IEC 60352-5:2012/COR1:2014
(Corrigendum)Corrigendum 1 - Solderless connections - Part 5: Press-in connections - General requirements, test methods and practical guidance
Corrigendum 1 - Solderless connections - Part 5: Press-in connections - General requirements, test methods and practical guidance
Corrigendum 1 - Connexions sans soudure - Partie 5: Connexions insérées à force - Exigences générales, méthodes d'essai et guide pratique
General Information
Relations
Standards Content (Sample)
IEC 60352-5
(4th edition – 2012)
SOLDERLESS CONNECTIONS –
Part 5: Press-in connections –
General requirements, test methods and practical guidance
CO RRI G E NDUM 1
Replace existing Table 5 by the following new Table 5 :
Table 5 – Qualification test schedule – Test group C
Test Measurement to be performed Requirement
Test phase
Test No. of
Title Subclause Title Subclause
IEC 60512
CP1 Mounting 5.3.2.2
CP2 if applicable Replacement 5.2.2.6
CP3 Contact resistance 2a 5.2.3.1
– millivolt level
method
CP4 5.2.4.2 11d
Rapid change of
temperature
CP5 Climatic 5.2.4.3 11a
sequence
CP6 Dry heat 5.2.4.4 11i
CP7 No required tests and measurements
CP8 Contact resistance 2a 5.2.3.1
– millivolt level
method
a)
CP9 5.2.2.3 Push-out force 5.2.2.3 ,
minimum push-
out force per
termination
according to
4.6 e)
a)
The test for push-out force has to be performed on 14 of the 200 terminations, 7 of them out of range a and 7 of
them out of range b.
Figure 9, in the bottom section of the flow chart, last column, delete:
"– Flowing mixed gas corrosion test"