Wind turbines - Part 25-1: Communications for monitoring and control of wind power plants - Overall description of principles and models

Gives an overall description of the principles and models used in the IEC 61400-25 series of standards. The IEC 61400-25 series deals with communications between wind power plant components such as wind turbines and actors such as SCADA Systems. It is designed for a communication environment supported by a client-server model.

Windenergieanlagen - Teil 25-1: Kommunikation für die Überwachung und Steuerung von Windenergieanlagen - Einführende Beschreibung der Prinzipien und Modelle

Eoliennes - Partie 25-1: Communications pour la surveillance et la commande des centrales éoliennes - Description générale des principes et modèles

Sistemi generatorjev vetrne turbine - 25-1. del: Komunikacije za spremljanje in nadzor vetrnih elektrarn - Celoten opis načel in modelov (IEC 61400-25-1:2006)

General Information

Status
Withdrawn
Publication Date
27-Feb-2007
Withdrawal Date
31-Jan-2010
Technical Committee
Drafting Committee
Parallel Committee
Current Stage
9960 - Withdrawal effective - Withdrawal
Start Date
01-Dec-2020
Completion Date
01-Dec-2020

Relations

Buy Standard

Standard
EN 61400-25-1:2007
English language
35 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)


2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.Wind turbines - Part 25-1: Communications for monitoring and control of wind power plants - Overall description of principles and modelsEoliennes - Partie 25-1: Communications pour la surveillance et la commande des centrales éoliennes - Description générale des principes et modelesWindenergieanlagen - Teil 25-1: Kommunikation für die Überwachung und Steuerung von Windenergieanlagen - Einführende Beschreibung der Prinzipien und ModelleTa slovenski standard je istoveten z:EN 61400-25-1:2007SIST EN 61400-25-1:2007en,de27.180Sistemi turbin na veter in drugi alternativni viri energijeWind turbine systems and other alternative sources of energyICS:SLOVENSKI
STANDARDSIST EN 61400-25-1:200701-november-2007

EUROPEAN STANDARD EN 61400-25-1 NORME EUROPÉENNE
EUROPÄISCHE NORM February 2007
CENELEC European Committee for Electrotechnical Standardization Comité Européen de Normalisation Electrotechnique Europäisches Komitee für Elektrotechnische Normung
Central Secretariat: rue de Stassart 35, B - 1050 Brussels
© 2007 CENELEC -
All rights of exploitation in any form and by any means reserved worldwide for CENELEC members.
Ref. No. EN 61400-25-1:2007 E
ICS 27.180
English version
Wind turbines -
Part 25-1: Communications for monitoring
and control of wind power plants -
Overall description of principles and models (IEC 61400-25-1:2006)
Eoliennes -
Partie 25-1: Communications
pour la surveillance et la commande
des centrales éoliennes - Description générale
des principes et modèles (CEI 61400-25-1:2006)
Windenergieanlagen -
Teil 25-1: Kommunikation
für die Überwachung und Steuerung
von Windenergieanlagen -
Einführende Beschreibung
der Prinzipien und Modelle (IEC 61400-25-1:2006)
This European Standard was approved by CENELEC on 2007-02-01. CENELEC members are bound to comply with the CEN/CENELEC Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the Central Secretariat or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation under the responsibility of a CENELEC member into its own language and notified to the Central Secretariat has the same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Cyprus, the Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the Netherlands, Norway, Poland, Portugal, Romania, Slovakia, Slovenia, Spain, Sweden, Switzerland and the United Kingdom.

Foreword The text of document 88/274/FDIS, future edition 1 of IEC 61400-25-1, prepared by IEC TC 88, Wind turbines, was submitted to the IEC-CENELEC parallel vote and was approved by CENELEC as EN 61400-25-1 on 2007-02-01. The following dates were fixed: – latest date by which the EN has to be implemented
at national level by publication of an identical
national standard or by endorsement
(dop)
2007-11-01 – latest date by which the national standards conflicting
with the EN have to be withdrawn
(dow)
2010-02-01 Annex ZA has been added by CENELEC. __________ Endorsement notice The text of the International Standard IEC 61400-25-1:2006 was approved by CENELEC as a European Standard without any modification. __________

- 3 - EN 61400-25-1:2007
Annex ZA
(normative)
Normative references to international publications with their corresponding European publications
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
NOTE
When an international publication has been modified by common modifications, indicated by (mod), the relevant EN/HD applies.
Publication Year Title EN/HD Year
IEC 61400-12-1 -1) Wind turbines -
Part 12-1: Power performance measurements of electricity producing wind turbines EN 61400-12-1 20062)
IEC 61400-25 Series Wind turbines -
Part 25: Communications for monitoring and control of wind power plants EN 61400-25 Series
IEC 61850-7-1 2003 Communication networks and systems in substations -
Part 7-1: Basic communication structure for substation and feeder equipment - Principles and models EN 61850-7-1 2003
IEC 61850-7-2 2003 Communication networks and systems in substations -
Part 7-2: Basic communication structure for substation and feeder equipment - Abstract communication service interface (ACSI) EN 61850-7-2 2003
IEC 61850-7-3 2003 Communication networks and systems in substations -
Part 7-3: Basic communication structure for substation and feeder equipment - Common data classes EN 61850-7-3 2003
IEC 61850-7-4 2003 Communication networks and systems in substations -
Part 7-4: Basic communication structure for substation and feeder equipment - Compatible logical node classes and data classes EN 61850-7-4 2003
IEC 61850-8-1 2004 Communication networks and systems in substations -
Part 8-1: Specific Communication Service Mapping (SCSM) - Mappings to MMS (ISO 9506-1 and ISO 9506-2) and
to ISO/IEC 8802-3 EN 61850-8-1 2004
1) Undated reference. 2) Valid edition at date of issue.

Publication Year Title EN/HD Year ISO/IEC 7498-1 1994 Information technology - Open systems interconnection - Basic reference model: The basic model EN ISO/IEC 7498-11995

INTERNATIONAL STANDARD IEC61400-25-1 First edition2006-12 Wind turbines – Part 25-1: Communications for monitoring
and control of wind power plants – Overall description of principles and models © IEC 2006

Copyright - all rights reserved No part of this publication may be reproduced or utilized in any form or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from the publisher. International Electrotechnical Commission,
3, rue de Varembé, PO Box 131, CH-1211 Geneva 20, SwitzerlandTelephone: +41 22 919 02 11 Telefax: +41 22 919 03 00 E-mail: inmail@iec.ch
Web: www.iec.ch V For price, see current cataloguePRICE CODE
Commission Electrotechnique InternationaleInternational Electrotechnical Commission

– 2 – 61400-25-1 © IEC:2006(E) CONTENTS FOREWORD.3 INTRODUCTION.5
1 Scope.7 2 Normative references.8 3 Terms and definitions.9 4 Abbreviated terms.13 5 Overall description of the IEC 61400-25 series.13 5.1 General.13 5.2 Top-down view on wind power plants.14 5.3 Generic requirements on communication.15 5.4 Communication model of the IEC 61400-25 series.17 6 Wind power plant information model.20 6.1 General.20 6.2 Information modelling methodology.20 7 Wind power plant information exchange model.24 7.1 General.24 7.2 Information exchange modelling methodology.24 8 Mapping to communication protocols.30 8.1 General.30 8.2 Architecture of the mappings.31 8.3 Mapping of the wind power plant information model.31
Figure 1 – Conceptual communication model of the IEC 61400-25 series.8 Figure 2 – Data processing by the server (conceptual).18 Figure 3 – Modelling approach (conceptual).19 Figure 4 – Structure of wind power plant information model.22 Figure 5 – Client and server role.24 Figure 6 – IEM Service models.25 Figure 7 – Conceptual information exchange model for a wind power plant.26 Figure 8 – IEM service model with examples.28 Figure 9 – Sequence diagram.29 Figure 10 – ACSI mapping to communication stacks/profiles.30 Figure 11 – Communication profiles.31
Table 1 – Operational functions.16 Table 2 – Management functions.17 Table 3 – Wind power plant information categories.21 Table 4 – General table structure of a logical node (LN).23 Table 5 – Data class attributes in a logical node.23 Table 6 – Service table.28

61400-25-1 © IEC:2006(E) – 3 – INTERNATIONAL ELECTROTECHNICAL COMMISSION ____________
WIND TURBINES –
Part 25-1: Communications for monitoring
and control of wind power plants – Overall description of principles and models
FOREWORD 1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising all national electrotechnical committees (IEC National Committees). The object of IEC is to promote international co-operation on all questions concerning standardization in the electrical and electronic fields. To this end and in addition to other activities, IEC publishes International Standards, Technical Specifications, Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested in the subject dealt with may participate in this preparatory work. International, governmental and non-governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely with the International Organization for Standardization (ISO) in accordance with conditions determined by agreement between the two organizations. 2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international consensus of opinion on the relevant subjects since each technical committee has representation from all interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any misinterpretation by any end user. 4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications transparently to the maximum extent possible in their national and regional publications. Any divergence between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in the latter. 5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any equipment declared to be in conformity with an IEC Publication. 6) All users should ensure that they have the latest edition of this publication. 7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and members of its technical committees and IEC National Committees for any personal injury, property damage or other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is indispensable for the correct application of this publication. 9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of patent rights. IEC shall not be held responsible for identifying any or all such patent rights. International Standard IEC 61400-25-1 has been prepared by IEC technical committee 88: Wind turbines.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2. The text of this standard is based on the following documents: FDIS Report on voting 88/274/FDIS 88/280/RVD
Full information on the voting for the approval of this standard can be found in the report on voting indicated in the above table. A list of all parts of the IEC 61400 series, under the general title Wind turbines can be found on the IEC website.

– 4 – 61400-25-1 © IEC:2006(E)
The committee has decided that the contents of this publication will re
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.