Status
Not Published
Publication Date
22-Nov-2027
Current Stage
4098 - Decision to drop project - Standstill maintained / released - Enquiry
Start Date
17-Aug-2026

Buy Documents

Draft

prEN IEC 63409-6:2026 - BARVE

English language (55 pages)
Preview
Preview
e-Library read for
×1 day

prEN IEC 63409-6:2026 is a draft CLC/IEC document for photovoltaic power generating systems connected to the grid. It specifies test procedures for power conversion equipment (PCE) used in photovoltaic (PV) systems, with or without energy storage, to check power control functions and grid support behavior. It is aimed at manufacturers, test laboratories, and conformity assessment teams that need to verify how a PCE follows setpoints and reacts to grid changes.

What does prEN IEC 63409-6:2026 specify?

prEN IEC 63409-6:2026 specifies how to test the performance of power control functions in PCE for PV systems. Its focus is on test methods, measurement setup, and pass criteria based on the manufacturer’s declared tolerances.

The document is organized around general requirements in Clause 4, test procedures in Clause 5, and supporting annexes. Clause 5 covers both constant power control and response control against grid variation.

AnnexWhat it covers
Annex AExamples of testing environments, including power supply and measuring instrument specifications
Annex BNormative sign conventions for voltage, current, active power, and reactive power measurements
Annex CInfluence of MPPT control and PV simulator behavior on test results
Annex DGrid support functions in other standards, with chapter lists and abstracts

What are the key requirements of prEN IEC 63409-6:2026?

General test conditions

Clause 4 sets the basic test conditions that make results comparable. prEN IEC 63409-6:2026 allows tests to be performed in any order unless the document says otherwise, and the same sample does not have to be used for every test.

Clause 4.1.4 says all grid support functions except the one under test should be disabled. If another function must stay enabled to complete the test, the report has to note that fact. In practice, this helps isolate the behavior being checked and avoids ambiguous results.

Clause 4.2 requires the DC and AC ports of the EUT (equipment under test) to be connected to external supplies according to the manufacturer’s instructions. The document also requires measurement of apparent power, active power, and reactive power at the AC ports, using the sign conventions in Annex B. That matters because a reversed measurement direction changes the meaning of the result.

Clause 4.3 ties the tests to IEC 61850-7-4 and IEC 61850-7-420 logical nodes and data objects. The manufacturer has to declare the monitored parameters before testing, and the document lists status and measured values in Tables 1 and 2. This gives labs a common parameter map for setting and reading the PCE.

Constant power control

Clause 5.2 covers constant power control. It includes active power control, change of maximum active power configuration, and reactive power control in constant reactive power mode and constant power factor mode.

For active power control and maximum active power control, the test checks whether the output follows the commanded setpoint. The criterion is the error between the PCE setting and the measured value at the AC ports, within the allowable range declared by the manufacturer. In practice, this tells a buyer or certifier whether the unit can hold a commanded power limit accurately.

For constant reactive power control, the same approach applies to reactive power. Clause 5.2.4.1 uses the reactive power setpoint and compares it with the measured value at the AC ports, again against the manufacturer’s declared tolerance.

For constant power factor control, the document checks accuracy at the commanded power factor and also measures active power, reactive power, and power factor during changes. This matters for grid codes that require a specific displacement power factor over a range of operating points.

Response control against grid variation

Clause 5.3 covers response control functions that change output when frequency or voltage changes. The functions include frequency-watt control, voltage-watt control, voltage-var control, and power-reactive power/power factor control.

Clause 5.3.2 defines common procedures for frequency-watt, voltage-watt, and voltage-var testing. The tests use step changes in the independent variable, measure voltage, current, active power, apparent power, reactive power, and power factor, and record settling time. The tests are repeated at different output levels, including 100%, 66%, and 33% of rated active power. That shows whether the response is consistent across operating points.

Clause 5.3.2.3 bases acceptance on the manufacturer’s declared permissible range for the stabilized output and the settling time. In practice, the document does not impose one universal performance limit here; it requires the declared performance to be verified.

Clause 5.3.3 gives separate procedures for each response function using configured curves and parameters in Tables 10 to 19. The tests check curve behavior, ramp-rate limiting, settling time settings, and snapshot behavior where used. For example, the voltage-var, frequency-watt, voltage-watt, power-reactive power, and power factor functions are each tested against their configured characteristic curves.

Annex C is relevant to these tests because it explains that MPPT control and the choice of DC source can change transient-response results. For a lab, this means the DC supply type has to be recorded, and the test setup should avoid DC-side effects that distort the AC response.

What terms does prEN IEC 63409-6:2026 define?

  • battery energy storage system (BESS) - An electrical energy storage system based on batteries with secondary cells, including flow battery energy systems.
  • power conversion equipment (PCE) - An electrical device that converts one kind of electrical power into another with respect to voltage, current, and frequency.
  • step response time - The time from an input step change until the output first reaches a specified percentage of the final change.
  • settling time - The time from an input step change until the output stays within the specified tolerance band around steady state.
  • overshoot - The maximum transient deviation of the output from its final steady-state value.
  • dead time - The time interval by which the output is shifted relative to the input.

Who uses prEN IEC 63409-6:2026?

Manufacturers of PCE for PV systems use prEN IEC 63409-6:2026 to design validation and factory or type testing for control functions. Test laboratories use it to set up AC and DC supplies, measurement points, and pass/fail checks in a repeatable way.

Conformity assessment teams use it to check whether a PCE follows commanded active power, reactive power, and power factor settings, and whether it responds correctly to grid frequency or voltage changes. Grid-connection engineers and technical buyers use it when they need evidence that a PV inverter or similar PCE supports the required control modes.

The document is also relevant where PV systems include energy storage, because the procedures cover PCE with or without BESS and include cases where active power flow can be absorbing as well as generating.

What changed in prEN IEC 63409-6:2026 from the previous edition?

prEN IEC 63409-6:2026 supersedes IEC committee draft documents 82/2412/CD and 82/2458A/CC.

Which standards are used with prEN IEC 63409-6:2026?

  • IEC 60050-351:2013 - Provides control-technology terminology used for response time, settling time, overshoot, and dead time.
  • IEC TS 62786-1:2023 - Provides the general DER grid-connection requirements that the test items are aligned with.
  • IEC TS 61836 - Provides solar photovoltaic energy system terms, definitions, and symbols.
  • IEC 62934:2021 - Provides renewable-energy grid-integration terms and definitions.
  • IEC 61850-7-4:2010/AMD1:2020 - Provides the basic communication structure, logical node classes, and data object classes used for parameter setting and monitoring.
  • IEC 61850-7-420:2021 - Provides DER and distribution automation logical nodes and data objects used in the test procedures.

What does the prEN IEC 63409-6:2026 document contain?

The document contains step-by-step test procedures, parameter tables, and acceptance criteria for each control function. It also includes example figures for step response and test setup, plus curve-based procedures for voltage-var, frequency-watt, voltage-watt, power-reactive power, and power factor control.

Annex A gives example test environments and recommended capabilities for AC and DC power supplies and measuring instruments. Annex B explains the sign conventions and power-flow meanings needed to interpret measured voltage, current, active power, and reactive power correctly.

Annex C explains how PV simulator behavior and MPPT control can change transient results, which is important when comparing tests across labs. Annex D compares the grid support functions in this document with related functions in IEEE 1547-1, EN 50549-10, and AS/NZS 4777.2.

Buy Documents

Draft

prEN IEC 63409-6:2026 - BARVE

English language (55 pages)
Preview
Preview
e-Library read for
×1 day

Frequently Asked Questions

prEN IEC 63409-6:2026 is a draft published by CLC. Its full title is "Photovoltaic power generating systems connection with the grid - Testing of power conversion equipment - Part 6: Power control functions and grid support". This standard covers: Photovoltaic power generating systems connection with the grid - Testing of power conversion equipment - Part 6: Power control functions and grid support

Photovoltaic power generating systems connection with the grid - Testing of power conversion equipment - Part 6: Power control functions and grid support

prEN IEC 63409-6:2026 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)

Contents

  • 1 Scope
  • 2 Normative references
  • 3 Terms and definitions
  • 3.1 battery energy storage system
  • 3.2 power conversion equipment
  • 3.3 step response time
  • 3.4 settling time
  • 3.5 overshoot
  • 3.6 dead time
  • 3.7 tolerance band
  • 4 General requirements
  • 4.1 General conditions for testing
  • 4.2 Test setup
  • 4.3 Parameters used in the tests
  • 5 Test procedures
  • 5.1 Test items
  • 5.3 Response control against grid 4.7.3 Reactive power control modes DWPF
  • 5.3 Response control against grid 4.7.3 Reactive power control modes DWVR
  • 5.3 Response control against grid 4.6 Active power response to frequency DHFW/DLFW
  • 5.3 Response control against grid 4.7.4 Voltage related active power reduction DVWC
  • 5.3 Response control against grid 4.7.2 Voltage support by reactive power DVVR
  • 5.2 Constant power control
  • 5.3 Response control against grid variation
  • Annex A
  • 7 Table 1)
  • Annex B
  • 1 Consume (+) Consume (+) +
  • 2 Supply (-) Consume (+) -
  • 3 Supply (-) Supply (-) -
  • 4 Consume (+) Supply (-) +
  • 1 Output (+) Supply (+) +
  • 2 Input (-) Supply (+) -
  • 3 Input (-) Absorption (-) -
  • 4 Output (+) Absorption (-) +
  • Annex C
  • Annex D
  • 5.2 Autonomous 4.10 Connection 5.9 Connection and 3.2 Inverter demand
  • 5.6 Enter service
  • 5.4 Response 4.7.3 Reactive 5.5.2.5 Verification
  • 5.4 Response 4.7.3 Reactive 5.14.7 Test for active 5.5.2.5 Verification
  • 5.4 Response 4.6 Active power 5.15.2 Test for 5.4 Active response to 4.5.3 Sustained
  • 5.4 Response 4.7.4 Voltage 5.14.9 Test for 5.6 Voltage related 3.3.2 Volt response
  • 5.4 Response 4.7.2 Voltage 5.14.4 Test for 5.5.2.4 Verification 3.3.2.3 Volt–var
  • 5.4 Response control
  • 5.4 Response control 5.15.2 Test for [5.15.2]
  • 5.4 Response control 5.14.9 Test for voltage- [5.14.9]
  • 5.4 Response control 5.14.4 Test for voltage- [5.14.4]
  • 5.2 Autonomous 3.2 Inverter demand
  • 5.4 Response
  • 5.4 Response
  • 5.4 Response 4.5.3 Sustained
  • 5.4 Response 3.3.2.2 Volt response
  • 5.4 Response 3.3.2.3 Volt–var
  • Bibliography

INTRODUCTION Background TC82 has been making efforts to contribute to the standardization of DER connection with the grid. In 2016, TC82 joined TC8/JWG10 to standardize utility power system operation requirements. In parallel with this liaison work, TC82 has also been preparing the standardization of testing of grid connection requirements for power conversion equipment (PCE) for use in PV systems since 2016. Purpose This document proposes Part 6 of this series which gives test procedures for confirming power control functions and grid support of PCE.

Figure 1 gives an overview of the structure of the whole IEC 63409 series.

Figure 1 – Overview of IEC 63409 series

oSIST prEN IEC 63409-6:2026

PHOTOVOLTAIC POWER GENERATING SYSTEMS CONNECTION WITH THE GRID – TESTING OF POWER CONVERSION EQUIPMENT

PART 6: POWER CONTROL FUNCTIONS AND GRID SUPPORT

1 Scope

This part of IEC 63409 specifies test procedures for the evaluation of performance of power control functions of power conversion equipment (PCE) for use in photovoltaic (PV) power systems with or without energy storage. This document covers testing requirements of the following functions equipped with the PCE:

  • Constant power control
  • Active power control
  • Change of maximum active power configuration
  • Reactive power control (constant reactive power control, constant power factor control)
  • Response control
  • Active power response to frequency variations (frequency - watt control)
  • Active power response to voltage variations (voltage - watt control)
  • Reactive power response to voltage variations (voltage - var control)
  • Power - reactive power / power factor control

2 Normative references

The following documents are referred to in the text in such a way that some or all of their content constitutes requirements of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.

IEC 60050-351:2013, International Electrotechnical Vocabulary (IEV) - Part 901: Control technology IEC TS 62786-1:2023, Distributed energy resources connection with the grid – Part 1: General requirements IEC TS 61836, Solar photovoltaic energy systems - Terms, definitions and symbols IEC 62934:2021, Grid integration of renewable energy generation - Terms and definitions IEC 61850-7-4:2010/AMD1:2020, Amendment 1 - Communication networks and systems for power utility automation - Part 7-4: Basic communication structure - Compatible logical node classes and data object classes IEC 61850-7-420:2021, Communication networks and systems for power utility automation - Part 7-420: Basic communication structure - Distributed energy resources and distribution automation logical nodes

oSIST prEN IEC 63409-6:2026

3 Terms and definitions

For the purposes of this document, the terms and definitions given in IEC TS 61836, IEC 62934, IEC TS 62786 series, and the following apply.

ISO and IEC maintain terminology databases for use in standardization at the following addresses:

  • IEC Electropedia: available at https://www.electropedia.org/
  • ISO Online browsing platform: available at https://www.iso.org/obp

3.1 battery energy storage system

BESS electrical energy storage system with an accumulation subsystem based on batteries with secondary cells Note 1 to entry: Battery energy storage systems include flow battery energy systems. [SOURCE: IEC 60050-631:2024]

3.2 power conversion equipment

PCE electrical device converting one kind of electrical power from a voltage or current source into another kind of electrical power with respect to voltage, current and frequency [SOURCE: IEC 62109-1:2010, 3.66]

3.3 step response time

for a step response the duration of the time interval between the instant of the step change of an input variable and the instant when the output variable reaches for the first time a specified percentage of the difference between the final and the initial steady-state value Note: See Figure 2 [SOURCE: IEC 60050-351:2013, 351-45-36]

3.4 settling time

for a step response the duration of the time interval between the instant of the step change of an input variable and the instant, when the difference between the step response and their steady-state value remains smaller than the transient value tolerance Note: See Figure 2 [SOURCE: IEC 60050-351:2013, 351-45-37]

3.5 overshoot

for a step response of a transfer element the maximum transient deviation from the final steady-state value of the output variable, usually expressed in percent of the difference between the final and the initial steady-state values and for reference-variable step response or disturbance-variable step response of a control system the maximum transient deviation from the desired value Note: See Figure 2

oSIST prEN IEC 63409-6:2026

[SOURCE: IEC 60050-351:2013, 351-45-37]

3.6 dead time

in a dead-time element the duration of the time interval by which the output variable is shifted relative to the input variable Note: See Figure 2 [SOURCE: IEC 60050-351:2013, 351-50-30]

3.7 tolerance band

tolerance limit with stabilized power supplies the range of steady-state values of a stabilized output quantity lying between specified limits of deviation from a preset value, e.g. a nominal value Note: See Figure 2 [SOURCE: IEC 60050-551:1998, 551-19-07]

Key 1) For periodic behaviour 2) For aperiodic behaviour u Input variable U Initial value of the input variable

U Step height of the input variable s v Output variable V , V Steady-state values before and after application of the step 0 ∞

oSIST prEN IEC 63409-6:2026

Overshoot (maximum transient deviation from the final steady-state value) m 2・Δv Tolerance band s T Step response time sr T Settling time s T Dead time t [SOURCE: IEC 60050-351: 2013, 351-45-36] Figure 2 – Example of step response

4 General requirements

4.1 General conditions for testing

4.1.1 Sequence of tests

The test may be performed in any order unless otherwise specified in this document. It is not necessary to use the same sample for all tests unless otherwise specified in this document.

4.1.2 Test equipment conditions

Examples of the test equipment such as external power supplies and test instruments are described in Annex A.

4.1.3 Manufacturer’s stated tolerance

The tolerance bands for ac voltage, frequency, active power, reactive power and the time measurements can be subject to local regulations. If not, the manufacturer of the PCE under evaluation shall state the tolerance.

4.1.4 Required setting for EUT (equipment under test)

All the grid support functions, except being tested function, should be disabled throughout the test. If any one of the grid support functions is essential to perform the test, it is permissible to enable it. In that case, it shall be written in the test report as remark that the specific function was enabled during the test because it was essential to complete the test. Maximum power point tracking (MPPT) and DC power supply shall be configured as written in 4.2.

4.1.5 PCE firmware used during the test

The versions of the PCE firmware used during the test shall be recorded in the test report.

4.2 Test setup

During testing, the EUT’s DC and AC ports shall be connected to external DC and AC power supplies according to EUT manufacturer’s instructions. The test circuit diagram with positions of measurement sensors shall be recorded in the test report. Figure 3 shows the typical test setup required for test items described in this document.

Apparent power, active power and reactive power shall be measured at AC ports of EUT. The current measuring instruments at AC port of the EUT shall be installed so that the current flowing from EUT to AC power supply is measured as positive. See Annex B or more detailed definitions of sign conventions for measurements of voltage, current and power in this document.

oSIST prEN IEC 63409-6:2026

The testing of the EUT shall not be influenced by the performance of DC power supply used for the test. Therefore, where the EUT has the capability to disable MPPT control, it is allowed to do so and a DC power supply that is able to provide constant voltage at any required power levels shall be used. A PV simulator may be used provided that the test results are not influenced by any DC instability by the PV simulator. In each case, remarks shall be written in the test report to note the type of the DC power supply or PV simulator used in the test. See Annex C for supplemental information regarding the influences from the PV simulator.

Figure 3 – Example of a test setup

4.3 Parameters used in the tests

This document describes the parameter setting procedure using the Logical node (LN) and Data object (message parameter) written in IEC 61850-7-4, and IEC 61850-7-420. The tests described in this document require parameter setting changes and status monitoring, but it does not matter whether remote communications are used to change or monitor the parameters. It does not mean that information exchange or remote monitoring with logical nodes specified in IEC 61850 shall be applied to evaluate the performance of functions. Date objects, or parameters, are used to describe test procedures.

The monitoring parameters for status of PCE are shown in Table 1, and measured value of PCE are shown in Table 2. Manufacturer shall declare the parameters before starting the tests. Table 1 – Status of PCE IEC 61850 Item Standard LN message parameter Description CSWI Pos.stVal Circuit breaker / switch Switch controller IEC 61850-7-4 position Table 2 – Measured values of PCE IEC 61850 Item Standard LN message parameter Description AC voltage MMXU PPV.phsAB / "PPV: Phase to Phase PNV.phsA Voltage

PNV: Phase to Neutral Voltage" IEC 61850-7-4 PPV.phsBC / "PPV: Phase to Phase PNV.phsB Voltage PNV: Phase to Neutral Voltage"

oSIST prEN IEC 63409-6:2026

PPV.phsCA / "PPV: Phase to Phase PNV.phsC Voltage PNV: Phase to Neutral Voltage" AC current A.phsA phase current A.phsB phase current A.phsC phase current Apparent power TotVA The total apparent power in a three-phase circuit [VA].

VA.phsA Phase A apparent power VA.phsB Phase B apparent power VA.phsC Phase C apparent power Active power TotW The total Active power in a three-phase circuit [W].

W.phsA Phase A active power W.phsB Phase B active power W.phsC Phase C active power Reactive power TotVAr The total Reactive power in a three-phase circuit [VAr].

VAr.phsA Phase A reactive power VAr.phsB Phase B reactive power VAr.phsC Phase C reactive power Power factor TotPF The total power factor in a three-phase circuit Frequency Hz Frequency [Hz].

AC voltage MMXN Vol Non-phase-related AC rms voltage.

AC current Amp Non-phase-related AC rms current.

Apparent power VolAmp Non-phase-related AC apparent power.

Active power Watt Non-phase-related AC real power.

Reactive power VolAmpr Non-phase-related AC reactive power.

Average power factor in Power factor PwrFact a three-phase circuit.

Frequency Hz Frequency [Hz].

DC voltage MMDC Vol DC voltage.

DC current Amp DC current.

DC power Watt DC power.

5 Test procedures

5.1 Test items

Table 3 shows test items specified in this document. The test items are aligned with IEC TS 62786-1, which specifies technical requirements for distributed energy resources (DER) connected to an electric power network, and IEC 61850-7-420, which defines information models for DER.

oSIST prEN IEC 63409-6:2026

Table 3 – Test items and relations to IEC TS 62786-1 and information models IEC 63409-6 IEC TS62786-1 Information model

5.2.2 Active power control 4.11 Ceasing and reduction of active power on DWGC

set point

5.2.3 Change of maximum active 4.11 Ceasing and reduction of active power on DWMX

power configuration set point

5.2.4.1 Constant reactive power 4.7.3 Reactive power control modes DVAR

control

5.2.4.2 Constant power factor 4.7.3 Reactive power control modes DFPF

control

5.3 Response control against grid 4.7.3 Reactive power control modes DWPF

variation (Power - power factor control)

5.3 Response control against grid 4.7.3 Reactive power control modes DWVR

variation (Power – reactive power control)

5.3 Response control against grid 4.6 Active power response to frequency DHFW/DLFW

variation (Frequency – watt control) deviation

5.3 Response control against grid 4.7.4 Voltage related active power reduction DVWC

variation (Voltage – watt control)

5.3 Response control against grid 4.7.2 Voltage support by reactive power DVVR

variation (Voltage – var control) 4.7.5 Voltage related reactive power response

5.2 Constant power control

5.2.1 General

This subclause 5.2 describes following test items for constant power control. - Active power control - Change of maximum active power configuration - Reactive power control - Constant reactive power control - Constant power factor control

5.2.2 Active power control
5.2.2.1 General

This subclause 5.2.2 describes how to verify whether the active power output tracks the set value or commanded value of the active power control.

5.2.2.2 Procedure

Minimum required parameters for active power control are shown in Table 4. Table 4 – Minimum required parameters for active power control IEC 61850 Item Standard LN message parameter Description Switch controller IEC 61850-7-4 CSWI Pos.ctlVal Circuit breaker / switch position Enabling 1 (on): The application IEC 61850-7-420 DWGC Mod.ctlVal function represented by the LN works.

oSIST prEN IEC 63409-6:2026

5 (off): The application represented by the LN does not work.

Active power Active power setpoint setting as a WSptPct setpoint percentage of Wmax.

Use ramp rates Use ramp rates limit. True = RmpRteUse limited to ramp rates ; False = limit Not limited to ramp rates Value of ramp Maximum ramp up rate during generating rate (discharging)/injecting.

RpuMax Ramp rate as percentage of WMax or VArMax or AMax per second.

Maximum ramp down rate during generating (discharging)/injecting.

RpdMax Ramp rate as percentage of WMax or VArMax or AMax per second.

a) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

b) Set parameter of PCE “DWGC.Mod.ctlVal” with “1”, and “DWGC.RmpRteUse” with True. c) Set parameter of PCE “DWGC.RpuMax” and “DWGC.RpdMax” with the maximum value. d) Set parameter of PCE “DWGC.WSptPct” with 80 %.

e) Set parameter of PCE “CSWI.Pos.ctlVal” with True.

f) Measure active power at the AC power ports.

g) Set parameter of PCE “DWGC.WSptPct” with 100 %.

h) Measure active power at the AC power ports.

i) Set parameter of PCE “DWGC.WSptPct” with 80 %.

j) Measure active power at the AC power ports.

k) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

l) Set parameter of PCE “DWGC.RpuMax” and “DWGC.RpdMax” with the minimum value, then repeat d) to k).

5.2.2.2.1 Criteria The error between the parameter of PCE and the detected value of the measuring device (“MMXU.TotW” or “MMXN.Watt”) is within the allowable range declared by the manufacturer.

5.2.3 Maximum active power control
5.2.3.1 General

This subclause 5.2.3 describes how to verify whether active power tracks the set value or commanded value of the maximum active power control.

5.2.3.2 Procedure

Minimum required parameters for active power control are shown in Table 5.

oSIST prEN IEC 63409-6:2026

Table 5 – Minimum required parameters for maximum active power control IEC 61850 Item Standard LN message parameter Description Switch controller IEC 61850-7-4 CSWI Pos.ctlVal Circuit breaker / switch position 1 (on): The application represented by the LN works.

Enabling function Mod.ctlVal 5 (off): The application represented IEC 61850-7-420 DWMX by the LN does not work.

Maximum active Maximum active power setting as WMaxSptPct power setting percentage value a) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

b) Set parameter of PCE “DWMX.Mod.ctlVal” with “1”.

c) Set parameter of PCE “DWMX.WMaxSptPct” with 80 %.

d) Set parameter of PCE “CSWI.Pos.ctlVal” with True.

e) Measure active power at the AC power ports.

f) Set parameter of PCE “DWMX.WMaxSptPct” with 100 %.

g) Measure active power at the AC power ports.

h) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

5.2.3.3 Criteria

The error between the parameter of PCE and the detected value of the measuring device (“MMXU.TotW” or “MMXN.Watt”) is within the allowable range declared by the manufacturer.

5.2.4 Reactive power control
5.2.4.1 Constant reactive power control

5.2.4.1.1 General This subclause 5.2.4.1 describes how to verify whether reactive power tracks the set value or commanded value of the reactive power control.

5.2.4.1.2 Procedure Minimum required parameters for reactive power control are shown in Table 6. Table 6 – Minimum required parameters for reactive power control IEC 61850 Item Standard LN message parameter Description Switch controller IEC 61850-7-4 CSWI Pos.ctlVal Circuit breaker / switch position 1 (on): The application represented by the LN works.

Enabling Mod.ctlVal 5 (off): The application function represented by the LN does not work.

IEC 61850-7-420 DVAR Reactive power Target reactive power setpoint setpoint VArTgtSptPct expressed as percent as indicated by VArSetRef.

Use ramp rates limit. True = Use ramp rates RmpRteUse limited to ramp rates ; False = limit Not limited to ramp rates

oSIST prEN IEC 63409-6:2026

Value of ramp Maximum ramp up rate during rate generating (discharging)/injecting.

RpuMax Ramp rate as percentage of WMax or VArMax or AMax per second, Maximum ramp down rate during generating RpdMax (discharging)/injecting . Ramp rate as percentage of WMax or VArMax or AMax per second, Active power Active power setpoint setting as DWGC WSptPct setpoint a percentage of Wmax.

a) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

b) Set parameter of PCE “DVAR.Mod.ctlVal” with “1”, and “DVAR.RmpRteUse” with True. c) Set parameter of PCE “DVAR.RpuMax” and “DVAR.RpdMax” with the maximum value. d) Set parameter of PCE “DVAR.VArTgtSptPct” with 10 %.

e) Set parameter of PCE “DWGC.WSptPct” with 80 %.

f) Set parameter of PCE “CSWI.Pos.ctlVal” with True.

g) Measure reactive power at the AC power ports.

h) Set parameter of PCE “DVAR.VArTgtSptPct” with 0 %.

i) Measure reactive power at the AC power ports.

j) Set parameter of PCE “DVAR.VArTgtSptPct” with 10 %.

k) Measure reactive power at the AC power ports.

l) Set parameter of PCE “CSWI.Pos.ctlVal” with False.

m) Set parameter of PCE “DVAR.RpuMax” and “DVAR.RpdMax” with the minimum value, then repeat d) to l).

5.2.4.1.3 Criteria The error between the parameter of PCE and the detected value of the measuring device (“MMXU.TotVAr” or “MMXN.VolAmpr”) is within the allowable range declared by the manufacturer.

5.2.4.2 Constant power factor control

5.2.4.2.1 General This test aims to evaluate the accuracy of constant power factor control and its time response to changes in output power or AC voltage.

5.2.4.2.2 Procedure Minimum required parameters for constant power factor control are shown in Table 7. Table 7 – Minimum required parameters for constant power factor control IEC 61850 Item Standard LN message parameter Description Switch IEC 61850-7-4 CSWI Pos.ctlVal Circuit breaker / switch position controller 1 (on): The application represented by the LN works.

Enabling IEC 61850-7-420 DFPF Mod.ctlVal function 5 (off): The application represented by the LN does not work.

oSIST prEN IEC 63409-6:2026

Target power Target power factor setting when PFGnTgtSpt factor generating Use ramp rates limit. True = limited Use ramp rates to ramp rates ; False = Not limited RmpRteUse limit to ramp rates Maximum ramp up rate during generating (discharging)/injecting.

RpuMax Ramp rate as percentage of WMax or VArMax or AMax per second.

...