The total force F (“shear force”) is then measured.
8.1.1.20 As soon as the shear force F stops increasing (steady-state flow is reached), Fig. 17, reverse the direction of rotation of
the shear cell. After both load beams are relieved (shear force F = 0), continue rotating the shear cell until the tie rods 13 have about
1 mm clearance in the seatings 16. Then stop the motor.
8.1.1.21 Record the force F measured at steady-state flow.
(1) If the shear force does not reach a constant value, steady-state flow can be assumed if, after 30 mm of shear displacement
(measured at the mean radius of the shear cell annulus), this force does not increase more than 0.05 % per mm of shear
displacement. If this condition has not been achieved after 30 mm of displacement, preshear should be continued continue preshear
until it is met. If the technician decides to terminate preshear before this condition is met, it shouldmust be noted before continuing
with the test.
(2) The shear force should not decrease during preshear. If it starts to do so after a period of constant value, preshear should
be stopped stop preshear immediately and begin the steps starting with 8.1.2 begun.
(3) Constancy of the values of the steady state shear stress τ obtained after preshear is an indication of the reproducibility of
p
consolidation. With correctly consolidated specimens individual values of the steady state shear stress should not deviate by more
than 65 % from the average steady state shear stress for the given preshear normal stress. With some particulate solids (particularly
coarser particles), however, this tolerance cannot be achieved. If this happens it shouldmust be noted by the technician performing
the test.
8.1.2 Shear:
8.1.2.1 Select a shear normal stress level σ within the range of 25 to 80 % of the preshear normal stress level σ , and replace the
s p
mass m by a smaller mass m . Switch on the motor again in the forward direction.
Wp Ws
FIG. 17 Stress-Strain Curves—Preshear and Shear
D6773 − 22
NOTE 12—After the tie rods 13 are tensed again, the shear force rapidly increases, goes through a maximum representing the yield shear force, and then
begins to decrease (Fig. 17). This part of the test is called shear.
NOTE 13—The value τ is the shear stress at failure (peak shear point) for the selected shear normal stress σ at the selected preshear normal stress σ .
s s p
Metal-to-powder friction, which may occur at the side walls of the shear cell and at the tips of the bars under the lid, is assumed to be negligible because
the areas where metal-to-powder friction may occur are very small compared to the cross-section of the shear plane, and therefore ignored.
8.1.2.2 Switch on the digital displacement indicator 31. After the display of the indicator shows “0.00 mm,” set the indicator on
the crossbeam 8. Position the probe tip through a hole in the crossbeam 8 in such a way that it presses on top of the inner side
wall of the shear cell 4 and the spacer tube 36 is in contact with the upper surface of the crossbeam 8 (Fig. 8). Note the displacement
indicated on the display.
8.1.2.3 Repeat the measurement at the opposite side of the crossbeam.
8.1.2.4 Remove the indicator 31.
8.1.2.5 Calculate the mean value of both measured displacements, which is the mean decrease in height Δh of the bulk solid
specimen. Note this mean value.
8.1.2.6 Drive back the shear cell 4 until tie rods 13 are relieved. Then switch off the motor.
8.1.2.7 Remove tie rods 13.
8.1.2.8 Unhook hook 14 from the central axis 10 thus deactivating the counterbalance system.
8.1.2.9 Remove applied mass pieces from the hanger 11.
8.1.2.10 Unhook hanger 11 from the hook 25 at the lower side of the crossbeam 8.
8.1.2.11 Take off the shear cell 4 along with the lid 7.
8.1.2.12 Empty the shear cell; if necessary clean the shear cell, the lid and the driving axle.
8.1.3 Additional Tests:
8.1.3.1 Repeat 7, 8.1.1, and 8.1.2.
8.1.3.2 Select 3 to 5 shear normal stress levels σ within the range of 25 to 80 % of the preshear normal stress level σ , and repeat
s p
7, 8.1.1, and 8.1.2.
8.1.3.3 Select higher preshear normal stress levels so that:
σ = 2σ
p,2 p,1
σ = 4σ
p,3 p,1
σ = 8σ
p,4 p,1
NOTE 14—Some adjustment in preshear normal stress levels may be necessary in order to cover the range of major principal stresses σ necessary to
accurately calculate critical arching and/or ratholing dimensions.
8.1.3.4 Repeat 7, 8.1.1, 8.1.2, and 8.1.3.2 for each selected preshear normal stress level.
NOTE 15—Following the procedure given in 7, 8.1.1, and 8.1.2 (Procedure A) requires a new filling of the shear cell for each measurement; that is, each
point on a yield locus. In the literature a second measuring procedure (Procedure B) is frequently recommended (for example, in (2)), where several points
of a yield locus are determined using the identical bulk solid specimen several times. In this case, one would jump again and again from 8.1.2.1 back
to 8.1.1.19 until all desired measuring points are determined. Only then would 8.1.2.2 and the following steps be performed.
Procedure B is generally the preferred procedure, since it is less time consuming than Procedure A. Unfortunately, some bulk solids are sensitive to
shear deformation and, as a result, their shear stress values decrease with large shear deformation. Sometimes a result of this can be that Procedure B
yields too small values of the unconfined yield strength (3). To determine if Procedure B is appropriate, examine a new bulk solid first with this procedure.
Repeat the first measuring point at the end. If the prorated shear stress is noticeably smaller than at the first measurement (say, a difference greater than
D6773 − 22
2.5 %), use Procedure A should be used for the product under consideration, or at least limit the number of shear points measured using Procedure B
should be limited.B.
If Procedure B is applicable, shear the specimen should be sheared only until the shear force becomes constant. Frequently, if the shear displacement
is large at the first preshearing of a bulk solid specimen, the shear force passes over a product dependent, weak maximum (3). Afterwards, a constant
shear force somewhat smaller than the maximum shear force is reached. Do not wait until this lower level is reached. The preshearing is finished when
the maximum is reached; that is, the shear force no longer increases, and the shear force does not yet start to decrease again. One can ascertain this
condition easily, if the shearing velocity is not too high.
In principle, all measurement results, as those of other shear testers, have to be considered critically and applied with the necessary caution and care.
8.2 Shear Testing Procedure for Time Consolidation
8.2.1 When a particulate solid is exposed to a normal or compressive stress for some time it may gain strength. This gain in
strength can be measured using the Schulze Ring Shear Tester, and the effect is called time consolidation.
8.2.2 Time consolidation is carried out using a consolidating bench which consists of several shear cells which can be
independently loaded. The time that the specimens sit at rest is specified according to the application.
8.2.2.1 As an alternative to using a consolidation bench, consider the following: a critically consolidated specimen is prepared by
preshearing with applied mass m . After attaining steady state flow, the rotation of the shear cell is stopped but the direction is
Wp
not reversed. The shear zone formed thus remains under the normal and shear stresses corresponding to steady state flow and is
kept in this state for a defined time t. If the shear cell rotation is then reversed, the shear force will drop to zero and the actual shear
test may be performed in the usual way.
NOTE 16—If the effect of time consolidation in the Schulze Ring Shear Tester were measured as described above, one test would monopolize the shear
tester for a very long time. Creep of the specimen could also cause a decrease in the applied shear force during the resting phase.
8.2.3 Specimen Preparation and Preshear Time Effect:
8.2.3.1 After completion of instantaneous testing and evaluation, perform time tests at the same preshear normal stress levels.
NOTE 17—For a selected preshear normal stress, specimen preparation and preshear are the same as for the instantaneous test.
8.2.4 Time Consolidation:
8.2.4.1 Perform each test for time consolidation in the following way. Using the shear tester, prepare and preshear specimens with
applied mass m in the normal manner and then reverse the rotation of the shear cell after preshear.
Wp
8.2.4.2 Remove the already relieved tie rods 13.
8.2.4.3 Carefully unhook hook 14 of the counterbalance system from the central axis 10 of the crossbeam 8. For this step as well
as the following through 8.2.4.11, be careful not to bump or jar the lid or cell; otherwise the results will be incorrect.
8.2.4.4 Remove the applied mass pieces from the hanger 11.
8.2.4.5 Unhook hanger 11 from the hook 25 on the lower side of the crossbeam 8.
8.2.4.6 Completely unscrew the knurled screws 9, which join the crossbeam 8 with the lid 7.
8.2.4.7 Carefully remove crossbeam 8 from lid 7.
8.2.4.8 Carefully put time consolidation crossbeam 26 centrally on the lid 7.
8.2.4.9 Fix plastic cap Z3 of time consolidation bench in its upper position with the help of the fixing screw Z6 (Fig. 9, right
position).
8.2.4.10 Remove the shear cell 4 along with the lid 7 from driving axle 5 carefully and without vibrations. Put the shear cell on
a free supporting plate Z2 of the prepared time consolidation bench (Fig. 9, medium position).
D6773 − 22
8.2.4.11 Hold plastic cap Z3 with one hand, and loosen the fixing screw Z6 with the other hand. Then let down the plastic cap
slowly, thereby leading loading rod Z4 with one hand so that it runs against the centric tip (or pit) of the time consolidation
crossbeam 26. Push plastic cap Z3 over plate Z2 (Fig. 9, left position).
(1) The plastic cap must not hit against shear cell or lid. Any shocks can influence the bulk solid specimen and lead to incorrect
measurement results.
8.2.4.12 Select the applied mass m in such a way that the stress state in the specimen during time consolidation is the same as
Wt
during preshear (that is, steady state flow).
8.2.4.13 The Mohr circle shown in Fig. 18 is drawn through point P (steady state flow) and is tangential to the yield locus. During
time consolidation, the specimen is loaded with the major principal stress σ of that Mohr circle as shown in Fig. 18.
NOTE 18—During preshear a normal stress as well as a shear stress is acting, although on the consolidating bench only normal stresses can be applied.
Through nearly 40 years of industrial practice with the Jenike Shear Tester (see Standard D6128), it has been found that the stress state developed by
the application of normal stress alone can successfully approximate that developed in steady state flow.
8.2.4.14 Calculate the force, which must act on the bulk solid at time consolidation, from:
F 5 σ A (1)
t 1 D
NOTE 19—The mass of the bulk solid in the area of the bars of the lid is neglected here, because it only produces a normal stress on the order of magnitude
of 10 to 50 Pa (depending on the bulk density of the bulk solid).
When using a time consolidation bench, the masses of the lid 7 (mass m ) and the time consolidation crossbeam 26 (mass m ) as well as the masses
L CB
of the loading rod Z4 with the disk Z5 (mass m ) are acting on the bulk solid specimen. Thus, for an exact adjustment of the load one has to determine
C
the masses of lid 4, time consolidation crossbeam 26, and loading rod Z4 with disk Z5. To obtain mass m of the masses which have to be placed on
Wt
disk Z5 of the time consolidation bench, these masses have to be subtracted from mass m = F /g, which would exert the force F as determined following
t t t
equation (2) :
m 5 F /g 2 m 2 m 2 m (2)
~ !
Wt t L CB C
The remaining mass m is to be exerted through applied mass pieces on the bulk solid specimen; that is, corresponding applied masses have to be
Wt
placed on disk Z5 of the time consolidation bench when the specimen under consideration is loaded.
Often one can neglect the masses of loading rod Z4 and disk Z5, so that one subtracts only the masses of lid 7 and time consolidation crossbeam 26
from mass m = F /g:
t t
m 5 F /g 2 m 2 m (3)
~ !
Wt t L CB
When Eq 3 is used, the results of the time consolidation measurements gain some additional safety with regard to silo design for flow, since the masses
of the loading rod Z4 and the disk Z5 will cause a somewhat larger time consolidation.
8.2.4.15 Since the shear strength after time consolidation is not very sensitive to the force σ , it is sufficient to select m to satisfy
1 Wt
Eq 2 to within 65 %.
FIG. 18 Yield Locus Showing Valid Shear Points
D6773 − 22
NOTE 20—To reduce the danger of falling masses, put the applied mass pieces one after the other on disk Z5, turning each applied mass piece by about
90° relative to the applied mass piece below.
8.2.4.16 Store the specimen under load for the time interval specified by the requesting agency or client.
(1) The time consolidation bench may not be subjected to shocks or vibrations during this time. Also pay attention to constant
temperature. Do not expose the specimens in the time consolidation bench to direct sunlight.
8.2.4.17 After the chosen time t has elapsed, remove the guide rollers 12 (see Figs. 2 and 3) from the ring shear tester.
8.2.4.18 Carefully remove the applied mass pieces from disk Z5 of the time consolidation bench. For this step as well as the
following through 8.2.4.23, be careful not to bump or jar the lid or cell; otherwise the results will be incorrect.
8.2.4.19 Carefully lift up loading rod Z4 with plastic cap Z3 and fix the loading rod Z4 in its upper position with fixing screw Z6
(Fig. 9, medium position).
(1) The plastic cap must not hit against shear cell or lid. Any shocks can influence the bulk solid specimen and lead to incorrect
measurement results.
8.2.4.20 Remove the shear cell 4 along with the lid 7 from the supporting plate Z2 carefully and without vibrations. Put the shear
cell on driving axle 5 of the ring shear tester.
8.2.4.21 Remove time consolidation crossbeam 26 from lid 7.
8.2.4.22 Carefully put crossbeam 8 on lid 7 and fix it into position with knurled screws 9. Tighten knurled screws 9 only loosely.
8.2.4.23 Append hanger 11 carefully at hook 25 which is located on the lower side of the crossbeam 8.
8.2.5 Shear of Specimen After Time Consolidation:
8.2.5.1 Select a mass m . Perform shear in the same manner as for instantaneous flow. For time tests, select no more than three
Ws
shear normal stress levels for each preshear stress.
NOTE 21—Due to the scatter obtained in time shear tests, it is recommended that they be performed at least twice at each shear normal stress. Only use
the higher (highest) value.
8.3 Procedure for Wall Friction:
8.3.1 Start the motor.
NOTE 22—After some time, both tie rods 13 are transferring tensile forces. The total force F (“shear force”) is
...








Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.
Loading comments...