(Main)Rules for steam turbine thermal acceptance tests - Part 3: Thermal performance verification tests of retrofitted steam turbines
Rules for steam turbine thermal acceptance tests - Part 3: Thermal performance verification tests of retrofitted steam turbines
This part of IEC 60953 establishes a Supplementary Standard (SS) for thermal verification tests of retrofitted steam turbines. The rules given in this SS follow the guidance given in IEC 60953-0, hereinafter called the Reference Standard (RS) but contain amendments and supplements regarding guarantees and verification of the guarantees by thermal acceptance tests on retrofitted steam turbines. General principles for the preparation, performance, evaluation, comparison with guaranteed values and the determination of the measurement uncertainties of verification tests are given in this SS. This SS is applicable only when the retrofit involves some hardware change in the steam turbine equipment. Conversely, any modification on the cycle or any retrofit of other equipment of the power plant (e.g. boiler, feedwater heaters, etc.) is not covered by this SS.
Regeln für thermische Abnahmeprüfungen für Dampfturbinen - Teil 3: Thermische Leistungsangabenüberprüfung für modernisierte Dampfturbinen
Règles pour les essais thermiques de réception des turbines à vapeur - Partie 3: Essais de vérification des performances thermiques des turbines à vapeur rénovées
IEC 60953-3:2022 La présente partie établit une norme supplémentaire pour les essais de vérification thermique des turbines à vapeur modernisées. Les règles données dans le présent document suivent les directives données dans la CEI 60953-0, mais contiennent des amendements et des suppléments concernant les garanties et la vérification des garanties par des essais de réception thermique sur des turbines à vapeur modernisées. Les principes généraux pour la préparation, l’exécution, l’évaluation, la comparaison avec les valeurs garanties et la détermination des incertitudes de mesure des essais de vérification sont donnés dans le présent document. Le présent document ne s’applique que lorsque la mise à niveau implique un changement de matériel dans l’équipement de la turbine à vapeur. Inversement, toute modification du cycle ou toute modernisation d’autres équipements de la centrale (par exemple chaudière, chauffe-eau, etc.) n’est pas couverte par le présent document.
Pravila za preskuse toplotne sprejemljivosti parne turbine - 3. del: Preskusi preverjanja toplotne učinkovitosti naknadno vgrajenih parnih turbin (IEC 60953-3:2022)
Ta del standarda IEC 60953 določa dodatni standard (SS) za preskuse preverjanja toplotne učinkovitosti naknadno vgrajenih parnih turbin.
Pravila, podana v tem dodatnem standardu, sledijo smernicam iz standarda IEC 60953-0 (v nadaljevanju: referenčni standard (RS)), vendar vključujejo spremembe in dopolnitve v zvezi z jamstvi in preverjanjem jamstev s preskusi toplotne sprejemljivosti naknadno vgrajenih parnih turbin.
V tem dodatnem standardu so podana splošna načela za pripravo, delovanje, vrednotenje, primerjavo z zajamčenimi vrednostmi in ugotavljanje merilne negotovosti preskusov preverjanja.
Ta dodatni standard se uporablja le, kadar naknadna vgradnja vključuje zamenjavo strojne opreme v parni turbini. Nasprotno pa ta dodatni standard ne zajema morebitnih sprememb v ciklu ali morebitne naknadne vgradnje druge opreme elektrarne (npr. kotla, grelnikov napajalne vode itd.).
General Information
Relations
Standards Content (Sample)
SLOVENSKI STANDARD
01-november-2022
Nadomešča:
SIST EN 60953-3:2002
Pravila za preskuse toplotne sprejemljivosti parne turbine - 3. del: Preskusi
preverjanja toplotne učinkovitosti naknadno vgrajenih parnih turbin (IEC 60953-
3:2022)
Rules for steam turbine thermal acceptance tests - Part 3: Thermal performance
verification tests of retrofitted steam turbines (IEC 60953-3:2022)
Regeln für thermische Abnahmeprüfungen für Dampfturbinen - Teil 3: Thermische
Leistungsangabenüberprüfung für modernisierte Dampfturbinen (IEC 60953-3:2022)
Règles pour les essais thermiques de réception des turbines à vapeur - Partie 3: Essais
de vérification des performances thermiques des turbines à vapeur rénovées (IEC 60953
-3:2022)
Ta slovenski standard je istoveten z: EN IEC 60953-3:2022
ICS:
27.040 Plinske in parne turbine. Gas and steam turbines.
Parni stroji Steam engines
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
EUROPEAN STANDARD EN IEC 60953-3
NORME EUROPÉENNE
EUROPÄISCHE NORM September 2022
ICS 27.040 Supersedes EN 60953-3:2002
English Version
Rules for steam turbine thermal acceptance tests - Part 3:
Thermal performance verification tests of retrofitted steam
turbines
(IEC 60953-3:2022)
Règles pour les essais thermiques de réception des Regeln für thermische Abnahmeprüfungen für
turbines à vapeur - Partie 3: Essais de vérification des Dampfturbinen - Teil 3: Thermische
performances thermiques des turbines à vapeur rénovées Leistungsangabenüberprüfung für modernisierte
(IEC 60953-3:2022) Dampfturbinen
(IEC 60953-3:2022)
This European Standard was approved by CENELEC on 2022-08-24. CENELEC members are bound to comply with the CEN/CENELEC
Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the CEN-CENELEC
Management Centre or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CENELEC member into its own language and notified to the CEN-CENELEC Management Centre has the
same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Türkiye and the United Kingdom.
European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2022 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Ref. No. EN IEC 60953-3:2022 E
European foreword
The text of document 5/249/FDIS, future edition 2 of IEC 60953-3, prepared by IEC/TC 5 "Steam
turbines" was submitted to the IEC-CENELEC parallel vote and approved by CENELEC as
The following dates are fixed:
• latest date by which the document has to be implemented at national (dop) 2023-05-24
level by publication of an identical national standard or by endorsement
• latest date by which the national standards conflicting with the (dow) 2025-08-24
document have to be withdrawn
This document supersedes EN 60953-3:2002 and all of its amendments and corrigenda (if any).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC shall not be held responsible for identifying any or all such patent rights.
Any feedback and questions on this document should be directed to the users’ national committee. A
complete listing of these bodies can be found on the CENELEC website.
Endorsement notice
The text of the International Standard IEC 60953-3:2022 was approved by CENELEC as a European
Standard without any modification.
Annex ZA
(normative)
Normative references to international publications
with their corresponding European publications
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments)
applies.
NOTE 1 Where an International Publication has been modified by common modifications, indicated by (mod),
the relevant EN/HD applies.
NOTE 2 Up-to-date information on the latest versions of the European Standards listed in this annex is available
here: www.cenelec.eu.
Publication Year Title EN/HD Year
IEC 60953-0 - Rules for steam turbine thermal EN IEC 60953-0 -
acceptance tests - Part 0: Wide range of
accuracy for various types and sizes of
turbines
IEC 60953-3 ®
Edition 2.0 2022-07
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Rules for steam turbine thermal acceptance tests –
Part 3: Thermal performance verification tests of retrofitted steam turbines
Règles pour les essais thermiques de réception des turbines à vapeur –
Partie 3: Essais de vérification des performances thermiques des turbines à
vapeur rénovées
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
INTERNATIONALE
ICS 27.040 ISBN 978-2-8322-3974-2
– 2 – IEC 60953-3:2022 © IEC 2022
CONTENTS
FOREWORD . 8
INTRODUCTION . 10
1 Scope . 13
1.1 General . 13
1.2 Object . 13
1.3 Matters to be considered in the contract . 13
2 Normative references . 13
3 Units, symbols, terms and definitions . 14
3.1 General . 14
3.2 Symbols, units . 14
3.3 Subscripts, superscripts and definitions . 14
3.4 Guarantee parameters . 16
3.4.1 Guidance on guarantee parameters . 16
3.4.2 Thermal efficiency . 16
3.4.3 Heat rate . 16
3.4.4 Thermodynamic efficiency . 16
3.4.5 Steam rate . 16
3.4.6 Main steam flow capacity . 16
3.4.7 Power output . 16
3.4.8 Guarantee values for extraction and mixed-pressure turbines . 16
3.4.9 Thermal Load Capacity (for Nuclear applications) . 16
3.5 Additional guarantee parameters . 16
3.5.1 General . 16
3.5.2 Cylinder isentropic efficiency – expansion in superheated region . 16
3.5.3 Cylinder isentropic efficiency – expansion involving wet region . 17
3.5.4 Pressure loss . 19
3.5.5 Flow-passing capacity (FPC) . 19
4 Guiding principles . 19
4.1 Advance planning for test . 19
4.2 Preparatory agreements and arrangements for tests . 20
4.3 Planning of the test . 20
4.3.1 Time for verification tests . 20
4.3.2 Direction of acceptance tests . 21
4.4 Preparation of the tests . 21
4.4.1 Condition of the plant. 21
4.4.2 Condition of the steam turbine . 22
4.4.3 Condition of the condenser . 22
4.4.4 Isolation of the cycle . 22
4.4.5 Checks for leakage of condenser and feed water heaters . 22
4.4.6 Cleanliness of the steam strainers . 22
4.4.7 Checking of the test measuring equipment . 22
4.5 Comparison measurements . 22
4.6 Settings for test . 23
4.6.1 Load settings . 23
4.6.2 Special settings . 23
4.7 Preliminary tests . 23
4.8 Acceptance tests . 23
IEC 60953-3:2022 © IEC 2022 – 3 –
4.8.1 Constancy of test conditions . 23
4.8.2 Maximum deviation and fluctuation in test conditions . 23
4.8.3 Duration of test runs and frequency of reading . 23
4.8.4 Reading of integrating measuring instruments . 23
4.8.5 Alternative methods . 23
4.8.6 Recording of tests . 23
4.8.7 Additional measurement . 23
4.8.8 Preliminary calculations . 23
4.8.9 Consistency and number of tests . 24
4.9 Repetition of acceptance tests . 24
4.10 Guidance on retrofit guarantees . 24
4.10.1 General . 24
4.10.2 Absolute guarantees . 25
4.10.3 Relative guarantees . 26
5 Measuring techniques and measuring instruments . 27
5.1 Overview. 27
5.1.1 Instrument accuracy requirements . 27
5.1.2 Measuring instruments. 27
5.1.3 Measuring uncertainty . 27
5.1.4 Calibration of instruments . 27
5.1.5 Alternative instrumentation .
...
Questions, Comments and Discussion