Abstract

IEC 60965:2009 establishes requirements for the supplementary control points provided to enable the operating staff of nuclear power plants to shut down the reactor and maintain the plant in a safe shut-down state in the event that control of the safety functions can no longer be exercised from the main control room, due to unavailability of the main control room or its facilities. The main technical changes with regard to the previous edition are as follows:
- to clarify the definitions and review the requirements;
- to update the references to new IEC standards published since the first issue;
- to align the standard with new editions of the relevant IAEA documents.

Status
Published
Publication Date
15-Jul-2009
Current Stage
DELPUB - Deleted publication - 99 Deleted
Start Date
23-Feb-2016

Buy Documents

Standard

IEC 60965:2009 - Nuclear power plants - Control rooms - Supplementary control points for reactor shutdown without access to the main control room Released:7/16/2009

ISBN:9782889103
English and French language (34 pages)
sale 15% off
Preview
sale 15% off
Preview

Overview

IEC 60965:2009 is an international standard developed by the International Electrotechnical Commission (IEC) that establishes comprehensive requirements for supplementary control points (SCPs) in nuclear power plants. These supplementary control points enable operating staff to safely shut down nuclear reactors and maintain a safe shutdown state when the main control room (MCR) or its associated facilities become unavailable due to emergencies or unforeseen hazards. The standard encompasses design principles, safety requirements, human factors engineering, and verification guidelines to ensure that nuclear power plant operations remain safe and effective even under adverse conditions.

Key Topics

  • Supplementary Control Point (SCP) Requirements
    IEC 60965 outlines the functional design, location, and operational principles for SCPs to provide essential safety control when access to the main control room is lost.

  • Human-Machine Interface Design
    The standard emphasizes the application of human factors engineering principles, ensuring that interfaces are clear, intuitive, and effective for plant operators during emergencies.

  • Design Principles and Safety
    It details separation, redundancy, and environmental requirements for SCPs, ensuring their accessibility, reliability, and independence from the main control room’s systems.

  • Transfer of Control and Communication
    IEC 60965 specifies safe and reliable mechanisms for transferring operational authority from the MCR to the SCP, and mandates robust communication capabilities for coordination during emergencies.

  • Verification, Validation, and Documentation
    The standard requires systematic verification and validation processes, regular SCP testing, and well-documented procedures for both operation and maintenance.

Applications

IEC 60965:2009 is applicable across multiple nuclear power plant scenarios, providing practical value in ensuring operational resilience and regulatory compliance. Its use cases include:

  • Nuclear Power Plant Design and Upgrades
    The standard guides new NPP projects in integrating robust supplementary control points from concept development. For existing plants, it offers a framework for upgrades or modifications addressing new safety requirements.

  • Regulatory Licensing and Compliance
    IEC 60965 is essential for demonstrating adherence to international safety standards, facilitating regulatory review processes and licensing for plant operators and vendors.

  • Emergency Preparedness
    By establishing SCP guidelines, the standard ensures that plants are equipped for emergency scenarios that render the main control room unusable, supporting continued plant monitoring and safe shutdown.

  • Human Factors Optimization
    It directs the ergonomic and cognitive design of control interfaces at SCPs, helping operators perform critical actions efficiently under stress.

Related Standards

IEC 60965:2009 aligns with several internationally recognized standards and regulatory documents to ensure a comprehensive safety approach. Key related standards include:

  • IEC 60964: Nuclear power plants - Control rooms - Design
    Provides overall guidelines for designing main control rooms and their interfaces, to be read in conjunction with IEC 60965.

  • IEC 61226: Nuclear power plants - I&C important for safety - Classification
    Details classification principles for instrumentation and control (I&C) systems used at SCPs.

  • IEC 61513: Nuclear power plants - I&C for systems important to safety - General requirements
    Offers general requirements for I&C systems involved in critical safety functions.

  • IEC 60709: Nuclear power plants - I&C systems important to safety - Separation
    Addresses separation criteria to avoid common-cause failures between main and supplementary control points.

  • IEC 61771: Nuclear power plants - Main control room - Verification and validation of design
    Focuses on methods to verify and validate the design of control rooms and, by extension, supplementary control panels.

  • IAEA NS-R-1 and NS-G-1.3:
    International Atomic Energy Agency documents that establish safety objectives and guidance specifically referenced and aligned with IEC 60965:2009.

Practical Value

Implementing IEC 60965:2009 ensures that nuclear power plants are equipped with reliable, independently functional supplementary control systems, enhancing safety and operational integrity during control room inaccessibility. By referencing IEC 60965, plant designers, operators, and regulators can adopt internationally recognized best practices, optimize operator performance, and maintain compliance with evolving safety requirements in the nuclear energy sector.

Relations

Effective Date
05-Sep-2023

Buy Documents

Standard

IEC 60965:2009 - Nuclear power plants - Control rooms - Supplementary control points for reactor shutdown without access to the main control room Released:7/16/2009

ISBN:9782889103
English and French language (34 pages)
sale 15% off
Preview
sale 15% off
Preview

Get Certified

Connect with accredited certification bodies for this standard

DNV

DNV is an independent assurance and risk management provider.

NA Norway Verified

Lloyd's Register

Lloyd's Register is a global professional services organisation specialising in engineering and technology.

UKAS United Kingdom Verified

DNV Energy Systems

Energy and renewable energy certification.

NA Norway Verified

Sponsored listings

Frequently Asked Questions

IEC 60965:2009 is a standard published by the International Electrotechnical Commission (IEC). Its full title is "Nuclear power plants - Control rooms - Supplementary control points for reactor shutdown without access to the main control room". This standard covers: IEC 60965:2009 establishes requirements for the supplementary control points provided to enable the operating staff of nuclear power plants to shut down the reactor and maintain the plant in a safe shut-down state in the event that control of the safety functions can no longer be exercised from the main control room, due to unavailability of the main control room or its facilities. The main technical changes with regard to the previous edition are as follows: - to clarify the definitions and review the requirements; - to update the references to new IEC standards published since the first issue; - to align the standard with new editions of the relevant IAEA documents.

IEC 60965:2009 establishes requirements for the supplementary control points provided to enable the operating staff of nuclear power plants to shut down the reactor and maintain the plant in a safe shut-down state in the event that control of the safety functions can no longer be exercised from the main control room, due to unavailability of the main control room or its facilities. The main technical changes with regard to the previous edition are as follows: - to clarify the definitions and review the requirements; - to update the references to new IEC standards published since the first issue; - to align the standard with new editions of the relevant IAEA documents.

IEC 60965:2009 is classified under the following ICS (International Classification for Standards) categories: 27.120.20 - Nuclear power plants. Safety. The ICS classification helps identify the subject area and facilitates finding related standards.

IEC 60965:2009 has the following relationships with other standards: It is inter standard links to IEC 60965:2016. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.

IEC 60965:2009 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)


IEC 60965 ®
Edition 2.0 2009-07
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Nuclear power plants – Control rooms – Supplementary control points for
reactor shutdown without access to the main control room

Centrales nucléaires de puissance – Salles de commande – Points de
commande supplémentaires pour l’arrêt des réacteurs sans accès à la salle de
commande principale (salle de commande de repli)

All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form or by
any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from either IEC or
IEC's member National Committee in the country of the requester.
If you have any questions about IEC copyright or have an enquiry about obtaining additional rights to this publication,
please contact the address below or your local IEC member National Committee for further information.

Droits de reproduction réservés. Sauf indication contraire, aucune partie de cette publication ne peut être reproduite
ni utilisée sous quelque forme que ce soit et par aucun procédé, électronique ou mécanique, y compris la photocopie
et les microfilms, sans l'accord écrit de la CEI ou du Comité national de la CEI du pays du demandeur.
Si vous avez des questions sur le copyright de la CEI ou si vous désirez obtenir des droits supplémentaires sur cette
publication, utilisez les coordonnées ci-après ou contactez le Comité national de la CEI de votre pays de résidence.

IEC Central Office
3, rue de Varembé
CH-1211 Geneva 20
Switzerland
Email: inmail@iec.ch
Web: www.iec.ch
About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.

About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.
ƒ Catalogue of IEC publications: www.iec.ch/searchpub
The IEC on-line Catalogue enables you to search by a variety of criteria (reference number, text, technical committee,…).
It also gives information on projects, withdrawn and replaced publications.
ƒ IEC Just Published: www.iec.ch/online_news/justpub
Stay up to date on all new IEC publications. Just Published details twice a month all new publications released. Available
on-line and also by email.
ƒ Electropedia: www.electropedia.org
The world's leading online dictionary of electronic and electrical terms containing more than 20 000 terms and definitions
in English and French, with equivalent terms in additional languages. Also known as the International Electrotechnical
Vocabulary online.
ƒ Customer Service Centre: www.iec.ch/webstore/custserv
If you wish to give us your feedback on this publication or need further assistance, please visit the Customer Service
Centre FAQ or contact us:
Email: csc@iec.ch
Tel.: +41 22 919 02 11
Fax: +41 22 919 03 00
A propos de la CEI
La Commission Electrotechnique Internationale (CEI) est la première organisation mondiale qui élabore et publie des
normes internationales pour tout ce qui a trait à l'électricité, à l'électronique et aux technologies apparentées.

A propos des publications CEI
Le contenu technique des publications de la CEI est constamment revu. Veuillez vous assurer que vous possédez
l’édition la plus récente, un corrigendum ou amendement peut avoir été publié.
ƒ Catalogue des publications de la CEI: www.iec.ch/searchpub/cur_fut-f.htm
Le Catalogue en-ligne de la CEI vous permet d’effectuer des recherches en utilisant différents critères (numéro de référence,
texte, comité d’études,…). Il donne aussi des informations sur les projets et les publications retirées ou remplacées.
ƒ Just Published CEI: www.iec.ch/online_news/justpub
Restez informé sur les nouvelles publications de la CEI. Just Published détaille deux fois par mois les nouvelles
publications parues. Disponible en-ligne et aussi par email.
ƒ Electropedia: www.electropedia.org
Le premier dictionnaire en ligne au monde de termes électroniques et électriques. Il contient plus de 20 000 termes et
définitions en anglais et en français, ainsi que les termes équivalents dans les langues additionnelles. Egalement appelé
Vocabulaire Electrotechnique International en ligne.
ƒ Service Clients: www.iec.ch/webstore/custserv/custserv_entry-f.htm
Si vous désirez nous donner des commentaires sur cette publication ou si vous avez des questions, visitez le FAQ du
Service clients ou contactez-nous:
Email: csc@iec.ch
Tél.: +41 22 919 02 11
Fax: +41 22 919 03 00
IEC 60965 ®
Edition 2.0 2009-07
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Nuclear power plants – Control rooms – Supplementary control points for
reactor shutdown without access to the main control room

Centrales nucléaires de puissance – Salles de commande – Points de
commande supplémentaires pour l’arrêt des réacteurs sans accès à la salle de
commande principale (salle de commande de repli)
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
PRICE CODE
INTERNATIONALE
Q
CODE PRIX
ICS 27.120.20 ISBN 978-2-88910-354-6
– 2 – 60965 © IEC:2009
CONTENTS
FOREWORD.3
INTRODUCTION.5
1 Scope.7
2 Normative references .7
3 Terms and definitions .8
4 Abbreviations .9
5 Design principles.9
5.1 General .9
5.2 Main objectives .9
5.3 Safety principles.10
5.4 Human factors engineering principles.12
6 Design process.12
7 Functional design .13
7.1 General .13
7.2 Human factors.13
7.3 Location and access route.13
7.4 SCP environment .14
7.5 Space and configuration.14
7.6 Information and control equipment .14
7.7 Communication systems.15
7.8 Other equipment.15
8 System verification and validation.15
Bibliography.16

60965 © IEC:2009 – 3 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
NUCLEAR POWER PLANTS –
CONTROL ROOMS –
SUPPLEMENTARY CONTROL POINTS FOR REACTOR SHUTDOWN
WITHOUT ACCESS TO THE MAIN CONTROL ROOM

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any
equipment declared to be in conformity with an IEC Publication.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 60965 has been prepared by subcommittee 45A: Instrumentation
and control of nuclear facilities, of IEC technical committee 45: Nuclear instrumentation.
The text of this standard is based on the following documents:
FDIS Report on voting
45A/749/FDIS 45A/769/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.
This second edition cancels and replaces the first edition published in 1989. This edition
constitutes a technical revision.

– 4 – 60965 © IEC:2009
The main technical changes with regard to the previous edition are as follows:
• to clarify the definitions and review the requirements.
• to update the reference to new standards published since the first issue, including
IEC 61227, IEC 61771, IEC 61772, IEC 61839, and IEC 62241.
• to align the Standard with the new revisions of IAEA documents NS-R-1 and NS-G-1.3.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.
The committee has decided that the contents of this publication will remain unchanged until
the maintenance result date indicated on the IEC web site under "http://webstore.iec.ch" in
the data related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
60965 © IEC:2009 – 5 –
INTRODUCTION
a) Technical background, main issues and organization of the standard
IEC 60965:1989 was developed to provide requirements relevant to the design of NPP
supplementary control points for reactor shutdown without access to the main control room.
The first edition of IEC 60965 has been used extensively within the nuclear industry. It was
however recognized that recent technical developments especially those which are based on
software technology should be incorporated. It was also recognized that the relationships with
the standard for the main control room (i.e. IEC 60964) and the derivative standards to that
standard (i.e. IEC 61227, IEC 61771, IEC 61772, IEC 61839, and IEC 62241) should be
clarified and conditioned.
This IEC standard specifically focuses on the functional design process of the supplementary
control points of an NPP. It is intended that the standard is used by NPP designers, design
authorities, vendors, utilities, and by licensors.
At the end of the current revision, at the FDIS stage, two further points were identified. These
are: (a) requirements should be included associated with regular testing of the SCP, and (b) a
theoretical assessment is needed of the time available during which the reactor will be safe
but unattended, in order to move from the MCR to the SCP and for the SCP to become
operational. However, since these points were not raised formally by any National Committee,
they are recorded in this introduction for development in the next revision.
b) Situation of the current standard in the structure of the IEC SC 45A standard series
IEC 60965 is the third level IEC SC 45A document tackling the issue of the design of
supplementary control points.
IEC 60965 is to be read in association with IEC 60964 for the design of the main control room
(including the derivative standards mentioned above) which is the appropriate IEC SC 45A
document providing guidance on operator controls, verification and validation of design,
application of visual display units, functional analysis and assignment, and alarm functions
and presentation.
For more details on the structure of the IEC SC 45A standard series, see item d) of this
introduction.
c) Recommendations and limitations regarding the application of this Standard
The purpose of this standard is to provide functional design requirements to be used in the
design of the supplementary control points of a nuclear power plant to meet safety
requirements.
This standard is intended for application to supplementary control points whose conceptual
design is initiated after the publication of this standard. The recommendations of the standard
may be used for refits, upgrades and modifications.
Aspects for which special recommendations have been provided in this Standard, in
accordance with Clauses 6.15 to 6.30 of IAEA NS-G-1.3, are:
• The definition of the MCR and plant design bases for which the supplementary control
points are to be used.
• Access by station staff to the supplementary control points in such emergencies.
• Assurance for the station staff that the environment at the supplementary control points is
safe when they are to be used.

– 6 – 60965 © IEC:2009
• Provision of information at the supplementary control points on the state of the reactor
critical functions.
• Transfer of control and indication functions from the main control room to the
supplementary control points in emergencies.
• Independence and separation of the cabling used by the supplementary control points
from that used by the main control room.
• Assurance that a safe shutdown state has been reached using the supplementary control
points.
• Communication facilities between the supplementary control points and to the station
management.
To ensure that the Standard will continue to be relevant in future years, the emphasis has
been placed on issues of principle, rather than specific technologies.
d) Description of the structure of the IEC SC 45A standard series and relationships
with other IEC documents and other bodies documents (IAEA, ISO)
The top-level document of the IEC SC 45A standard series is IEC 61513. It provides general
requirements for I&C systems and equipment that are used to perform functions important to
safety in NPPs. IEC 61513 structures the IEC SC 45A standard series.
IEC 61513 refers directly to other IEC SC 45A standards for general topics related to
categorization of functions and classification of systems, qualification, separation of systems,
defence against common cause failure, software aspects of computer-based systems,
hardware aspects of computer-based systems, and control room design. The standards
referenced directly at this second level should be considered together with IEC 61513 as a
consistent document set.
At a third level, IEC SC 45A standards not directly referenced by IEC 61513 are standards
related to specific equipment, technical methods, or specific activities. Usually these
documents, which make reference to second-level documents for general topics, can be used
on their own.
A fourth level extending the IEC SC 45A standard series, corresponds to the Technical
Reports which are not normative.
IEC 61513 has adopted a presentation format similar to the basic safety publication
IEC 61508 with an overall safety life-cycle framework and a system life-cycle framework and
provides an interpretation of the general requirements of IEC 61508-1, IEC 61508-2 and
IEC 61508-4, for the nuclear application sector. Compliance with IEC 61513 will facilitate
consistency with the requirements of IEC 61508 as they have been interpreted for the nuclear
industry. In this framework IEC 60880 and IEC 62138 correspond to IEC 61508-3 for the
nuclear application sector.
IEC 61513 refers to ISO as well as to IAEA 50-C-QA (now replaced by IAEA GS-R-3) for
topics related to quality assurance (QA).
The IEC SC 45A standards series consistently implements and details the principles and
basic safety aspects provided in the IAEA code on the safety of NPPs and in the IAEA safety
series, in particular the Requirements NS-R-1, establishing safety requirements related to the
design of Nuclear Power Plants, and the Safety Guide NS-G-1.3 dealing with instrumentation
and control systems important to safety in Nuclear Power Plants. The terminology and
definitions used by SC 45A standards are consistent with those used by the IAEA.

60965 © IEC:2009 – 7 –
NUCLEAR POWER PLANTS –
CONTROL ROOMS –
SUPPLEMENTARY CONTROL POINTS FOR REACTOR SHUTDOWN
WITHOUT ACCESS TO THE MAIN CONTROL ROOM

1 Scope
This International Standard establishes requirements for the supplementary control points
provided to enable the operating staff of nuclear power plants to shut down the reactor and
maintain the plant in a safe shut-down state in the event that control of the safety functions
can no longer be exercised from the main control room, due to unavailability of the main
control room or its facilities.
The standard also establishes requirements for the selection of functions, the design and
organisation of the human-machine interface, and the procedures which shall be used
systematically to verify and validate the functional design of the supplementary control points.
It is assumed that supplementary control points provided for shutdown operations from
outside the main control room would be unattended during normal plant conditions other than
for periodic testing. The requirements reflect the application of human engineering principles
as they apply to the human-machine interface during such periodic testing and during
abnormal plant conditions.
This standard does not cover special emergency response facilities (e.g. a technical support
centre) or facilities provided for radioactive waste handling. Detailed equipment design is also
outside the scope of the standard.
This standard follows the principles of IAEA Requirements NS-R-1 “Safety of Nuclear Power
Plants: Design” and IAEA Safety Guide NS-G-1.3 “Instrumentation and Control Systems
Important to Safety in Nuclear Power Plants”.
The purpose of this standard is to provide functional design requirements to be used in the
design of the supplementary control points of a nuclear power plant to meet safety
requirements.
This standard is intended for application to supplementary control points whose conceptual
design is initiated after the publication of this standard. If it is desired to apply it to existing
plants or designs, special care must be taken to ensure a consistent design basis. This
relates, for example, to factors such as the consistency between the supplementary control
points and the main control room, the ergonomic approach, the automation level and the
information technology.
2 Normative references
The following referenced documents are indispensable for the application of this document.
For dated references, only the edition cited applies. For undated references, the latest edition
of the referenced document (including any amendments) applies.
IEC 60709, Nuclear power plants – Instrumentation and control systems important to safety –
Separation
IEC 60964, Nuclear power plants – Control rooms – Design

– 8 – 60965 © IEC:2009
IEC 61226, Nuclear power plants – Instrumentation and control systems important for safety –
Classification of instrumentation and control functions
IEC 61513, Nuclear power plants – Instrumentation and control for systems important to
safety – General requirements for systems
IEC 61771, Nuclear power plants – Main control room – Verification and validation of design
IAEA NS-R-1:2000, Safety of nuclear power plants: Design
IAEA NS-G-1.3:2002, Instrumentation and Control Systems Important to Safety in Nuclear
Power Plants
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply. For other terms,
refer to the general terminology defined in IEC 60964, IEC 61513 and in the IAEA NUSS
programme, such as Safety Guide NS-G-1.3 or the safety glossary.
3.1
control room staff
a group of plant personnel stationed in the control room, which is responsible for achieving
the plant operational goals by controlling plant through the human-machine interface.
Typically, the control room staff consists of supervisory operators, and operators who actually
monitor plant and plant conditions and manipulate controls, but may also include those staff
members and experts who are authorised to be present in the control room, e.g. during long
lasting event sequences.
[IEC 60964, 3.4]
3.2
local control points (or facilities)
points (or facilities) located outside the control room where local operators perform control
activities
[IEC 60964, 3.17]
3.3
local operators
the operating staff that perform tasks outside the control room
[IEC 60964, 3.18]
3.4
operating staff
plant personnel working on shift to operate the plant. The operating staff includes the control
room staff, maintenance engineers, etc.
[IEC 60964, 3.20]
3.5
supplementary control point
a location from which limited plant control and/or monitoring can be carried out to accomplish
the safety functions identified by the safety analysis as required in the event of a loss of
ability to perform those functions from the main control room. The supplementary control point
may be a special control room, but in many cases comprises a set of control panels and
displays in switchgear rooms or similar areas.

60965 © IEC:2009 – 9 –
4 Abbreviations
I&C Instrumentation and Control
LCP Local Control Point
MCR Main Control Room
NPP Nuclear Power Plant
PIE Postulated Initiating Event
SCP Supplementary Control Points, Supplementary Control Point
V&V Verification and Validation
5 Design principles
5.1 General
Clause 6.75 of IAEA NS-R-1 states “Sufficient instrumentation and control equipment shall be
available, preferably at a single location (supplementary control room) that is physically and
electrically separate from the control room, so that the reactor can be placed and maintained
in a shut down state, residual heat can be removed, and the essential plant variables can be
monitored should there be a loss of ability to perform these essential safety functions in the
control room”.
Clauses 6.15 to 6.30 of IAEA NS-G-1.3 provide guidance on the requirements for
supplementary control rooms (‘SCP’ in this standard), including requirements associated with
the following:
• definition of the plant design bases that require use of the SCP (Clauses 6.17, 6.19, 6.20);
• location and configuration of the SCP to promote prompt mobilisation (Clause 6.29);
• qualified access path to the SCP, with hazard indication and suitable countermeasures
along this path (Clauses 6.27, 6.28);
• prevention of unauthorised access to or use of the SCP (Clause 6.21);
• safety functions of the MCR and SCP not affected by the same PIE, and independence of
the circuits associated with the SCP from those of the MCR (Clauses 6.20, 6.23);
• priority of control between the MCR and SCP, and transfer of control from the MCR to the
SCP (Clauses 6.18, 6.20, 6.24);
• manual control in the SCP accomplished by simple actions (Clause 6.22);
• displays and controls in the SCP similar to those in the MCR, to the extent possible
(Clause 6.22);
• consideration of the difference of purpose between the MCR and the SCP (Clause 6.25);
• if long-term use is envisaged, suitable facilities for habitability and workspace for tasks
(Clause 6.30).
5.2 Main objectives
The SCP shall be provided with the means to trip the reactor and bring the plant to a safe
shutdown state and maintain it in that state without access to the MCR. However, the SCP are
not required to perform all the other plant control and monitoring functions which are typically
performed in the MCR. According to the type of NPP and the detailed safety arguments,
provisions to cope with a predefined set of PIE could be integrated in the SCP.
The SCP are required if the conditions within the MCR are no longer within its operational
design bases, and in consequence are such that the MCR is no longer available. Possible
causes include a control room fire, the entry of excess smoke or a dangerous atmosphere to
the MCR, severe damage to the MCR or its cables such that safety functions cannot be
performed, major damage to the control room area, or major failure of control room facilities.

– 10 – 60965 © IEC:2009
The design basis PIE and sequences of events for which the SCP are necessary and intended
to be used shall be identified. This shall include identification and justification of the assumed
duration for which the SCP may be required.
Since events leading to unavailability of the MCR are very infrequent, it is anticipated that the
plant safety analysis will demonstrate that such events can only coincide with another
independent event in the plant at an acceptably low frequency; in particular, it is anticipated
that the primary coolant circuit will be intact. However, due account shall be taken of any plant
fault that may occur as a consequence of reactor trip and of any plant faults at shutdown that
are of sufficient frequency to coincide with use of the SCP. In particular, the design of the
SCP shall take account of the possible long-term unavailability of the MCR due to fire or other
reasons.
The criteria for use of the SCP shall be clearly stated in the plant operating procedures.
It shall be possible to determine the complete safety state of the plant from outside the MCR.
This should preferably be from the SCP.
From an operational viewpoint (e.g. to simplify operation and avoid misunderstanding), it is
preferable to have only one SCP. Care shall be taken, however, to meet safety requirements,
particularly requirements for redundancy and independence.
There should be full presentation ability at all SCP of any computer-based information display
and alarm system.
There shall be adequate time to reach the SCP before necessary actions are required as well
as sufficient equipment to provide necessary communication between all operating staff
involved in these actions and with on-site and off-site locations. Requirements are given in
7.7.
The layout of the instrumentation and the mode of presentation at the SCP shall provide the
operating staff with adequate information to assess the plant state and to supervise the
shutdown (and subsequent hold down) of the reactor, the long term cooling of the reactor core
and confinement of all radioactive substances.
The plant systems controlled from the SCP may be limited to those providing the safety
functions.
The SCP shall provide sufficient control over the safety functions to reach and maintain a safe
shutdown state, for the defined set of PIEs and conditions for which the MCR cannot be used.
The supervision and control provided at the SCP shall include the state of the safety functions
concerned and control of their initiation and termination, and the state of the related
fundamental safety functions (see IAEA NS-R-1, Clause 4.6).
Facilities for site security monitoring, plant access control and fire alarms which are normally
provided in the MCR shall also be provided in an independent location. This independent
location may be the SCP or may be a location that would not be affected by the same event
that causes the SCP to be used.
The design of SCP shall be consistent with the MCR design. The identification and design
process for the relevant controls and indications needed for the SCP shall follow the
requirements of IEC 60964, as summarised in Clause 6 of this standard.
5.3 Safety principles
The design basis of an NPP normally specifies the internal and external hazards to be taken
into account. The design shall ensure that such events are not able to make those functions
of the MCR and SCP (and local control points) required for safe shutdown, monitoring to

60965 © IEC:2009 – 11 –
ensure safe shutdown and critical functions control and monitoring, unusable or ineffective
simultaneously.
The functions of the SCP shall be classified in accordance with IEC 61226, with due account
being taken of the criteria described in 5.2 for the use of the SCP.
Equipment and systems shall be designed with a degree of redundancy in accordance with
their safety classification. Account shall also be taken of the need for functional isolation and
physical separation where safety and non-safety systems and redundant systems are brought
into close proximity (see IEC 60709).
Taking into account the postulated causes of unavailability of the MCR functions, the SCP
functions shall be so designed (and, if necessary, the SCP so located) that, even under
emergency conditions, the SCP are accessible by safe routes.
The design shall allow adequate time for control room staff to reach the SCP after the MCR
becomes unavailable. The actions and duration of unattended automatic operation of the
safety functions, after initiation at the MCR, up to the time when the SCP becomes
operational, should be shown to be satisfactory for this transfer. This shall allow time for
access control and time to assess the plant state at the SCP.
Facilities to disable MCR control and transfer control to the SCP shall be provided. These
facilities shall be classified according to the highest category of safety functions for which
control from the MCR could be disabled. They shall be demonstrated as highly reliable and, if
required, demonstrated to comply with the single failure criterion.
The control transfer facilities shall disable the MCR controls in order to ensure that a fire or
damage affecting the MCR cannot cause spurious control actions. The facilities shall also be
such as to avoid or minimize transients of the controlled variables during the transfer of
control, in both directions: from MCR to SCP and from SCP to MCR.
The control transfer facilities may be on the route from the MCR to the SCP, or at the SCP, or
in the MCR itself if analysis shows that this cannot lead to failure to accomplish the control
transfer or failure of control from the SCP. Where the facilities are located in the MCR,
additional means that do not involve the MCR should also be provided.
The SCP should include a means to identify the control status of the SCP and of the MCR
controls.
I&C systems shall be so designed to prevent simultaneous control of plant systems from both
the MCR and SCP.
I&C systems shall be so designed that there is an acceptably low probability of false signals
from the MCR elements of the systems affecting plant safety. I&C systems shall be so
designed that there is an acceptably low probability of false signals from the SCP elements of
the systems interfering with the supervision and control of plant from the MCR under normal
or abnormal conditions. Examples of design techniques to achieve these objectives are the
use of: transfer switches, coded signals, optical isolation links.
When an SCP is in use, actions taken from it shall have priority over any other manual control
actions, except when control has to be taken at a local control point.
The design of the SCP shall include provisions to prevent unauthorised access or use. The
means of control transfer shall also include provisions to prevent unauthorised transfer of
control from the MCR to the SCP and vice versa. Access to the SCP, and any attempt at
control transfer to the SCP, shall be indicated in the MCR.
The SCP shall be designed to minimise operator errors.

– 12 – 60965 © IEC:2009
The design shall include the provision of written instructions at the SCP for operation of:
• Plant systems and control devices.
• Information and recording systems.
• Communication equipment.
• Any other equipment to be operated from the SCP.
The operating procedures for actions to be taken from the SCP shall be simple and clear.
The SCP equipment shall be qualified for the environmental conditions applicable to the
design basis PIE and sequence of events for which the SCP are necessary and intended to be
used.
The designer shall specify the regular testing and inspection of the SCP equipment required
to meet the design principles.
The design shall permit regular training and practice in the use of the SCP without affecting
plant availability.
5.4 Human factors engineering principles
In order to provide an optimal assignment of functions which ensures maximum utilisation of
operator and system capabilities and to achieve the maximum plant safety, the design shall
pay particular attention to the human factors engineering principles and human characteristics
of personnel under emergency conditions, especially for immediate actions, i.e. actions to be
performed within a short time after mobilisation at the SCP.
If the safety analysis shows that long term occupation of the SCP may be necessary, means
shall be provided to ensure habitability (for example ventilation). Such provisions may not
need to meet the same requirements as specified for the MCR.
The human-machine interface in the SCP shall follow the same design rules as that for the
MCR.
Where multiple SCP and/or LCP are necessary, clear guidance shall be developed for the
use, staffing and co-ordination of activities involving these facilities. In addition, human
factors analysis shall be undertaken to demonstrate that the required tasks can be achieved
reliably and within the timescale assumed in the safety analysis.
If more than one SCP is necessary, for redundancy and separation alone (for example for two
similar plant trains, separated by a principal fire barrier), they should have matching layouts,
with clear identification of the plant items concerned, and should not be mirrored (see
IEC 60964).
6 Design process
A system approach shall be used for developing the SCP specification. This process should
parallel the design process for the MCR and should use similar procedures, criteria and
methods. More specifically, the following elements shall be applied to the SCP design and
documentation objectives and principles.
a) Define the design basis scenarios, their goals and failure criteria (see 5.2).
b) Develop the plant specific SCP functions consistent with the overall design basis.
c) Assign basic functions to operating staff or I&C systems and allocate them to operating
locations.
60965 © IEC:2009 – 13 –
d) Classify the SCP functions with respect to their importance to safety, and define the
corresponding design and qualification requirements.
e) Design the plant specific SCP consistent with the general principles given in Clause 5 of
IEC 60964.
f) Conduct a design concept verification (i.e. control room staff, SCP training and
procedures) and validation of the entire system (see Clause 8).
g) Finalise the SCP design specification based on the above (see Clause 7).
h) Complete the detailed design and conduct a final verification and validation on plant after
completion (see Clause 8).
NOTE The process described above should establish the list of the systems to be controlled from the SCP, and
their configuration, and the list of plant parameters to be monitored from the SCP.
7 Functional design
7.1 General
Because of the low frequency of use and the relatively small number of tasks which need to
be performed in the SCP, the design shall aim to achieve a minimum extent of equipment,
high reliability of functions and a configuration for easy and quick understanding.
7.2 Human factors
Anthropometric considerations, population stereotypes, intensity of audible signals, visual and
viewing angles as well as preference for analogue or digital indications shall be chosen
consistently with those for the MCR.
An adequate level of illumination shall be provided to ensure that visibility is sufficient for task
performance on a continuous basis without undue fatigue.
The auditory environment shall enable clear verbal communication to be held.
If working areas are provided for use over an extended time, means for adequate seated
operation, writing and document reference and document lay down should be provided.
If computer based information or control is used at the SCP, these shall function in a manner
closely matching and preferably in an identical way to that of similar controls and indications
in the MCR. Reliability and environmental considerations may require different equipment, but
corresponding and compatible operating sequences to those in the MCR shall be used.
7.3 Location and access route
The location of the SCP shall be chosen and the protection shall be designed so that no
sequence of events of any PIE can simultaneously affect the functions of both the SCP and
the MCR. This should include consideration of events that might affect them either directly or
by affecting the service systems that support the SCP and MCR, respectively.
Fire is an important hazard following which use of the SCP may be required, and an
assessment of the fire protection of the SCP and the human routes to them should be made
and should show accessibility to the SCP location. Similar assessments of all service
systems, with special reference to heating, ventilation and air conditioning systems, access
routes and cables, should be made for other design basis conditions for which the SCPs are
to be used. The assessment of the cable routes should demonstrate independence of the
SCP cables from the MCR cables.
It shall be possible to reach the SCP easily, safely and within the time allowed,
notwithstanding the need for access control. This shall be possible both from the MCR upon

– 14 – 60965 © IEC:2009
its evacuation and by routes avoiding the MCR and avoiding any other areas potentially
affected by hazards following which use of the SCP is required.
An indication of the potential hazards (e.g. fire) and suitable countermeasures (e.g. breathing
equipment) should be provided along the access route from the MCR to the SCP. Before an
SCP is to be accessed, it shall be possible for the operating staff to be assured that the
environment is safe for their access.
In order to alert all operating staff, particularly those who were off site when the MCR was
abandoned, it shall be clearly indicated that the MCR is unavailable and shall not be accessed
for control purposes until it is available again.
7.4 SCP environment
The environmental conditions at the SCP shall meet the requirements derived from the safety
analysis for normal and emergency conditions and shall take into account national rules,
including the security plan in the respective country.
For the design basis conditions requiring use of the SCP, the environmental conditions shown
by the safety analysis for the intended location of an SCP shall not exceed those for normal
unprotected human access. Where an SCP may be required for use in a beyond design basis
or severe accident condition, involving the national security plan, the location should be
shown to be suitable for normal human access in those conditions.
A battery powered emergency lighting system shall be continuously available even upon
failure of the normal system. The emergency system should provide sufficient illumination for
task performance on the basis of a limited operational period, which should be shown to meet
the requirements of the plant emergency plan.
7.5 Space and configuration
The SCP shall have sufficient space for:
• All necessary information and control equipment in a well-structured arrangement.
• Writing and laying down documents and procedures.
• Storage of documents and procedures.
• Communication equipment.
Spare space shall be included for additions and modifications.
The SCP configuration shall enable prompt mobilisation by the operating staff upon their
arrival at the SCP.
7.6 Information and control equipment
All information, displays, recording and control equipment shall be arranged and structured
according to their functions and priority in order to minimise the possibility of human errors
and shall operate in the same way as the related MCR interface.
Mimic diagrams may be used to improve the presentation of information.
Coding, labelling and grouping principles shall be consistent with those for the MCR.
Displays and controls shall be provided for safety functions as defined in 5.2. These displays
and controls shall be provided with a degree of redundancy in accordance with their safety
classification and design requirements.

60965 © IEC:2009 – 15 –
Where a single SCP
...