SIST EN 62446-1:2016
(Main)Photovoltaic (PV) systems - Requirements for testing, documentation and maintenance - Part 1: Grid connected systems - Documentation, commissioning tests and inspection
Photovoltaic (PV) systems - Requirements for testing, documentation and maintenance - Part 1: Grid connected systems - Documentation, commissioning tests and inspection
IEC 62446-1:2016 defines the information and documentation required to be handed over to a customer following the installation of a grid connected PV system. It also describes the commissioning tests, inspection criteria and documentation expected to verify the safe installation and correct operation of the system. It is for use by system designers and installers of grid connected solar PV systems as a template to provide effective documentation to a customer. This new edition cancels and replaces IEC 62446 published in 2009 and includes the following significant technical change with respect to IEC 62446:2009: expansion of the scope to include a wider range of system test and inspection regimes to encompass larger and more complex PV systems.
Photovoltaik (PV) Systeme - Anforderungen an Prüfung, Dokumentation und Instandhaltung - Teil 1: Netzgekoppelte Systeme - Dokumentation, Inbetriebnahmeprüfung und Prüfanforderungen
Systèmes photovoltaïques (PV) - Exigences pour les essais, la documentation et la maintenance - Partie 1: Systèmes connectés au réseau électrique - Documentation, essais de mise en service et examen
L'IEC 62446-1:2016 définit les informations et la documentation exigées devant être remises à un client à la suite de l'installation d'un système PV connecté au réseau. Elle décrit également les exigences des essais de mise en service, des critères d'examen et de la documentation prévus pour vérifier la sécurité d'installation et le fonctionnement correct du système. Elle est utilisée par des concepteurs et installateurs de systèmes PV solaires connectés au réseau, en tant que modèle pour une documentation efficace destinée à un client. Cette nouvelle édition annule et remplace l'IEC 62446, parue en 2009 et inclut la modification technique majeure suivante par rapport à l'IEC 62446:2009: extension du domaine d'application pour inclure une gamme plus vaste d'essais de système et de programmes d'examen permettant d'englober des systèmes PV plus importants et plus complexes.
Fotonapetostni sistemi – Zahteve za preskušanje, dokumentiranje in vzdrževanje – 1. del: Sistemi, priključeni na omrežje – Dokumentacija, prevzemni preskusi in nadzor
Ta del IEC 62446 opredeljuje informacije in dokumentacijo, ki mora biti izročena uporabniku ob prevzemu nameščenega in na omrežje priključenega fotonapetostnega sistema. Opisuje tudi prevzemne preskuse, merila pregleda in dokumentacijo, pričakovano za preverjanje varnosti namestitve in pravilnega delovanja sistema. Uporabi se lahko tudi pri periodičnih preskusih.
Ta del IEC 62446 je napisan za na omrežje priključene fotonapetostne sisteme, ki ne uporabljajo hranilnikov energije (na primer baterij) ali hibridnih sistemov.
Ta del IEC 62446 uporabljajo načrtovalci in inštalaterji na omrežje priključenih sončnih fotonapetostnih sistemov kot podlago, da je uporabniku izročena uporabna dokumentacija. Podrobnosti prevzemnih preskusov in meril pregleda so namenjene tudi v pomoč pri preverjanju/pregledu na omrežje priključenega fotonapetostnega sistema po namestitvi in pri poznejšem ponovnem pregledu, vzdrževanju ali spremembah.
Ta del IEC 62446 določa različne preskusne režime za različne sončne fotonapetostne sisteme, da bi se zagotovil ustrezen preskusni režim glede na konkretno izvedbo, tip in sestavo.
OPOMBA: Ta del IEC 62446 ni namenjen koncentriranim fotonapetostnim (CPV) sistemom, čeprav je kar nekaj delov mogoče uporabiti tudi zanje.
General Information
Relations
Standards Content (Sample)
SLOVENSKI STANDARD
01-junij-2016
1DGRPHãþD
SIST EN 62446:2010
)RWRQDSHWRVWQLVLVWHPLSULNOMXþHQLQDRPUHåMH0LQLPDOQH]DKWHYH]DVLVWHPVNR
GRNXPHQWDFLMRSUHY]HPQHSUHVNXVHLQQDG]RU
Grid connected PV systems - Minimum requirements for system documentation,
commissioning tests and inspection
Systèmes photovoltaïques connectés au réseau électrique - Exigences minimales pour
la documentation du système, les essais de mise en service et l’examen
Ta slovenski standard je istoveten z: EN 62446-1:2016
ICS:
27.160 6RQþQDHQHUJLMD Solar energy engineering
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
EUROPEAN STANDARD EN 62446-1
NORME EUROPÉENNE
EUROPÄISCHE NORM
April 2016
ICS 27.160 Supersedes EN 62446:2009
English Version
Photovoltaic (PV) systems - Requirements for testing,
documentation and maintenance - Part 1: Grid connected
systems - Documentation, commissioning tests and inspection
(IEC 62446-1:2016)
Systèmes photovoltaïques (PV) - Exigences pour les Photovoltaik (PV) Systeme - Anforderungen an Prüfung,
essais, la documentation et la maintenance - Partie 1: Dokumentation und Instandhaltung - Teil 1: Netzgekoppelte
Systèmes connectés au réseau électrique - Documentation, Systeme - Dokumentation, Inbetriebnahmeprüfung und
essais de mise en service et examen Prüfanforderungen
(IEC 62446-1:2016) (IEC 62446-1:2016)
This European Standard was approved by CENELEC on 2016-02-23. CENELEC members are bound to comply with the CEN/CENELEC
Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the CEN-CENELEC
Management Centre or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CENELEC member into its own language and notified to the CEN-CENELEC Management Centre has the
same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, Former Yugoslav Republic of Macedonia, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia,
Lithuania, Luxembourg, Malta, the Netherlands, Norway, Poland, Portugal, Romania, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Turkey and the United Kingdom.
European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Avenue Marnix 17, B-1000 Brussels
© 2016 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Ref. No. EN 62446-1:2016 E
European foreword
The text of document 82/1036/FDIS, future edition 1 of IEC 62446-1, prepared by IEC/TC 82 “Solar
photovoltaic energy systems" was submitted to the IEC-CENELEC parallel vote and approved by
CENELEC as EN 62446-1:2016.
The following dates are fixed:
(dop) 2016-11-23
• latest date by which the document has to be
implemented at national level by
publication of an identical national
standard or by endorsement
• latest date by which the national (dow) 2019-02-23
standards conflicting with the
document have to be withdrawn
This document supersedes EN 62446:2009.
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC [and/or CEN] shall not be held responsible for identifying any or all such
patent rights.
Endorsement notice
The text of the International Standard IEC 62446-1:2016 was approved by CENELEC as a European
Standard without any modification.
Annex ZA
(normative)
Normative references to international publications
with their corresponding European publications
The following documents, in whole or in part, are normatively referenced in this document and are
indispensable for its application. For dated references, only the edition cited applies. For undated
references, the latest edition of the referenced document (including any amendments) applies.
NOTE 1 When an International Publication has been modified by common modifications, indicated by (mod), the relevant
EN/HD applies.
NOTE 2 Up-to-date information on the latest versions of the European Standards listed in this annex is available here:
www.cenelec.eu.
Publication Year Title EN/HD Year
IEC 60364-6 - Low voltage electrical installations -- Part HD 60364-6 -
6: Verification
IEC 61010 series Safety requirements for electrical EN 61010 series
equipment for measurement, control and
laboratory use
IEC 61557 series Electrical safety in low voltage distribution EN 61557 series
systems up to 1 000 V a.c. and 1 500 V
d.c. - Equipment for testing, measuring or
monitoring of protective measures
IEC 61730 series Photovoltaic (PV) module safety EN 61730 series
qualification
IEC/TS 62548 2013 Photovoltaic (PV) arrays - Design - -
requirements
IEC 62446-1 ®
Edition 1.0 2016-01
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
colour
inside
Photovoltaic (PV) systems – Requirements for testing, documentation
and maintenance –
Part 1: Grid connected systems – Documentation, commissioning tests
and inspection
Systèmes photovoltaïques (PV) – Exigences pour les essais, la documentation
et la maintenance –
Partie 1: Systèmes connectés au réseau électrique – Documentation,
essais de mise en service et examen
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
INTERNATIONALE
ICS 27.160 ISBN 978-2-8322-3100-5
– 2 – IEC 62446-1:2016 © IEC 2016
CONTENTS
FOREWORD . 5
INTRODUCTION . 7
1 Scope . 8
2 Normative references . 8
3 Terms and definitions . 8
4 System documentation requirements . 10
4.1 General . 10
4.2 System data . 10
4.2.1 Basic system information . 10
4.2.2 System designer information . 11
4.2.3 System installer information . 11
4.3 Wiring diagram . 11
4.3.1 General . 11
4.3.2 Array – General specifications . 11
4.3.3 PV string information . 11
4.3.4 Array electrical details . 12
4.3.5 AC system . 12
4.3.6 Earthing and overvoltage protection. 12
4.4 String layout . 12
4.5 Datasheets . 12
4.6 Mechanical design information . 12
4.7 Emergency systems . 12
4.8 Operation and maintenance information . 13
4.9 Test results and commissioning data . 13
5 Verification . 13
5.1 General . 13
5.2 Inspection . 14
5.2.1 General . 14
5.2.2 DC system – General . 14
5.2.3 DC system – Protection against electric shock . 14
5.2.4 DC system – Protection against the effects of insulation faults . 14
5.2.5 DC system – Protection against overcurrent . 15
5.2.6 DC system – Earthing and bonding arrangements . 15
5.2.7 DC system – Protection against the effects of lightning and overvoltage . 15
5.2.8 DC system – Selection and erection of electrical equipment . 15
5.2.9 AC system . 16
5.2.10 Labelling and identification . 16
5.3 Testing . 16
5.3.1 General . 16
5.3.2 Test regimes and additional tests . 17
5.3.3 Test regimes for systems with module level electronics . 17
5.3.4 Category 1 test regime – All systems . 18
5.3.5 Category 2 test regime . 18
5.3.6 Additional tests . 19
6 Test procedures – Category 1 . 19
6.1 Continuity of protective earthing and equipotential bonding conductors . 19
IEC 62446-1:2016 © IEC 2016 – 3 –
6.2 Polarity test . 19
6.3 PV string combiner box test . 20
6.4 PV string – Open circuit voltage measurement . 20
6.5 PV string – Current measurement . 21
6.5.1 General . 21
6.5.2 PV string – Short circuit test . 21
6.5.3 PV string – Operational test . 22
6.6 Functional tests . 22
6.7 PV array insulation resistance test . 22
6.7.1 General . 22
6.7.2 PV array insulation resistance test – Test method. 23
6.7.3 PV array insulation resistance – Test procedure . 23
7 Test procedures – Category 2 . 25
7.1 General . 25
7.2 String I-V curve measurement . 25
7.2.1 General . 25
7.2.2 I-V curve measurement of V and I . 25
oc sc
7.2.3 I-V curve measurement – Array performance . 25
7.2.4 I-V curve measurement – Identification of module / array defects or
shading issues . 26
7.3 PV array infrared camera inspection procedure . 27
7.3.1 General . 27
7.3.2 IR test procedure . 27
7.3.3 Interpreting IR test results . 27
8 Test procedures – Additional tests . 28
8.1 Voltage to ground – Resistive ground systems . 28
8.2 Blocking diode test . 28
8.3 PV array – Wet insulation resistance test . 29
8.3.1 General . 29
8.3.2 Wet insulation test procedure . 29
8.4 Shade evaluation . 29
9 Verification reports . 30
9.1 General . 30
9.2 Initial verification . 31
9.3 Periodic verification . 31
Annex A (informative) Model verification certificate . 32
Annex B (informative) Model inspection report . 33
Annex C (informative) Model PV array test report . 36
Annex D (informative) Interpreting I-V curve shapes . 37
D.1 General . 37
D.2 Variation 1 – Steps or notches in curve . 38
D.3 Variation 2 – Low current . 38
D.4 Variation 3 – Low voltage . 38
D.5 Variation 4 – Rounder knee . 39
D.6 Variation 5 – Shallower slope in vertical leg . 39
D.7 Variation 6 – Steeper slope in horizontal leg . 40
Figure 1 – Example sun-path diagram . 30
– 4 – IEC 62446-1:2016 © IEC 2016
Figure D.1 – I-V curve shapes. 37
Table 1 – Modifications to the test regime for systems with module level electronics . 17
Table 2 – Minimum values of insulation resistance – PV arrays up to 10 kWp . 24
IEC 62446-1:2016 © IEC 2016 – 5 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
PHOTOVOLTAIC (PV) SYSTEMS – REQUIREMENTS FOR TESTING,
DOCUMENTATION AND MAINTENANCE –
Part 1: Grid connected systems – Documentation,
commissioning tests and inspection
FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC itself does not provide any attestation of conformity. Independent certification bodies provide conformity
assessment services and, in some areas, access to IEC marks of conformity. IEC is not responsible for any
services carried out by independent certification bodies.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 62446-1 has been prepared by IEC technical committee 82: Solar
photovoltaic energy systems.
This first edition cancels and replaces IEC 62446 published in 2009. This edition constitutes a
technical revision.
This edition includes the following significant technical change with respect to
IEC 62446:2009:
– the scope has been expanded to include a wider range of system test and inspection
regimes to encompass larger and more complex PV systems.
– 6 – IEC 62446-1:2016 © IEC 2016
The text of this standard is based on the following documents:
FDIS Report on voting
82/1036/FDIS 82/1056A/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.
A list of all parts in the IEC 62446 series, published under the general title Photovoltaic (PV)
systems – Requirements for testing, documentation and maintenance, can be found on the
IEC website.
The committee has decided that the contents of this publication will remain unchanged until
the stability date indicated on the IEC website under "http://webstore.iec.ch" in the data
related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
IMPORTANT – The 'colour inside' logo on the cover page of this publication indicates
that it contains colours which are considered to be useful for the correct
understanding of its contents. Users should therefore print this document using a
colour printer.
IEC 62446-1:2016 © IEC 2016 – 7 –
INTRODUCTION
Grid connected PV systems are expected to have a lifetime of decades, with maintenance or
modifications likely at some point over this period. Building or electrical works in the vicinity of
the PV array are very likely, for example roof works adjacent to the array or modifications
(structural or electrical) to a home that has a PV system. The ownership of a system may also
change over time, particularly for systems mounted on buildings. Only by the provision of
adequate documentation at the outset can the long term performance and safety of the PV
system and works, on or adjacent to the PV system, be ensured.
This part of IEC 62446 is split into two sections:
• System documentation requirements – This section details the information that shall be
provided within the documentation provided to the customer following installation of a grid
connected PV system.
• Verification – This section provides the information expected to be provided following
initial (or periodic) verification of an installed system. It includes requirements for
inspection and testing.
This part of IEC 62446 references IEC TS 62548:2013, which is in the process of being
converted into an International Standard. It is envisaged that work on the second edition of
IEC 62446-1 will start when IEC 62548 is completed.
– 8 – IEC 62446-1:2016 © IEC 2016
PHOTOVOLTAIC (PV) SYSTEMS – REQUIREMENTS FOR TESTING,
DOCUMENTATION AND MAINTENANCE –
Part 1: Grid connected systems – Documentation,
commissioning tests and inspection
1 Scope
This part of IEC 62446 defines the information and documentation required to be handed over
to a customer following the installation of a grid connected PV system. It also describes the
commissioning tests, inspection criteria and documentation expected to verify the safe
installation and correct operation of the system. It can also be used for periodic retesting.
This part of IEC 62446 is written for grid connected PV systems that do not utilize energy
storage (e.g. batteries) or hybrid systems.
This part of IEC 62446 is for use by system designers and installers of grid connected solar
PV systems as a template to provide effective documentation to a customer. By detailing the
expected commissioning tests and inspection criteria, it is also intended to assist in the
verification/inspection of a grid connected PV system after installation and for subsequent re-
inspection, maintenance or modifications.
This part of IEC 62446 defines the different test regimes expected for different solar PV
system types to ensure that the test regime applied is appropriate to the scale, type and
complexity of the system in question.
NOTE This part of IEC 62446 does not address CPV (concentrating PV) systems, however many of the parts may
apply.
2 Normative references
The following documents, in whole or in part, are normatively referenced in this document and
are indispensable for its application. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any
amendments) applies.
IEC 60364-6, Low-voltage electrical installations – Part 6: Verification
IEC TS 62548:2013, Photovoltaic (PV) arrays – Design requirements
IEC 61730 (all parts), Photovoltaic (PV) module safety qualification
IEC 61557 (all parts), Electrical safety in low voltage distribution systems up to 1 000 V a.c.
and 1 500 V d.c. – Equipment for testing, measuring or monitoring of protective measures
IEC 61010 (all parts), Safety requirements for electrical equipment for measurement, control,
and laboratory use
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
IEC 62446-1:2016 © IEC 2016 – 9 –
3.1
AC module
PV module with an integrated inverter in which the electrical terminals are AC only
3.2
cable type
description of a cable to enable its rating and suitability for a particular use or environment to
be determined
Note 1 to entry: In many countries this is done via a code number (eg “H07RNF”).
3.3
data sheet
basic product description and specification
Note 1 to entry: Typically one or two pages. Not a full product manual.
3.4
inspection
examination of an electrical installation using all the senses in order to ascertain correct
selection and proper erection of electrical equipment
3.5
inverter
electric energy converter that changes direct electric current to single-phase or polyphase
alternating current
3.6
micro inverter
small inverter designed to be connected directly to one or two PV modules.
Note 1 to entry: A micro inverter will normally connect directly to the factory fitted module leads and be fixed to
the module frame or mounted immediately adjacent to the module.
3.7
module integrated electronics
any electronic device fitted to a PV module intended to provide control, monitoring or power
conversion functions
Note 1 to entry: Module integrated electronics may be factory fitted or assembled on site.
3.8
PV array
assembly of electrically interconnected PV modules, PV strings or PV sub-arrays.
3.9
PV cell
most elementary device that exhibits the photovoltaic effect, i.e the direct non-thermal
conversion of radiant energy into electrical energy
3.10
PV module
smallest complete environmentally protected assembly of interconnected PV cells
3.11
PV string
circuit of one or more series-connected PV modules
– 10 – IEC 62446-1:2016 © IEC 2016
3.12
PV string combiner box
junction box where PV strings are connected which may also contain overcurrent protection
devices, electronics and/or switch-disconnectors
3.13
I
MOD_MAX_OCPR
PV module maximum overcurrent protection rating determined by IEC 61730-2
Note 1 to entry: This is often specified by module manufacturers as the maximum series fuse rating.
3.14
reporting
recording of the results of inspection and testing
3.15
testing
implementation of measures in an electrical installation by means of which its effectiveness is
proved
Note 1 to entry: It includes ascertaining values by means of appropriate measuring instruments, said values not
being detectable by inspection.
3.16
verification
all measures by means of which compliance of the electrical installation to the relevant
standards is checked
Note 1 to entry: It comprises inspection, testing and reporting.
4 System documentation requirements
4.1 General
The purpose of Clause 4 is to list the minimum documentation that should be provided
following the installation of a grid connected PV system. This information will ensure key
system data is readily available to a customer, inspector or maintenance engineer. The
documentation includes basic system data and the information expected to be provided in the
operation and maintenance manual.
4.2 System data
4.2.1 Basic system information
As a minimum, the following basic system information shall be provided. This “nameplate”
information would typically be presented on the cover page of the system documentation
pack.
a) Project identification reference (where applicable).
b) Rated (nameplate) system power (kW DC or kVA AC).
c) PV modules and inverters – manufacturer, model and quantity.
d) Installation date.
e) Commissioning date.
f) Customer name.
g) Site address.
IEC 62446-1:2016 © IEC 2016 – 11 –
4.2.2 System designer information
As a minimum, the following information shall be provided for all bodies responsible for the
design of the system. Where more than one company has responsibility for the design of the
system, the following information should be provided for all companies together with a
description of their role in the project.
a) System designer, company.
b) System designer, contact person.
c) System designer, postal address, telephone number and e-mail address.
4.2.3 System installer information
As a minimum, the following information shall be provided for all bodies responsible for the
installation of the system. Where more than one company has responsibility for the
installation of the system, the following information should be provided for all companies
together with a description of their role in the project.
a) System installer, company.
b) System installer, contact person.
c) System installer, postal address, telephone number and e-mail address.
4.3 Wiring diagram
4.3.1 General
As a minimum, a single line wiring diagram shall be provided. This diagram shall be annotated
to include the information detailed in 4.3.2 to 4.3.6.
In general, it is expected that this information will be presented as annotations to the single
line wiring diagram. In some circumstances, typically for larger systems where space on the
diagram may be limited, this information may be presented in table form.
4.3.2 Array – General specifications
The wiring diagram or system specification shall include the following array design
information.
a) Module type(s).
b) Total number of modules.
c) Number of strings.
d) Number of modules per string.
e) Identify which strings connect to which inverter.
Where an array is split into sub-arrays, the wiring diagram shall show the array – sub-array
design and include all of the above information for each sub-array.
4.3.3 PV string information
The wiring diagram or system specification shall include the following PV string information.
a) String cable specifications – size and type.
b) String overcurrent protective device specifications (where fitted) – type and
voltage/current ratings.
c) Blocking diode type (if relevant).
– 12 – IEC 62446-1:2016 © IEC 2016
4.3.4 Array electrical details
The wiring diagram or system specification shall include the following array electrical
information (where fitted).
a) Array main cable specifications – size and type.
b) Array junction box / combiner box locations.
c) DC switch disconnector, location and rating (voltage / current).
d) Array overcurrent protective devices – type, location and rating (voltage / current).
e) Other array electronic protective circuitry (such as arc fault detection), if applicable – type,
location and rating.
4.3.5 AC system
The wiring diagram or system specification shall include the following AC system information.
a) AC isolator location, type and rating.
b) AC overcurrent protective device location, type and rating.
c) Residual current device location, type and rating (where fitted).
4.3.6 Earthing and overvoltage protection
The wiring diagram or system specification shall include the following earthing and
overvoltage protection information.
a) Details of all earth / bonding conductors – size and type. Including details of array frame
equipotential bonding cable where fitted.
b) Details of any connections to an existing Lightning Protection System (LPS).
c) Details of any surge protection device installed (both on AC and DC lines) to include
location, type and rating.
4.4 String layout
For systems with three or more strings, a layout drawing of the PV system showing how the
array is split and connected into strings shall be provided.
NOTE This is particularly useful for finding faults in larger systems and on building mounted arrays where access
to the rear of the modules is difficult.
4.5 Datasheets
As a minimum, datasheets shall be provided for the following system components.
a) Module datasheet for all types of modules used in system – to the requirements of
IEC 61730-1.
b) Inverter datasheet for all types of inverters used in system.
The provision of datasheets for other significant system components should also be
considered.
4.6 Mechanical design information
A data sheet for the array mounting system shall be provided. If the mounting structure was
custom engineered, include the relevant documentation.
4.7 Emergency systems
Documentation of any emergency systems associated with the PV system (fire alarms, smoke
alarms, etc). This information shall include both operation and design details.
IEC 62446-1:2016 © IEC 2016 – 13 –
4.8 Operation and maintenance information
Operation and maintenance information shall be provided and shall include, as a minimum,
the following items:
a) Procedures for verifying correct system operation.
b) A checklist of what to do in case of a system failure.
c) Emergency shutdown / isolation procedures.
d) Maintenance and cleaning recommendations (mechanical, civil & electrical) – if any.
e) Considerations for any future building works related to the PV array (e.g. roof works).
f) Warranty documentation for PV modules and inverters – to include starting date of
warranty and period of warranty.
g) Documentation on any applicable workmanship or weather-tightness warranties.
4.9 Test results and commissioning data
Copies of all test and commissioning data shall be provided. As a minimum, these shall
include the results from the verification tests detailed in Clause 5 of this standard.
5 Verification
5.1 General
Clause 5 provides the requirements for the initial and periodic verification of a grid connected
PV electrical installation. It references IEC 60364-6 where appropriate and also details
additional requirements or considerations.
Much of the verification of a grid connected PV system should be done with reference to
IEC 60364-6, which provides the requirements for initial and periodic verification of any
electrical installation.
Every installation of subsystems and components shall be verified with reference to
IEC 60364-6 during erection, as far as reasonably practicable, and on completion, before
being put into service by the user. Initial verification shall include comparison of the results
with relevant criteria to confirm that the requirements of IEC 60364 have been met.
For an addition or alteration to an existing installation, it shall be verified that the addition or
alteration complies with IEC 60364 and does not impair the safety of the existing installation.
Initial and periodic verifications shall be made by a skilled person, competent in verification.
NOTE 1 Typical verification test sheets are provided in Annexes A, B and C to this standard.
Initial verification takes place upon completion of a new installation or completion of additions
or of alterations to existing installations. Periodic verification shall determine, as far as
reasonably practicable, whether the installation and all its constituent equipment remain in a
satisfactory condition for use.
For a PV system, the interval between verifications shall be no longer than that required by
the AC electrical system that the PV system is connected to.
NOTE 2 In some countries the interval between verifications is stipulated by national regulations.
– 14 – IEC 62446-1:2016 © IEC 2016
5.2 Inspection
5.2.1 General
Inspection shall precede testing and shall normally be done prior to energizing the installation.
The inspection shall be done to the requirements of IEC 60364-6.
If wiring will not be readily accessible after the installation, wiring may need to be inspected
prior to or during installation works.
The following items, specific to grid connected PV systems, shall be included in the
inspection.
5.2.2 DC system – General
Inspection of the DC installation shall include at least verification that:
a) the DC system has been designed, specified and installed to the requirements of
IEC 60364 and IEC TS 62548:2013;
b) the maximum PV array voltage is suitable for the array location (IEC TS 62548:2013 and
local codes may dictate that installations above a certain voltage may only be placed in
certain locations);
c) all system components and mounting structures have been selected and erected to
withstand the expected external influences such as wind, snow, temperature and
corrosion;
d) roof fixings and cable entries are weatherproof (where applicable).
5.2.3 DC system – Protection against electric shock
Inspection of the DC installation shall include at least verification of the measures in place for
protection against electric shock:
a) Protective measure provided by extra low voltage (SELV / PELV) – yes / no.
b) Protection by use of class II or equivalent insulation adopted on the DC side – yes / no.
c) PV string and array cables have been selected and erected so as to minimize the risk of
earth faults and short-circuits. Typically achieved by the use of cables with protective and
reinforced insulation (often termed “double insulated”) – yes / no.
5.2.4 DC system – Protection against the effects of insulation faults
Inspection of the DC installation shall include at least verification of the measures in place for
protection against the effects of insulation faults, including the following:
a) Galvanic separation in place inside the inverter or on the AC side – yes / no.
b) Functional earthing of any DC conductor – yes / no.
Knowledge of the galvanic separation and functional earthing arrangements is necessary
in order to determine if the measures in place to protect against the effects of insulation
faults have been correctly specified.
c) That a PV Array Earth Insulation Resistance detection and alarm system is installed – to
the requirements of IEC TS 62548:2013.
NOTE 1 This is typically provided within the inverter.
d) That a PV Array Earth Residual Current Monitoring detection and alarm system is
installed – to the requirements of IEC TS 62548:2013.
NOTE 2 This is typically provided within the inverter.
IEC 62446-1:2016 © IEC 2016 – 15 –
5.2.5 DC system – Protection against overcurrent
Inspection of the DC installation shall include at least verification of the measures in place for
protection against overcurrent in the DC circuits:
a) For systems without string overcurrent protective device, verify that:
• I (the module maximum series fuse rating) is greater than the possible
MOD_MAX_OCPR
reverse current;
• string cables are sized to accommodate the maximum combined fault current from
parallel strings.
NOTE See IEC TS 62548:2013 for calculation of array reverse currents.
b) For systems with string overcurrent protective device, verify that:
• the string overcurrent protective devices are fitted and correctly specified to the
requirements of IEC TS 62548:2013.
c) For systems with array / sub-array overcurrent protective devices, verify that:
• the overcurrent protective devices are fitted and correctly specified to the requirements
of IEC TS 62548:2013.
The potential for the system inverter(s) to produce a DC back-feed into the PV array circuits
shall also be verified. It shall be verified that any back-feed current is lower than both the
module maximum fuse rating and the string cable ampere rating.
5.2.6 DC system – Earthing and bonding arrangements
Inspection of the DC installation shall include at least verification that:
a) where the PV system includes functional earthing of one of the DC conductors, the
functional earth connection has been specified and installed to the requirements of
IEC TS 62548:2013;
b) where a PV system has a direct connection to earth on the DC side, a functional earth
fault interrupter is provided to the requirements of IEC TS 62548:2013;
c) array frame bonding arrangements have been specified and installed to the requirements
of IEC TS 62548:2013;
NOTE Local codes may require different bonding arrangements.
d) where protective earthing and/or equipotential bonding conductors are installed, they are
parallel to, and bundled with, the DC cables.
5.2.7 DC system – Protection against the effects of lightning and overvoltage
Inspection of the DC installation shall include at least verification that:
a) to minimize voltages induced by lightning, the area of all wiring loops has been kept as
small as possible;
b) measures are in place to protect long cables (e.g. screening or the use of surge protective
devices, SPDs);
c) where SPDs are fitted, they have been installed to the requirements of
IEC TS 62548:2013.
5.2.8 DC system – Selection and erection of electrical equipment
Inspection of the DC installation shall include at least verification that:
a) the PV modules are rated for the maximum possible DC system voltage;
b) all DC components are rated
...
ba
SLOVENSKI SIST EN 62446-1
STANDARD junij 2016
Fotonapetostni sistemi – Zahteve za preskušanje, dokumentiranje in
vzdrževanje – 1. del: Sistemi, priključeni na omrežje – Dokumentacija,
prevzemni preskusi in nadzor
Photovoltaic (PV) systems – Requirements for testing, documentation and
maintenance – Part 1: Grid connected systems – Documentation, commissioning
tests and inspection
Systèmes photovoltaïques (PV) – Exigences pour les essais, la documentation et
la maintenance – Partie 1: Systèmes connectés au réseau électrique –
Documentation, essais de mise en service et examen
Photovoltaik (PV) Systeme – Anforderungen an Prüfung, Dokumentation und
Instandhaltung – Teil 1: Netzgekoppelte Systeme – Dokumentation,
Inbetriebnahmeprüfung und Prüfanforderungen
Referenčna oznaka
ICS 27.160 SIST EN 62466-1:2016 (sl)
Nadaljevanje na straneh II do III in od 1 do 42
© 2019-01. Slovenski inštitut za standardizacijo. Razmnoževanje ali kopiranje celote ali delov tega standarda ni dovoljeno.
SIST EN 62446-1 : 2016
NACIONALNI UVOD
Standard SIST EN 62446-1 (sl), Fotonapetostni sistemi – Zahteve za preskušanje, dokumentiranje in
vzdrževanje – 1. del: Sistemi, priključeni na omrežje – Dokumentacija, prevzemni preskusi in nadzor,
2016, ima status slovenskega standarda in je istoveten evropskemu standardu EN 62446-1 (en),
Photovoltaic (PV) systems – Requirements for testing, documentation and maintenance – Part 1: Grid
connected systems – Documentation, commissioning tests and inspection, 2016.
Ta standard nadomešča SIST EN 62446:2010.
NACIONALNI PREDGOVOR
Evropski standard EN 62446-1:2016 je pripravil tehnični odbor Evropskega komiteja za standardizacijo
v elektrotehniki CLC/TC 82 Sončni fotonapetostni energetski sistemi. Slovenski standard SIST EN
62446-1:2016 je prevod evropskega standarda EN 62446-1:2016. V primeru spora glede besedila
slovenskega prevoda v tem standardu je odločilen izvirni evropski standard v angleškem jeziku.
Slovensko izdajo standarda je pripravil tehnični odbor SIST/TC PVS Fotonapetostni sistemi.
Odločitev za privzem tega standarda je v juniju 2016 sprejel tehnični odbor SIST/TC PVS Fotonapetostni
sistemi.
ZVEZE S STANDARDI
S privzemom tega evropskega harmonizacijskega dokumenta veljajo za omejeni namen referenčnih
standardov vsi standardi, navedeni v izvirniku, razen tistih, ki so že sprejeti v nacionalno standardizacijo:
SIST HD 60364-6 Nizkonapetostne električne inštalacije – 6. del: Preverjanje
SIST EN 61010 (skupina) Varnostne zahteve za električno opremo za meritve, nadzorovanje
in laboratorijsko uporabo
SIST EN 61557 (skupina) Električna varnost v nizkonapetostnih razdelilnih sistemih za
izmenične napetosti do 1 kV in enosmerne napetosti do 1,5 kV –
Oprema za preskušanje, merjenje ali nadzorovanje zaščitnih
ukrepov
SIST EN 61730 (skupina) Varnostne zahteve fotonapetostnih (PV) modulov
OSNOVA ZA IZDAJO STANDARDA
– privzem standarda EN 62446-1:2016
PREDHODNA IZDAJA
– SIST EN 62446:2010, Fotonapetostni sistemi, priključeni na omrežje – Minimalne zahteve za
sistemsko dokumentacijo, prevzemne preskuse in nadzor (IEC 62446:2009)
OPOMBE
– Povsod, kjer se v besedilu standarda uporablja izraz “evropski standard”, v EN 62446-1:2016 to
pomeni “slovenski standard”.
– Nacionalni uvod in nacionalni predgovor nista sestavni del standarda.
II
SIST EN 13108-7 : 2017
– Ta nacionalni dokument je istoveten EN 62446-1:2016 in je objavljen z dovoljenjem
CEN/CENELEC
Upravni center
Avenue Marnix 17
B-1000 Bruselj
This national document is identical with EN 62446-1:2016 and is published with the permission of
CEN/CENELEC
Management Centre
Avenue Marnix 17
B -1000 Brussels
III
SIST EN 62446-1 : 2016
(prazna stran)
IV
EVROPSKI STANDARD EN 62446-1
EUROPEAN STANDARD
NORME EUROPÉENNE
april 2016
EUROPÄISCHE NORM
ICS 27.160 Nadomešča EN 62446:2009
Slovenska izdaja
Fotonapetostni sistemi – Zahteve za preskušanje, dokumentiranje in
vzdrževanje – 1. del: Sistemi, priključeni na omrežje – Dokumentacija,
prevzemni preskusi in nadzor
Photovoltaic (PV) systems – Systèmes photovoltaïques (PV) - Photovoltaik (PV) Systeme –
Requirements for testing, Exigences pour les essais, la Anforderungen an Prüfung,
documentation and maintenance – documentation et la maintenance - Dokumentation und
Part 1: Grid connected systems – Partie 1: Systèmes connectés au Instandhaltung – Teil 1:
Documentation, commissioning réseau électrique – Netzgekoppelte Systeme –
tests and inspection Documentation, essais de mise en Dokumentation,
service et examen Inbetriebnahmeprüfung und
Prüfanforderungen
Ta evropski standard je CENELEC sprejel dne 23. februarja 2016. Člani CENELEC morajo izpolnjevati
določila poslovnika CEN/CENELEC, s katerim je predpisano, da mora biti ta standard brez kakršnihkoli
sprememb sprejet kot nacionalni standard.
Seznami najnovejših izdaj teh nacionalnih standardov in njihovi bibliografski podatki so na voljo pri
Upravnem centru CEN-CENELEC ali članih CENELEC.
Evropski standardi obstajajo v treh izvirnih izdajah (nemški, angleški in francoski). Izdaje v drugih jezikih,
ki jih člani CENELEC na lastno odgovornost prevedejo in izdajo ter prijavijo pri Upravnem centru CEN-
CENELEC, veljajo kot uradne izdaje.
Člani CENELEC so nacionalni elektrotehniški komiteji Avstrije, Belgije, Bolgarije, Cipra, Češke
republike, Danske, Estonije, Finske, Francije, Grčije, Hrvaške, Irske, Islandije, Italije, Latvije, Litve,
Luksemburga, Madžarske, Malte, Nekdanje jugoslovanske republike Makedonije, Nemčije,
Nizozemske, Norveške, Poljske, Portugalske, Romunije, Slovaške, Slovenije, Španije, Švedske, Švice,
Turčije in Združenega kraljestva.
CENELEC
Evropski komite za standardizacijo v elektrotehniki
European Committee for Electrotechnical Standardisation
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
Upravni center CEN-CENELEC: Avenue Marnix 17, B-1000 Bruselj
© 2016 CENELEC Lastnice vseh oblik avtorskih pravic so vse države članice CENELEC. Ref. oznaka EN 62446-1:2016 E
SIST EN 62446-1 : 2016
VSEBINA Stran
Evropski predgovor . 5
Dodatek ZA (normativni): Normativna sklicevanja na mednarodne publikacije z njihovimi ustreznimi
evropskimi publikacijami . 6
Predgovor . 7
Uvod . 9
1 Področje uporabe . 10
2 Zveze s standardi . 10
3 Izrazi in definicije . 10
4 Zahteve za dokumentacijo sistema . 12
4.1 Splošno . 12
4.2 Podatki o sistemu . 12
4.2.1 Osnovne informacije o sistemu . 12
4.2.2 Informacije o načrtovalcu sistema . 12
4.2.3 Informacije o inštalaterju sistema . 13
4.3 Načrt ožičenja . 13
4.3.1 Splošno . 13
4.3.2 Fotonapetostno polje – splošne specifikacije . 13
4.3.3 Informacije o fotonapetostnem nizu . 13
4.3.4 Električne podrobnosti o polju . 13
4.3.5 Izmenični sistem . 14
4.3.6 Ozemljitev in prenapetostna zaščita . 14
4.4 Razpored nizov . 14
4.5 Seznami podatkov . 14
4.6 Informacije o mehanski izvedbi . 14
4.7 Sistemi za nujna stanja. 14
4.8 Informacije o delovanju in vzdrževanju . 14
4.9 Rezultati preskusov in podatki o prevzemu . 15
5 Preverjanje . 15
5.1 Splošno . 15
5.2 Pregled . 15
5.2.1 Splošno . 15
5.2.2 Enosmerni sistem – splošno . 16
5.2.3 Enosmerni sistem – zaščita pred električnim udarom . 16
5.2.4 Enosmerni sistem – zaščita pred učinki okvar izolacije . 16
5.2.5 Enosmerni sistem – zaščita pred nadtokom . 16
5.2.6 Enosmerni sistem – sestavi za ozemljitev in za izenačitev potencialov . 17
5.2.7 Enosmerni sistem – zaščita pred učinki strel in prenapetostmi . 17
5.2.8 Enosmerni sistem – izbira in namestitev električne opreme . 17
5.2.9 Izmenični sistem . 18
SIST EN 62446-1 : 2016
5.2.10 Označevanje in identifikacija . 18
5.3 Preskušanje . 18
5.3.1 Splošno . 18
5.3.2 Preskusni režimi in dodatni preskusi . 19
5.3.3 Preskusni režimi za sisteme z elektronskimi moduli . 19
5.3.4 Preskusni režim kategorije 1 – vsi sistemi . 20
5.3.5 Preskusni režim kategorije 2 . 21
5.3.6 Dodatni preskusi . 21
6 Preskusni postopki – kategorija 1 . 21
6.1 Preskus neprekinjenosti ozemljitvenih vodnikov in vodnikov za izenačitev potencialov . 21
6.2 Preskus polaritete . 22
6.3 Preskus kombinirane omarice fotonapetostnega niza . 22
6.4 Fotonapetostni niz – merjenje napetosti odprtih sponk tokokroga . 22
6.5 Fotonapetostni niz – merjenje toka . 23
6.5.1 Splošno . 23
6.5.2 Fotonapetostni niz – kratkostični preskus . 23
6.5.3 Fotonapetostni niz – preskus delovanja . 24
6.6 Funkcijski preskusi . 24
6.7 Preskus izolacijske upornosti fotonapetostnega polja . 25
6.7.1 Splošno . 25
6.7.2 Preskus izolacijske upornosti fotonapetostnega polja – preskusna metoda . 25
6.7.3 Izolacijska upornost fotonapetostnega polja – preskusni postopek . 26
7 Preskusni postopki – kategorija 2 . 27
7.1 Splošno . 27
7.2 Meritev krivulje I-V niza . 27
7.2.1 Splošno . 27
7.2.2 Meritev V in I s pomočjo krivulje I-V . 27
OC SC
7.2.3 Meritev krivulje I-V – tehnične lastnosti polja . 27
7.2.4 Meritev krivulje I-V – prepoznavanje hib ali zadev v zvezi z osenčenjem modulov/polj . 28
7.3 Postopek pregleda fotonapetostnega polja z infrardečo kamero . 29
7.3.1 Splošno . 29
7.3.2 Postopek IR-preskusa . 29
7.3.3 Tolmačenje rezultatov IR-preskusa . 29
8 Preskusni postopki – dodatni preskusi . 30
8.1 Napetost proti zemlji – uporovni ozemljeni sistemi . 30
8.2 Preskus blokirnih diod . 30
8.3 Fotonapetostno polje – preskus upornosti mokre izolacije . 31
8.3.1 Splošno . 31
8.3.2 Postopek preskusa mokre izolacije . 31
8.4 Ovrednotenje osenčenja . 31
9 Poročila o preverjanju . 32
SIST EN 62446-1 : 2016
9.1 Splošno . 32
9.2 Prvo preverjanje . 33
9.3 Periodično preverjanje . 33
Dodatek A (informativni): Vzorec certifikata o preverjanju . 34
Dodatek B (informativni): Vzorec poročila o pregledu . 35
Dodatek C (informativni): Vzorec poročila o preskusu fotonapetostnega polja . 38
Dodatek D (informativni): Tolmačenje oblik krivulje I-V . 39
D.1 Splošno . 39
D.2 Sprememba 1 – stopnice ali zareze v krivulji . 40
D.3 Sprememba 2 – majhen tok . 40
D.4 Sprememba 3 – nizka napetost . 41
D.5 Sprememba 4 – bolj okroglo koleno . 41
D.6 Sprememba 5 – plitvejši nagib v navpičnem odseku . 41
D.7 Sprememba 6 – strmejši nagib v vodoravnem odseku . 42
Slika 1: Primer diagrama sončnih poti . 32
Slika D.1: Oblike krivulje I-V . 39
Preglednica 1: Spremembe preskusnega režima za sisteme z elektronskimi moduli . 19
Preglednica 2: Najmanjša vrednost izolacijske upornosti – fotonapetostna polja do 10 kWp . 26
SIST EN 62446-1 : 2016
Evropski predgovor
Besedilo dokumenta 82/1036/FDIS, poznejše prve izdaje IEC 62446-1, ki ga je pripravil tehnični odbor
IEC/TC 82 Sistemi sončne fotonapetostne energije, je bilo predloženo v vzporedno glasovanje IEC-
CENELEC in ga je CENELEC sprejel kot EN 62446-1:2016.
Določena sta bila naslednja roka:
– zadnji datum, do katerega mora dokument dobiti status
nacionalnega standarda bodisi z objavo istovetnega besedila
ali z razglasitvijo (dop) 2016-11-23
– zadnji datum, ko je treba razveljaviti nacionalne standarde,
ki so z EN v nasprotju (dow) 2019-02-23
Ta dokument nadomešča EN 62446:2009.
Upoštevati je treba, da so nekateri elementi tega dokumenta lahko predmet patentnih pravic. CENELEC
[in/ali CEN] ni odgovoren za identifikacijo katerekoli ali vseh teh pravic.
Razglasitvena objava
Besedilo mednarodnega standarda IEC 62446-1:2016 je CENELEC odobril kot evropski standard brez
kakršnekoli spremembe.
SIST EN 62446-1 : 2016
Dodatek ZA
(normativni)
Normativna sklicevanja na mednarodne publikacije z njihovimi ustreznimi
evropskimi publikacijami
Za uporabo tega standarda so, v celoti ali delno, nujno potrebni spodaj navedeni dokumenti. Pri datiranih
dokumentih velja samo navedena izdaja. Pri nedatiranih dokumentih velja najnovejša izdaja dokumenta
(vključno z morebitnimi spremembami).
OPOMBA 1: Kadar je bila mednarodna publikacija spremenjena s skupnimi spremembami, označenimi z (mod), se uporablja
ustrezni EN/HD.
OPOMBA 2: Posodobljene informacije o zadnjih izdajah evropskih standardov, navedenih v tem dodatku, so na voljo na
naslovu: www.cenelec.eu.
Publikacija Leto Naslov EN/HD Leto
IEC 60364-6 – Nizkonapetostne električne HD 60364-6 –
inštalacije – 6. del: Preverjanje
Varnostne zahteve za električno
IEC 61010 skupina EN 61010 skupina
opremo za meritve, nadzor in
laboratorijsko uporabo
IEC 61557 skupina Električna varnost v EN 61557 skupina
nizkonapetostnih razdelilnih
sistemih izmenične napetosti do
1 kV in enosmerne napetosti do
1,5 kV – Oprema za preskušanje,
merjenje ali nadzorovanje zaščitnih
ukrepov
IEC 61730 skupina Varnostne zahteve fotonapetostnih EN 61730 skupina
(PV) modulov
IEC TS 62548 2013 Zahteve za načrtovanje – –
fotonapetostnih (PV) polj
SIST EN 62446-1 : 2016
MEDNARODNA ELEKTROTEHNIŠKA KOMISIJA
FOTONAPETOSTNI SISTEMI – ZAHTEVE ZA PRESKUŠANJE,
DOKUMENTIRANJE IN VZDRŽEVANJE –
1. del: Sistemi, priključeni na omrežje –
Dokumentacija, prevzemni preskusi in nadzor
PREDGOVOR
1. Mednarodna elektrotehniška komisija (IEC) je svetovna organizacija za standardizacijo, ki združuje vse nacionalne
elektrotehnične komiteje (nacionalni komiteji IEC). Cilj IEC je pospeševati mednarodno sodelovanje v vseh vprašanjih
standardizacije s področja elektrotehnike in elektronike. V ta namen poleg drugih aktivnosti izdaja mednarodne standarde,
tehnične specifikacije, tehnična poročila, javno dostopne specifikacije (PAS) in vodila (v nadaljevanju: publikacije IEC). Za
njihovo pripravo so odgovorni tehnični odbori; vsak nacionalni komite IEC, ki ga zanima obravnavana tema, lahko sodeluje
v tem pripravljalnem delu. Prav tako lahko v pripravi sodelujejo mednarodne organizacije ter vladne in nevladne ustanove,
ki so povezane z IEC. IEC deluje v tesni povezavi z mednarodno organizacijo za standardizacijo ISO skladno s pogoji,
določenimi v soglasju med obema organizacijama.
2. Uradne odločitve ali sporazumi IEC o tehničnih vprašanjih, pripravljeni v tehničnih odborih, kjer so prisotni vsi nacionalni
komiteji, ki jih tema zanima, izražajo, kolikor je mogoče, mednarodno soglasje o obravnavani temi.
3. Publikacije IEC imajo obliko priporočil za mednarodno uporabo ter jih kot takšne sprejmejo nacionalni komiteji IEC. Čeprav
IEC skuša zagotavljati natančnost tehničnih vsebin v publikacijah IEC. IEC ni odgovoren za način uporabe ali za možne
napačne interpretacije končnih uporabnikov.
4. Da bi se pospeševalo mednarodno poenotenje, so nacionalni komiteji IEC v svojih nacionalnih in regionalnih standardih
dolžni čim pregledneje uporabljati mednarodne standarde. Vsako odstopanje med standardom IEC in ustreznim nacionalnim
ali regionalnim standardom je treba v slednjem jasno označiti.
5. IEC sam ne izvaja potrjevanja skladnosti. Storitve ugotavljanja skladnosti in na nekaterih območjih tudi dostop do znakov
skladnosti IEC izvajajo neodvisni certifikacijski organi. IEC ni določil nobenega postopka v zvezi z označevanjem kot znakom
strinjanja in ne prevzema nikakršne odgovornosti za storitve, ki jih izvajajo neodvisni certifikacijski organi. opremo, ki je
deklarirana, da ustreza kateremu od publikacij IEC.
6. Vsi uporabniki naj bi si zagotovili zadnjo izdajo teh publikacij.
7. IEC ali njegovi direktorji, zaposleni, uslužbenci ali agenti, vključno s samostojnimi strokovnjaki ter člani tehničnih odborov in
nacionalnih komitejev IEC, ne prevzemajo nobene odgovornosti za kakršnokoli osebno poškodbo, škodo na premoženju ali
katerokoli drugo škodo kakršnekoli vrste, bodisi posredne ali neposredne, ali za stroške (vključno z zakonitim lastništvom) in
izdatke, povezane s publikacijo, njeno uporabo ali zanašanjem na to publikacijo IEC ali katerokoli drugo publikacijo IEC.
8. Posebno pozornost je treba posvetiti normativnim virom, na katere se sklicuje ta publikacija. Uporaba navedenih publikacij
je nujna za pravilno uporabo te publikacije.
9. Opozoriti je treba na možnost, da bi lahko bil kateri od elementov tega mednarodnega standarda predmet patentnih pravic.
IEC ne odgovarja za identifikacijo nobene od teh patentnih pravic.
Mednarodni standard IEC 62446-1 je pripravil tehnični odbor IEC/TC 82 Sončni fotonapetostni
energetski sistemi.
Ta prva izdaja razveljavlja in nadomešča IEC 62446, izdan leta 2009. Ta izdaja vključuje tehnično
revizijo.
Ta izdaja vsebuje naslednje pomembne tehnične spremembe glede na IEC 62446:2009:
‒ področje uporabe je razširjeno z vključitvijo obsežnega sistema preskusov in režimov pregleda, da
bi bili zajeti večji in kompleksnejši fotonapetostni sistemi.
Besedilo tega standarda temelji na naslednjih dokumentih:
FDIS Poročilo o glasovanju
82/1036/FDIS 82/1056A/RVD
SIST EN 62446-1 : 2016
Celotna informacija o glasovanju za sprejetje tega standarda je na voljo v poročilu o glasovanju,
navedenem v gornji preglednici.
Ta dokument je bil pripravljen v skladu z Direktivami ISO/IEC, 2. del.
Seznam vseh delov skupine standardov IEC 62446 pod splošnim naslovom Fotonapetostni sistemi –
Zahteve za preskušanje, dokumentiranje in vzdrževanje je na voljo na spletni strani IEC.
Tehnični odbor je sklenil, da bo vsebina tega standarda ostala nespremenjena do datuma, določenega
za zaključek periodičnega pregleda, ki je določen na spletni strani IEC "http://webstore.iec.ch" pri
podatkih za to publikacijo. Po tem datumu bo publikacija:
– ponovno potrjena,
– razveljavljena,
– zamenjana z novo izdajo ali
– dopolnjena.
POMEMBNO: Logotip "v barvah" na platnicah te publikacije opozarja, da vsebuje barve, ki
so potrebne za pravilno razumevanje njene vsebine. Uporabniki naj zato tiskajo ta dokument
z barvnim tiskalnikom.
SIST EN 62446-1 : 2016
Uvod
Po pričakovanjih naj bi bila življenjska doba na omrežje priključenih fotonapetostnih sistemov nekaj
desetletij, seveda ob primernem vzdrževanju ali spremembah v tem obdobju. V tem času so zelo
verjetne gradnje ali električna dela v okolici fotonapetostnega polja, na primer dela na strehi v bližini
polja ali spremembe (gradbene ali električne) na samem fotonapetostnem sistemu. Prav tako se lahko
zamenja tudi lastništvo sistema, še posebej to velja za sisteme, nameščene na stavbah. Zato je za
dolgotrajno vzdrževanje in varnost fotonapetostnega sistema v obratovanju treba zagotoviti ustrezno
dokumentacijo.
Ta del IEC 62446 je razdeljen na dva dela:
— Zahteve za dokumentacijo sistema – podrobnosti v tem delu morajo uporabniku podati
informacije o fotonapetostnem sistemu, priključenem na omrežje;
— Preverjanje – ta del vsebuje informacije, pričakovane za prvo (ali periodično) preverjanje
nameščenega sistema. Vsebuje zahteve za pregled in preskušanje.
Ta del IEC 62446 se sklicuje na IEC TS 62548:2013, ki je v postopku pretvorbe v mednarodni standard.
Predvideva se, da se bo druga izdaja IEC 62446 začela pripravljati, ko bo končan IEC 62548.
SIST EN 62446-1 : 2016
FOTONAPETOSTNI SISTEMI – ZAHTEVE ZA PRESKUŠANJE,
DOKUMENTIRANJE IN VZDRŽEVANJE –
1. del: Sistemi, priključeni na omrežje –
Dokumentacija, prevzemni preskusi in pregled
1 Področje uporabe
Ta del IEC 62446 opredeljuje informacije in dokumentacijo, ki mora biti izročena uporabniku ob
prevzemu nameščenega in na omrežje priključenega fotonapetostnega sistema. Opisuje tudi
prevzemne preskuse, merila pregleda in dokumentacijo, pričakovano za preverjanje varnosti namestitve
in pravilnega delovanja sistema. Uporabi se lahko tudi pri periodičnih preskusih.
Ta del IEC 62446 je napisan za na omrežje priključene fotonapetostne sisteme, ki ne uporabljajo
hranilnikov energije (na primer baterij) ali hibridnih sistemov.
Ta del IEC 62446 uporabljajo načrtovalci in inštalaterji na omrežje priključenih sončnih fotonapetostnih
sistemov kot podlago, da je uporabniku izročena uporabna dokumentacija. Podrobnosti prevzemnih
preskusov in meril pregleda so namenjene tudi v pomoč pri preverjanju/pregledu na omrežje
priključenega fotonapetostnega sistema po namestitvi in pri poznejšem ponovnem pregledu,
vzdrževanju ali spremembah.
Ta del IEC 62446 določa različne preskusne režime za različne sončne fotonapetostne sisteme, da bi
se zagotovil ustrezen preskusni režim glede na konkretno izvedbo, tip in sestavo.
OPOMBA: Ta del IEC 62446 ni namenjen koncentriranim fotonapetostnim (CPV) sistemom, čeprav je kar nekaj delov
mogoče uporabiti tudi zanje.
2 Zveze s standardi
Za uporabo tega standarda so, delno ali v celoti, nujno potrebni spodaj navedeni referenčni dokumenti.
Pri datiranih sklicevanjih se uporablja le navedena izdaja. Pri nedatiranih sklicevanjih se uporablja
zadnja izdaja publikacije (vključno z dopolnili).
IEC 60364-6 Nizkonapetostne električne inštalacije – 6. del: Preverjanje
IEC TS 62548:2013 Fotonapetostna (PV) polja – Zahteve za načrtovanje
IEC 61730 (vsi deli) Varnostne zahteve fotonapetostnih (PV) modulov
IEC 61557 (vsi deli) Električna varnost v nizkonapetostnih razdelilnih sistemih za izmenične
napetosti do 1 kV in enosmerne napetosti do 1,5 kV – Oprema za preskušanje,
merjenje ali nadzorovanje zaščitnih ukrepov
IEC 61010 (vsi deli) Varnostne zahteve za električno opremo za meritve, nadzor in laboratorijsko
uporabo
3 Izrazi in definicije
V tem dokumentu so uporabljeni naslednji izrazi in definicije:
3.1
izmenični modul
fotonapetostni modul z vgrajenim razsmernikom, ki ima samo sponke z izmenično napetostjo
3.2
vrsta kabla
opis kabla z njegovimi naznačenimi lastnostmi, ki ustreza specifični rabi ali okolju
SIST EN 62446-1 : 2016
OPOMBA 1: V mnogih državah je to podano s kodno številko (na primer "H07RNF").
3.3
seznam podatkov
opis in specifikacije osnovnega proizvoda
OPOMBA: Po navadi sta to ena do dve strani in ne celoten priročnik o proizvodu.
3.4
pregled
preiskava električne inštalacije na vse načine, da se preverita pravilna izbira in ustrezna namestitev
električne opreme
3.5
razsmernik
razsmernik električne energije, ki spremeni enosmerni električni tok v enofazni ali večfazni izmenični tok
3.6
mikro razsmernik
majhen razsmernik, zasnovan za priključitev neposredno na enega ali dva fotonapetostna modula
OPOMBA: Mikro razsmernik je po navadi že v tovarni priključen neposredno na oba vodnika modula in pritrjen na okvir
modula ali nameščen takoj ob njem.
3.7
v modul vgrajena elektronika
vsaka na fotonapetostni modul prigrajena elektronska naprava, namenjena krmiljenju, nadzorovanju ali
močnostnim pretvornim funkcijam
OPOMBA: V modul vgrajena elektronika je lahko tovarniško prigrajena ali nameščena na kraju samem.
3.8
fotonapetostno polje
sestav električno med seboj povezanih fotonapetostnih modulov, fotonapetostnih nizov ali
fotonapetostnih podpolj
3.9
fotonapetostna celica
najbolj osnoven element, ki izkorišča fotonapetostni učinek, to je neposredno netermično pretvarjanje
sevane energije v električno energijo
3.10
fotonapetostni modul
najmanjši v celoti okoljsko zaščiten sestav med seboj povezanih fotonapetostnih celic
3.11
fotonapetostni niz
tokokrog enega ali več zaporedno priključenih fotonapetostnih modulov
3.12
kombinirana omarica fotonapetostnega niza
priključna doza, kjer so spojeni fotonapetostni nizi in v kateri so lahko tudi nadtokovne zaščitne naprave,
elektronika in/ali odklopni ločilniki
3.13
IMOD_MAX_OCPR
največja nadtokovna zaščita fotonapetostnega modula, določena v IEC 61730-2
OPOMBA: To vrednost pogosto določijo proizvajalci modulov kot največjo vrednost zaporedno vezane varovalke.
SIST EN 62446-1 : 2016
3.14
poročanje
zapis rezultatov pregledovanja in preskušanja
3.15
preskušanje
uporaba ukrepov na električni inštalaciji, s katerimi se dokazuje njena učinkovitost
OPOMBA: Preskušanje obsega uporabo ustreznih merilnih instrumentov za ugotavljanje vrednosti, ki jih ni mogoče ugotoviti
s pregledom.
3.16
preverjanje
vsi ukrepi, s katerimi se preverja skladnost električne inštalacije z ustreznimi standardi
OPOMBA: Preverjanje obsega pregled, preskušanje in poročanje.
4 Zahteve za dokumentacijo sistema
4.1 Splošno
Namen točke 4 je našteti minimalno dokumentacijo, ki naj se zagotovi po namestitvi na omrežje
priključenega fotonapetostnega sistema. Te informacije bodo uporabniku, pregledniku ali vzdrževalcu
zagotovile enostavno dostopne ključne podatke o sistemu. Dokumentacija vključuje osnovne podatke o
sistemu in informacije, ki morajo biti v priročniku za obratovanje in vzdrževanje.
4.2 Podatki o sistemu
4.2.1 Osnovne informacije o sistemu
O sistemu je treba zagotoviti vsaj naslednje osnovne informacije. Na naslovni strani dokumentacije o
sistemu bodo tipično predstavljene naslednje informacije z "naznačne ploščice":
a) referenčna identifikacija projekta (kjer se uporabi),
b) naznačena (naznačna ploščica) moč sistema (kW enosmerno ali kVA izmenično),
c) fotonapetostni moduli in razsmerniki – proizvajalec, tip in količina,
d) datum namestitve,
e) datum predaje v obratovanje,
f) ime stranke,
g) naslov lokacije.
4.2.2 Informacije o načrtovalcu sistema
Za vsak organ, odgovoren za načrtovanje sistema, je treba zagotoviti vsaj naslednje informacije. Kadar
je za načrtovanje sistema odgovornih več podjetij, naj se za vsako podjetje zagotovijo naslednje
informacije skupaj z navedbo njihove vloge v projektu:
a) načrtovalec sistema, podjetje,
b) načrtovalec sistema, kontaktna oseba,
c) načrtovalec sistema, poštni naslov, telefonska številka in naslov e-pošte.
SIST EN 62446-1 : 2016
4.2.3 Informacije o inštalaterju sistema
Za vsak organ, odgovoren za namestitev sistema, je treba zagotoviti vsaj naslednje informacije. Kadar
je za namestitev sistema odgovornih več podjetij, naj se za vsako podjetje zagotovijo naslednje
informacije skupaj z navedbo njihove vloge v projektu:
a) inštalater sistema, podjetje
b) inštalater sistema, kontaktna oseba
c) inštalater sistema, poštni naslov, telefonska številka in naslov e-pošte.
4.3 Načrt ožičenja
4.3.1 Splošno
Zagotoviti je treba vsaj enočrtni načrt ožičenja. V obrazložitvi tega načrta morajo biti vključene
informacije, podrobno opisane v 4.3.2 do 4.3.6.
Na splošno se pričakuje, da bodo te informacije predstavljene kot obrazložitev enočrtnega načrta
ožičenja. V nekaterih primerih, najpogosteje za velike sisteme, kjer je prostor na načrtu omejen, so lahko
te informacije podane tabelarično.
4.3.2 Fotonapetostno polje – splošne specifikacije
Načrt ožičenja ali specifikacija sistema mora vsebovati naslednje podatke o zasnovi polja:
a) tip(-i) modula(-ov),
b) skupno število modulov,
c) število nizov,
d) število modulov na niz,
e) podatki o tem, kateri niz je priključen na kateri razsmernik.
Če je polje razdeljeno na podpolja, mora načrt ožičenja prikazati shemo polje-podpolje in obsegati vse
zgoraj navedene informacije o vsakem podpolju.
4.3.3 Informacije o fotonapetostnem nizu
Načrt ožičenja ali specifikacija sistema mora vsebovati naslednje podatke o fotonapetostnem nizu:
a) specifikacije kabla niza – velikost in tip,
b) specifikacije nadtokovne zaščitne naprave niza (kjer je pritrjena) – tip in naznačena moč
(napetost/tok),
c) tip blokirne diode (če je ustrezno).
4.3.4 Električne podrobnosti o polju
Načrt ožičenja ali specifikacija sistema mora vključevati naslednje električne informacije o polju (kjer je
pritrjena):
a) specifikacije glavnega kabla polja – velikost in tip,
b) mesto priključne/kombinirane omarice polja,
c) mesto in naznačena moč (napetost/tok) enosmernega odklopnega ločilnika,
d) nadtokovne zaščitne naprave polja – tip, mesto in naznačena moč (napetost/tok),
SIST EN 62446-1 : 2016
e) druga elektronska zaščitna vezja polja (npr. zaznavanje okvarnega obloka), če so uporabljena –
tip, mesto in naznačena moč.
4.3.5 Izmenični sistem
Načrt ožičenja ali specifikacija sistema mora vsebovati naslednje informacije o izmeničnem sistemu:
a) mesto izmeničnega ločilnika, tip in naznačena moč,
b) mesto, tip in naznačena moč izmenične nadtokovne zaščitne naprave,
c) mesto naprave na preostali tok, tip in naznačena moč (kjer je uporabljena).
4.3.6 Ozemljitev in prenapetostna zaščita
Načrt ožičenja ali specifikacija sistema mora vsebovati naslednje informacije o ozemljitvi in
prenapetostni zaščiti:
a) podrobnosti o vseh ozemljitvenih vodnikih – velikost in tip. Kjer je to izvedeno, tudi podrobnosti o
kablu za izenačitev potencialov okvirja polja,
b) podrobnosti o vsaki povezavi na obstoječi sistem za zaščito pred delovanjem strele (LPS),
c) podrobnosti o vsaki nameščeni prenapetostni zaščitni napravi (na izmeničnih in enosmernih vodih),
vključno z mestom, tipom in naznačeno močjo.
4.4 Razpored nizov
Za sisteme s tremi ali več nizi mora biti narejen načrt razporeditve fotonapetostnega sistema, ki
prikazuje, kako je polje deljeno in povezano v nize.
OPOMBA: To je še posebej uporabno pri iskanju okvar na večjih sistemih in na poljih, nameščenih na stavbah, kjer je otežen
dostop do hrbtne strani modulov.
4.5 Seznami podatkov
Seznami podatkov o sistemskih komponentah morajo obsegati najmanj:
a) seznam podatkov za vse tipe modulov, uporabljene v sistemu – skladno z zahtevami IEC 61730-1,
b) seznam podatkov za vse tipe razsmernikov, uporabljene v sistemu.
Prouči naj se tudi možnost, da se zagotovi seznam drugih pomembnih podatkov o sistemskih
komponentah.
4.6 Informacije o mehanski izvedbi
Seznam podatkov o sistemu vgradnje polja mora biti zagotovljen. Če je vgradna struktura izvedena po
naročilu, mora seznam vsebovati ustrezno dokumentacijo.
4.7 Sistemi za nujna stanja
Zajemajo dokumentacijo vsakega sistema za nujna stanja, vezanega na fotonapetostni sistem (požarni
in dimni alarmi itd.). Ta informacija mora vsebovati podrobnosti o delovanju in izvedbi naprav.
4.8 Informacije o delovanju in vzdrževanju
Zagotoviti je treba informacije o delovanju in vzdrževanju, v katerih morajo biti vsaj naslednje postavke:
a) postopki za preverjanje pravilnega delovanja sistema,
b) kontrolni seznam, kaj se izvede v primeru odpovedi sistema,
SIST EN 62446-1 : 2016
c) postopki zaustavitve/ločevanja v izrednih razmerah,
d) priporočila za vzdrževanje in čiščenje (mehansko, gradbeniško in elektriško) – če sploh,
e) nasveti za vsa prihodnja gradbena dela v zvezi s fotonapetostnim poljem (npr. dela na strehi),
f) garancijska dokumentacija za fotonapetostne module in razsmernike – vključno z datumom
začetka veljavnosti garancije in trajanjem garancije,
g) dokumentacija o vseh garancijah glede izvedenih obrtniških del ali o odpornosti tesnjenja proti
vremenskim pojavom.
4.9 Rezultati preskusov in podatki o prevzemu
Zagotoviti je treba kopije vseh podatkov o preskusih in predajah v obratovanje. Vsebovati morajo vsaj
rezultate preskusov pri preverjanju, ki so podrobno obdelani v točki 5 tega standarda.
5 Preverjanje
5.1 Splošno
V točki 5 so navedene zahteve za prvo in periodično preverjanje fotonapetostne električne inštalacije,
priključene na omrežje. Kjer je primerno, se sklicuje na IEC 60364-6 ter tudi podrobno določa dodatne
zahteve ali nasvete.
Številna preverjanja na omrežje priključenih fotonapetostnih sistemov naj se izvedejo s sklicevanjem na
IEC 60364-6, ki navaja zahteve za prvo in periodično preverjanje katerekoli električne inštalacije.
Vsako namestitev podsistemov in komponent je treba preveriti s sklicevanjem na IEC 60364-6 med
namestitvijo, kolikor je le praktično smiselno, in po njeni izvedbi, še preden jo uporabnik preda v
obratovanje. Prvo preverjanje mora vključevati primerjavo rezultatov po ustreznih merilih, da potrdi, da
so izpolnjene zahteve iz IEC 60364.
Pri dodajanju k obstoječi inštalaciji ali njenem spreminjanju je treba preveriti, da je dodatek ali
sprememba v skladu z IEC 60364 in da ne bo poslabšala varnosti obstoječe inštalacije.
Prvo in periodično preverjanje mora izvajati strokovna oseba, kompetentna za preverjanje.
OPOMBA 1: Tipični obrazci za zapisovanje preskusov pri preverjanju so na voljo v dodatkih A, B in C tega standarda.
Prvo preverjanje poteka po dokončanju nove inštalacije ali dodatnih inštalacij ali sprememb obstoječih
inštalacij. Periodično preverjanje mora ugotoviti, kolikor je le praktično smiselno, ali ostajata inštalacija
in vsa njena sestavna oprema v zadovoljivem stanju za uporabo.
Za fotonapetostni sistem velja, da interval med preverjanji ne sme biti daljši od intervala, ki ga zahteva
izmenični električni sistem, na katerega je priključen.
OPOMBA 2: V nekaterih državah je interval med preverjanji pogodbeno določen z nacionalnimi predpisi.
5.2 Pregled
5.2.1 Splošno
Pregled mora biti izveden pred preskušanjem in mora biti normalno izveden pred priključitvijo inštalacije
pod napetost. Pregled mora biti izveden po zahtevah IEC 60364-6.
Če ožičenje po namestitvi inštalacije ne bo dostopno, ga je treba pregledati pred ali med inštalacijskimi
deli.
SIST EN 62446-1 : 2016
V pregled morajo biti vključene naslednje točke, ki so specifične za v omrežje priključene fotonapetostne
sisteme.
5.2.2 Enosmerni sistem – splošno
Pregled enosmerne inštalacije mora vsaj preveriti, da:
a) je bil enosmerni sistem zasnovan, specificiran in nameščen po zahtevah IEC 60364 in IEC TS
62548:2013;
b) najvišja napetost fotonapetostnega polja ustreza lokaciji polja (IEC TS 62548:2013 in lokalni
predpisi lahko določajo, da smejo biti inštalacije nad določeno napetostjo nameščene samo na
določenih lokacijah);
c) so bile vse komponente sistema in pritrdilne strukture izbrane in nameščene tako, da vzd
...










Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.
Loading comments...